This is the accessible text file for GAO report number GAO-03-653T 
entitled 'Federal Aviation Administration: Reauthorization Provides 
Opportunities to Address Key Agency Challenges' which was released on 
April 10, 2003.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Testimony:



Before the Committee on Commerce, Science, and Transportation, U.S. 

Senate:



United States General Accounting Office:



GAO:



For Release on Delivery Expected at 9:30 a.m. EDT:



Thursday, April 10, 2003:



Federal Aviation Administration:



Reauthorization Provides Opportunities to Address Key Agency 

Challenges:



Statement of Gerald L. Dillingham

Director, Civil Aviation Issues:



GAO-03-653T:



GAO Highlights:



Highlights of GAO-03-653T, a testimony before the Senate Committee on 

Commerce, Science, and Transportation



Why GAO Did This Study:



Much has changed since the Wendell H. Ford Aviation Investment and 

Reform Act for the 21st Century (AIR-21) reauthorized the Federal 

Aviation Administration’s (FAA) programs 3 years ago.  At that time, 

air traffic was increasing, and concerns about congestion and flight 

delays were paramount.  Since then, the downturn in the nation’s 

economy, the terrorist attacks of September 11, 2001, and, most 

recently, the war in Iraq have taken a heavy toll on aviation. Analysts 

nonetheless expect the demand for air travel to rebound, and the 

nation’s aviation system must be ready to accommodate the projected 

growth safely and securely.  



The current reauthorization of FAA’s programs provides an opportunity 

for the Congress and the administration to focus on challenges in 

increasing aviation capacity, efficiency, and safety and in controlling 

aviation program costs.  



What GAO Found:



Increasing capacity and service in the national airspace system poses 

several challenges.  While airports currently receive enough funding to 

cover FAA’s estimate of their planned capital development costs, a 

declining surplus in the trust fund that helps to support development 

and the need to spend up to $5 billion over the next 5 years for 

security-related capital improvements make the financial outlook for 

the next 5 to 8 years uncertain. Runway development, the principal 

means of increasing capacity, is now taking 10 to 14 years to complete, 

in large part because of time-consuming environmental reviews and 

community concerns.  Providing air service for small communities is 

also becoming more difficult as costs increase and passenger ticket 

revenues decline.  Intermodal alternatives may hold promise.



Efforts to improve the efficiency of the national airspace system by 

modernizing the air traffic control system face challenges despite 

actions taken by the Congress and the administration to eliminate the 

cost overruns, schedule delays, and performance shortfalls that have 

plagued FAA’s modernization efforts.  Overall, FAA is improving its 

management of the air traffic modernization program and has implemented 

some systems, but key projects continue to experience problems.   



To enhance aviation safety, FAA and the aviation industry have 

undertaken an initiative to reduce the fatal accident rate, and FAA is 

working to strengthen its safety inspections of airlines’ operations.  

Interagency coordination of aviation safety and aviation security 

activities has emerged as a challenge with the transfer of aviation 

security responsibilities from FAA to the Transportation Security 

Administration.  



FAA faces challenges in implementing controls over its costs.  

Although it has partially implemented a new cost accounting system that 

enables it to track 70 percent of its air traffic services costs, this 

system lacks internal controls over $3.1 billion in labor costs, 

according to the Department of Transportation’s Inspector General.  

Congressional oversight is important to ensure that FAA implements 

controls and spends its resources effectively.



What GAO Recommends:



This testimony does not contain recommendations.  However, GAO reports 

containing relevant recommendations are listed among the Related GAO 

Products following the testimony.



www.gao.gov/cgi-bin/getrpt?GAO-03-653T.



To view the full report, including the scope

and methodology, click on the link above.

For more information, contact Gerald L. Dillingham at (202) 512-2834 or 

dillinghamg@gao.gov.



