IRS Emergency Planning: Headquarters Plans Supported Response to 2006 Flooding, but Additional Guidance Could Improve All Hazard Preparedness

GAO-07-579 April 16, 2007
Highlights Page (PDF)   Full Report (PDF, 31 pages)   Accessible Text   Recommendations (HTML)

Summary

On June 25, 2006, the Internal Revenue Service (IRS) headquarters building suffered flooding during a period of record rainfall and sustained extensive damage to its infrastructure. IRS officials ordered the closure of the building until December 2006 to allow for repairs to be completed. IRS headquarters officials reported activating several of the agency's emergency operations plans. Within 1 month of the flood, over 2,000 employees normally assigned to the headquarters building were relocated to other facilities throughout the Washington, D.C., metropolitan area. GAO was asked to report on (1) how IRS emergency operations plans address federal guidance related to continuity planning and (2) the extent to which IRS emergency operations plans contributed to the actions taken by IRS officials in response to the flood. To address these objectives, GAO analyzed federal continuity guidance, reviewed IRS emergency plans, and interviewed IRS officials.

The IRS headquarters emergency operations plans that GAO reviewed--the headquarters Continuity of Operations (COOP) plan, Incident Management Plan, and three selected business resumption plans--collectively addressed several of the general elements identified within federal continuity guidance for all executive branch departments and agencies. For example, the plans adequately identified the people needed to continue performing essential functions. However, other elements were not addressed or were addressed only in part. Specifically, IRS had two separate lists of essential functions--critical business processes and essential functions for IRS leadership--within its plans, but prioritized only one of the lists. Furthermore, although the COOP plan outlined provisions for tests, training, and exercises, none of the other plans GAO reviewed outlined the need to conduct such activities. While IRS provided overall guidance to its business units on their business resumption plans, the guidance was inconsistent with the federal guidance on several elements, including the preparation of resources and facilities needed to support essential functions and requirements for regular tests, training, and exercises. The IRS Incident Management Plan was particularly useful in establishing clear lines of authority and communications in response to the flooding. Unit-level business resumption plans GAO reviewed contributed to a lesser extent, and the headquarters COOP plan was not activated because of conditions particular to the 2006 flood. Specifically, damage to the building was limited to the basement and subbasement levels, and employees were able to enter the building to retrieve equipment and assets. In addition, alternate work space was available for all employees within a relatively short period, reducing the importance of identifying critical personnel. While its plans helped guide IRS's response to the conditions that resulted from the flood, in more severe emergency events, conditions could be less favorable to recovery. Consequently, unless IRS fills in gaps in its guidance and plans, it lacks assurance that the agency is adequately prepared to respond to the full range of potential disruptions.



Recommendations

Our recommendations from this work are listed below with a Contact for more information. Status will change from "In process" to "Implemented" or "Not implemented" based on our follow up work.

Director:
Team:
Phone:
Bernice Steinhardt
Government Accountability Office: Strategic Issues
(202) 512-6543


Recommendations for Executive Action


Recommendation: To strengthen the ability of IRS to respond to the full range of potential disruptions to essential operations, the Commissioner of Internal Revenue should revise IRS internal emergency planning guidance to fully reflect federal guidance on the elements of a viable continuity capability, including the identification and prioritization of essential functions; the preparation of necessary resources and alternate facilities; and the regular completion of tests, training, and exercises of continuity capabilities.

Agency Affected: Department of the Treasury: Internal Revenue Service

Status: In process

Comments: IRS officials stated that a gap analysis was conducted and a crosswalk document was completed as planned, but that development of the new IRM on Business Continuity Planning is taking longer than expected. More time is needed for the review and incorporation of Business Units' feedback to the draft, final vetting of the report, finalization, and publishing. The IRS Emergency Management and Preparedness Steering Committee (EMPSC) is scheduled to address this topic during the April meeting.

Recommendation: To strengthen the ability of IRS to respond to the full range of potential disruptions to essential operations, the Commissioner of Internal Revenue should revise IRS emergency plans in accordance with the new internal guidance.

Agency Affected: Department of the Treasury: Internal Revenue Service

Status: In process

Comments: As a result of the first recommendation being delayed, IRS officials stated that they will also delay this corrective action to allow more time for development of the new IRM on Business Continuity Planning. The revision of IRS emergency plans will be dependent upon final guidance set forth in the new IRM.