[End of report]



Mr. Chairman and Members of the Committee:



We are here today to discuss the reauthorization of federal aviation 

programs and issues relevant to ensuring the safe and efficient 

operation of the national airspace system.[Footnote 1] Much has changed 

since the Wendell H. Ford Aviation Investment and Reform Act for the 

21st Century (AIR-21) reauthorized the Federal Aviation 

Administration’s (FAA) programs 3 years ago. At that time, as you know, 

air traffic was increasing, and concerns about congestion and flight 

delays were paramount. Since then, the downturn in the nation’s 

economy, the terrorist attacks of September 11, 2001, and, most 

recently, the war in Iraq have taken a heavy toll on aviation. Flights 

that were once filled are now being canceled for lack of business, and 

major air carriers are in serious financial difficulty. Furthermore, as 

the federal budget deficit has increased, competition for federal 

resources has intensified. Analysts nonetheless expect the demand for 

air travel to rebound, and the nation’s aviation system must be ready 

to accommodate the projected growth safely and securely. The current 

slowdown in the economy and in the aviation industry has created a 

window of opportunity to prepare for this growth without the pressures 

of congestion and flight delays. My statement today focuses on the 

challenges that the Congress, the administration, and FAA face in 

increasing aviation capacity, efficiency, and safety, and maintaining 

controls over costs. My statement is based primarily on our published 

reports, as well as our ongoing work for this Committee discussed in 

the scope and methodology section at the end of the statement.



In summary:



* Increasing capacity and service in the national airspace system poses 

several challenges for the Congress and the administration during this 

reauthorization process. Chief among them is deciding how much of 

airports’ planned capital development should be funded to increase 

capacity and service, as well as improve the efficiency and safety of 

the national airspace system. Funds for airports’ capital development 

have increased over the last 5 years, in part because of increases in 

the federal grant funding provided to airports under the Airport 

Improvement Program. Current funding levels are sufficient to cover 

much of the estimated cost of planned capital development. However, 

future funding levels may be affected by changes in the allocation of 

Airport Improvement Program grant funds and by projected decreases in 

the Airport and Airway Trust Fund, which supports the Airport 

Improvement Program and other FAA accounts. Other challenges include 

building runways expeditiously to increase capacity and providing air 

service to small communities. Runway development now takes 10 to 14 

years, primarily because of time-consuming environmental reviews and 

community concerns. Two federal programs, the Essential Air Service and 

the Small Community Air Service Development Pilot programs, help bring 

air service to small communities, but the costs of this service are 

increasing while passenger ticket revenues are declining. The 

administration is proposing an approach to streamline the environmental 

reviews required for runway development, and intermodal alternatives, 

such as rail or bus service, could provide access to the national air 

transportation system for some small communities.

:



* Efforts to improve the efficiency of the national airspace system by 

modernizing its principal component, the air traffic control system, 

face ongoing challenges despite actions taken by the Congress and the 

administration to eliminate the cost overruns, schedule delays, and 

performance shortfalls that have plagued FAA’s air traffic 

modernization program and led us to designate this program as high 

risk. These actions include granting FAA acquisition and human capital 

flexibilities in 1996 and creating a new, three-component structure to 

improve the oversight, management, and operation of the air traffic 

control system in 2000. Our work has shown that FAA has responded to 

these actions to varying degrees, but more remains to be done. Overall, 

FAA is improving its management of the air traffic modernization 

program and has implemented some systems, but key projects continue to 

experience cost, schedule, and performance problems. Additionally, FAA 

has used its acquisition flexibilities to establish an acquisition 

management system and its human capital flexibilities to fully or 

partially implement human capital reform initiatives. The acquisition 

management system has provided FAA with a structured management 

approach for selecting and controlling its investments, and the human 

capital reform initiatives are affording opportunities for FAA to 

manage its workforce more efficiently. However, in implementing both of 

these reforms, FAA has not yet incorporated important processes or 

elements for evaluating the results of its efforts, modifying these 

efforts as necessary, and holding its managers accountable. Finally, 

one of the three components of the new structure for improving the 

performance of the air traffic control system has been implemented. The 

oversight component, the Air Traffic Services Subcommittee, has been 

meeting since January 2001 and emphasizing performance management, but 

without the management and operating components, the new structure is 

not yet functioning as intended. Completing the implementation of, and 

continuing to improve, these efforts will be important to enhancing the 

efficiency of the air traffic control system.

:



* Important steps have been taken to enhance aviation safety, but some 

challenges remain. Safer Skies, an initiative designed by FAA and the 

aviation industry to reduce the nation’s fatal aviation accident rate 

by 80 percent by 2007, is the centerpiece of these efforts to improve 

aviation safety. This initiative began in 1998, and many preventive 

actions are under way but have not yet been fully implemented. Another 

key effort to improve aviation safety is FAA’s Air Transportation 

Oversight System, which was redesigned to provide more effective 

inspections of the nation’s airline operations. In reporting on this 

system in 1999, we noted that it incorporated important features to 

ensure that airlines have systems to control risks and prevent 

accidents, but that it had encountered startup problems with data 

collection and program guidance.[Footnote 2] Many of these problems 

were not yet fully resolved when the Department of Transportation’s 

Inspector General reported on the inspection system last year.[Footnote 

3] Finally, because of the often vital link between aviation safety and 

aviation security, it will be critical for FAA to ensure that aviation 

safety is maintained as the Department of Homeland Security’s 

Transportation Security Administration implements new security 

enhancements.

:



* With the decline in revenues to the Airport and Airway Trust Fund--

the principal source of funding for most of FAA’s operations, 

facilities and equipment, and grant programs--it is especially 

important that FAA control or reduce costs, run its programs 

efficiently, and detect and prevent fraudulent activities. FAA, 

however, faces challenges in implementing controls over its costs. For 

example, during fiscal year 2000, weaknesses in the internal controls 

over FAA’s purchase card program contributed to $5.4 million in 

improper purchases by FAA employees and over $630,000 in purchases that 

were considered wasteful or questionable. In addition, FAA has 

partially implemented a new cost accounting system that enables it to 

track 70 percent of its air traffic services costs; however, according 

to the Department of Transportation’s Inspector General, this system 

lacks internal controls over $3.1 billion in labor costs. The Inspector 

General further noted that a portion of this system, if implemented as 

designed, could provide workforce data that would be helpful in 

determining how many controllers are needed and where. These data would 

assist FAA in planning for the anticipated retirement of large numbers 

of air traffic controllers in the near and long term.

:



Efforts to Increase Aviation Capacity and Service Face Funding and 

Other Challenges:



During this reauthorization period, the Congress and the administration 

face several key challenges in attempting to increase the capacity of 

the national airspace system and expand service to small communities. 

These challenges include determining (1) how much airport capital 

development is needed, (2) how that development will be funded, (3) how 

assistance for enhancing air service to small communities will be 

provided, and (4) how the current process for enhancing capacity, 

particularly the runway development process, can be expedited.



FAA and the Airport Industry Have Developed Different Estimates of 

Airports’ Planned Capital Development Costs:



FAA and the Airport Council International (ACI), an organization 

representing the airport industry, have developed two different 

estimates of airports’ planned capital development costs that are based 

on two different sets of projects. According to FAA’s estimate, which 

includes only projects that are eligible for Airport Improvement 

Program (AIP) grants, such as runways, taxiways, and noise mitigation 

and noise reduction efforts, the total cost of airport development will 

be about $46 billion, or over $9 billion per year, for 2001 through 

2005. FAA’s estimate is based on the agency’s National Plan of 

Integrated Airport Systems, which FAA published in August 2002. ACI’s 

estimate includes all of the projects in FAA’s estimate, plus other 

planned airport capital projects that may or may not be eligible for 

AIP grants. Projects that are not eligible for AIP funding include 

parking garages, hangars, and expansions of commercial space in 

terminals. ACI estimates a total cost of almost $75 billion, or nearly 

$15 billion per year, for 2002 through 2006. Neither ACI’s nor FAA’s 

estimate includes funding for the terminal modification projects that 

are needed to accommodate the new explosives detection systems required 

to screen checked baggage. ACI estimates that these projects will cost 

about $3 billion to $5 billion over the next 5 years.



Although there is a difference of $6 billion a year between FAA’s and 

ACI’s estimates of planned development costs, both estimates cover 

projects for every type of airport. As table 1 indicates, the estimates 

are identical for all but the large-and medium-hub airports, which are 

responsible for transporting about 90 percent of the traveling public. 

For these airports, ACI’s estimate of planned development costs is 

about twice as large as FAA’s. As the Congress moves forward with 

reauthorizing FAA’s programs, it will have to determine what level of 

planned capital development is appropriate to increase the capacity, 

efficiency, and safety of the national airspace system.



Table 1: Average Annual Planned Development Costs Estimated by FAA and 

ACI, by Airport Type, 2001-2006:



Dollars in millions.



Large hub;   Number of airports: 31;  

Estimated average annual costs: FAA: $4,855;  

Estimated average annual costs: ACI: $8,554.



Medium hub;   Number of airports: 37;  

Estimated average annual costs: FAA: 1,073;  

Estimated average annual costs: ACI: 3,109.



Small hub;   Number of airports: 71;  

Estimated average annual costs: FAA: 675;  

Estimated average annual costs: ACI: 675.



Nonhub;   Number of airports: 280;  

Estimated average annual costs: FAA: 807;  

Estimated average annual costs: ACI: 807.



Other commercial service;   Number of airports: 124; 

Estimated average annual costs: FAA: 142; 

Estimated average annual costs: ACI: 142.



Reliever;   Number of airports: 260;  

Estimated average annual costs: FAA: 526;  

Estimated average annual costs: ACI: 526.



General aviation;   Number of airports: 2,558; 

Estimated average annual costs: FAA: 1,167; 

Estimated average annual costs: ACI: 1,167.



Total;   Number of airports: 3,364;  

Estimated average annual costs: FAA: $9,245;  

Estimated average annual costs: ACI: $14,980.



Source: FAA and ACI.



[End of table]



Airports’ Ability to Fund Planned Capital Development Has Improved:



Over the past 5 years, the ability of airports--especially smaller 

airports--to fund their capital development projects has improved, in 

part because AIR-21 increased both the total amount of funding for AIP 

grants and the proportion of AIP funding that went to smaller airports. 

In 1998, we reported that large-and medium-hub airports could fund 

about 79 percent of their planned capital development and smaller 

airports could fund about 52 percent of their planned capital 

development if they continued to receive funding at prior years’ 

levels. In 2003, the funding ability of both groups of airports 

increased. As shown in figure 1, large-and medium-hub airports could 

fund about 80 percent of their planned capital development, an increase 

of 1 percentage point, while smaller airports could fund about 73 

percent of their planned capital development, an increase of 21 

percentage points, assuming the continuation of prior years’ funding 

levels.[Footnote 4]



Figure 1: Ability of Smaller and Larger Airports to Fund Estimated 

Planned Capital Development in 1998 and 2003:



[See PDF for image]



[End of figure]





The primary reason why smaller airports are able to fund 73 percent of 

their planned development in 2003, rather than the 52 percent we 

reported in 1998, is that they have benefited significantly from the 

increases in AIP grants, which are a larger source of funding for 

smaller airports than for larger airports. In addition, smaller 

airports have received an increasing share of AIP grants because of 

statutorily required changes in the distribution of AIP grants. For 

example, in AIR-21, the Congress increased the funding for two grant 

categories that primarily or exclusively benefit smaller airports--the 

state apportionment fund and the small airport fund--and created 

general aviation entitlement grants, which also benefit smaller 

airports. The Senate’s and the administration’s reauthorization 

proposals continue to support increases in the amount of AIP grant 

funding awarded to smaller airports. In spite of the progress that has 

been made, over 25 percent of planned capital development is not 

funded. The Congress needs to be mindful of this situation as it 

considers reauthorization issues.



Changes in the Use of AIP Grants and Additional Decreases in Trust Fund 

Revenue Could Affect Airports’ Future Funding Ability:



The use of AIP grants to fund new airport security requirements and 

additional decreases in the Airport and Airway Trust Fund’s[Footnote 5] 

revenues could affect the future ability of airports to fund their 

planned capital development. In recent fiscal years, airports obtained 

most of their funding for planned capital development from bonds, AIP 

grants, and passenger facility charges.[Footnote 6] Because the Trust 

Fund is the source of funding for AIP grants, its financial condition 

is important to the ability of airports to fund capital development, 

and decreases in its revenues could reduce the amount of funding for 

airport planned capital development. Reductions in AIP grant funds 

would have the greatest effect on smaller airports, which derive most 

of their planned capital development funding from AIP grants, whereas 

large-and medium-hub airports derive most of their funding from bonds.



Continued Use of AIP Grant Funds for Security Projects Would Reduce 

Funding for Capacity Projects:



According to FAA officials, FAA plans to allocate the same amount of 

AIP grant funds for new security projects at airports in fiscal year 

2003 as it allocated in fiscal year 2002--$561 million. As we reported 

in October 2002,[Footnote 7] the use of AIP grants for security 

projects reduced the funding available for other airport development 

projects, such as projects to bring airports up to FAA’s design 

standards and reconstruction projects, and caused FAA to defer three 

letter-of-intent payments totaling $28 million to three airports until 

fiscal year 2003 or later.[Footnote 8] Among the key reauthorization 

issues facing the Congress are how the funding needs for capacity and 

security projects will be balanced and how the new security 

requirements, including the terminal modification projects that are 

expected to cost $3 billion to $5 billion, will be funded.



Additional Declines in Airport and Airway Trust Fund Revenue Could Also 

Affect Amount of AIP Grant Funds Available for Future Capital 

Development:



The future ability of airports to fund planned capital development may 

be affected by uncertainties surrounding the condition of the Trust 

Fund. As you know, the Trust Fund is the source of funding not only for 

AIP grants but also for other FAA accounts, including facilities and 

equipment; research, engineering, and development; and most operations. 

Revenues to the Trust Fund come from several types of taxes, including 

passenger ticket and fuel taxes. Although projections made in November 

2002 indicate that the Trust Fund will be able to meet its traditional 

obligations over the next 10 years, the financial outlook for the next 

5 to 8 years is uncertain, in part, because passenger traffic has 

decreased with the slowdown in the economy. Current estimates indicate 

that between fiscal year 2003 and fiscal year 2007, the Trust Fund’s 

2002 uncommitted balance of about $4.8 billion will decline by about $4 

billion, leaving a balance of less than a billion dollars. In addition, 

if revenues fall short of current projections, the Trust Fund’s 

uncommitted balance may be zero. Under this scenario, AIP grants and 

other FAA accounts supported by the Trust Fund could potentially 

receive less funding, and the Congress and the administration would 

have to decide how to offset the potential decreases.



As figure 2 shows, from 1999 through 2002, revenues to the Trust Fund 

have declined, while expenditures from the fund have increased. 

Revenues fell from about $11 billion in 1999 to almost $10 billion in 

2002, a decrease of almost 10 percent. During the same period, 

expenditures increased from about $8 billion to about $12 billion, an 

increase of about 47 percent. As a result, the uncommitted balance 

(surplus) has fallen by nearly 35 percent, from $7 billion in 1999 to 

almost $5 billion in 2002.



Figure 2: Financial Condition of the Airport and Airway Trust Fund:



[See PDF for image]



[End of figure]



The major reason for the decline in Trust Fund revenues was a drop in 

passenger ticket tax revenues, which fell by nearly $1.2 billion from 

1999 to 2002. The increase in Trust Fund expenditures from 1999 through 

2002, amounting to almost $4 billion, can be attributed primarily to 

increases in funding for FAA operations and AIP grants, which accounted 

for about 47 percent and about 34 percent of the total increase, 

respectively.



In addition, the administration is proposing actions that would further 

reduce the Trust Fund balance over the next several years. 

Specifically, the President’s fiscal year 2004 budget request would 

increase the percentage of FAA operations funded by the Trust Fund from 

75 percent[Footnote 9] to 79 percent. The decrease in Trust Fund 

revenues and increase in Trust Fund expenditures presents an issue that 

the Congress may want to address as it moves forward with the 

reauthorization process.



Resolving Challenges to Runway Development Remains an Important Issue:



While there is a general consensus that building runways is one of the 

most effective ways to increase capacity in the national airspace 

system, resolving the challenges associated with planning and building 

runways is an important issue that is directly related to enhancing 

capacity. In December 2002, FAA published the most recent version of 

its Operational Evolution Plan, a 10-year plan to increase the capacity 

and efficiency of the national airspace system, primarily by building 

runways.[Footnote 10] Figure 3 illustrates how capacity will be 

increased at one airport through runway construction.



Figure 3: Increasing Airport Capacity through Runway Development:



[See PDF for image]



[End of figure]





If successfully carried out, FAA’s Operational Evolution Plan would 

substantially increase capacity and improve efficiency. However, FAA 

faces several challenges in implementing the plan. First, the success 

of the plan depends on adequate funding and on the consensus of FAA’s 

aviation industry partners. Yet according to the most recent version of 

the plan, the timing and implementation of some activities may be in 

jeopardy because of the current economic situation and the uncertain 

viability of some industry participants. For example, the plan calls 

for the airline industry to invest $11 billion in new equipment for 

aircraft. FAA is currently reviewing the ability of the airlines to 

make this investment. Second, as noted, the plan relies heavily on 

runway development to increase capacity, but the most recent version of 

the plan reports mixed results in building new runways. While the plan 

indicates that one new runway will be built during the next 10 years, 

it points out that another runway has been canceled and the 

construction of six additional runways has been delayed because of 

local situations.



In January 2003, we reported that airports spent about 10 years 

planning and building recently completed runways and expect to spend 

about 14 years on runways that are not yet completed.[Footnote 11] We 

also reported that several external factors affect how much time is 

spent planning and building runways, and several airports with 

unfinished runway projects identified significant challenges that had 

delayed the completion of their projects. While many airports believed 

that completing the environmental review phase was a significant 

challenge and is an issue that warrants immediate attention, airports 

also faced obstacles that some said were as onerous as the 

environmental review phase. They identified significant challenges in 

reaching agreement with community interest groups during the planning 

phase and in mitigating the potential impact of aircraft noise on the 

surrounding community. Although there may be no single solution to 

resolving all of the issues involved in planning and building runways, 

the federal government and airport authorities are taking some action. 

For example, the Senate’s and the administration’s reauthorization 

proposals call for streamlining the environmental review of 

transportation infrastructure projects.



Recognizing that building new runways is not always a practicable way 

to increase capacity at some airports, we identified three alternatives 

to building runways in our December 2001 report:[Footnote 12]



* Find ways to manage and distribute demand within the system’s 

existing capacity at busy airports such as LaGuardia, by, for example, 

limiting the number of takeoffs and landings during peak periods or 

limiting the ability of general aviation aircraft to use especially 

congested airports (under current law, all aircraft have equal access 

to even the largest airports). Airports are restricted in using pricing 

to reflect the scarcity and congestion of airspace.

:



* Add capacity by using nearby airports that have available capacity.

:



* Examine other modes of intercity travel, such as high-speed rail, 

where metropolitan areas are relatively close, to form an integrated, 

intermodal transportation network.

:



Accordingly, we recommended that the Department of Transportation (DOT) 

begin a more extensive evaluation of initiatives, including intermodal 

solutions and a dialogue with transportation stakeholders, as a basis 

for developing a comprehensive blueprint for addressing the nation’s 

long-term transportation needs. DOT has recognized the need for more 

and better long-range planning on the potential use of such measures 

and agreed with our recommendation. The Department’s evaluation efforts 

are in the beginning stages. The current hiatus in air traffic growth 

creates an opportunity for the development of long-term transportation 

plans.



Federal Programs to Help Small Communities Improve Air Service Face 

Budgetary Pressures and Questions about Their Effectiveness:



While the need for greater capacity is a vital issue for some large-and 

medium-hub airports, the primary issue at other airports that serve 

small communities is to obtain or retain commercial air service. The 

reauthorization process provides an opportunity for the Congress to 

clarify the federal strategy for helping small communities acquire the 

commercial air service they desire. Currently, the challenges that 

small communities have long faced in obtaining or retaining commercial 

air service are increasing as many U.S. airlines try to stem 

unprecedented financial losses through numerous cost-cutting measures, 

including reducing or eliminating service in some markets. Small 

communities feel such losses disproportionately because they may have 

service from only one or two airlines. For them, reductions can mean no 

air service at all.



The Essential Air Service (EAS) program, authorized under the Airline 

Deregulation Act of 1978, guarantees that small communities served 

before deregulation will continue to receive a certain level of 

scheduled air service. Its costs have more than tripled since fiscal 

year 1995, and indications are that without changes to the program, the 

demand for subsidies will soon exceed the program’s $113 million 

appropriation for fiscal year 2003. At the same time, aggregate 

passenger levels at EAS-subsidized airports continue to fall. Often 

fewer than 10 percent of a community’s potential passengers use the 

subsidized local service; the rest choose to drive to their destination 

or drive to a larger airport that offers lower fares or more frequent 

service to more destinations. In 2000, the median number of passengers 

on each EAS-subsidized flight was three. The administration’s budget 

proposal for fiscal year 2004 would substantially reduce the federal 

subsidy for small community air service and require communities that 

wish to retain the service to help subsidize it. Specifically, the 

budget proposal would reduce federal EAS funding from $133 million in 

2003 to $50 million in 2004, alter the eligibility criteria for 

funding, and require nonfederal matching funds. Consistent with its 

budget proposal, the administration’s reauthorization proposal would 

restructure the EAS program to direct its resources to the small 

communities with the greatest need to maintain access to national air 

transportation service. The Senate bill proposes to reauthorize funding 

for the program at current levels.



The Small Community Air Service Development Pilot Program, authorized 

as part of AIR-21, provides grants to communities to enhance local air 

service. In fiscal year 2002, 180 communities requested over $142 

million in air service development grants, and $20 million was 

appropriated. In March 2003, we reported that the program funded some 

innovative approaches.[Footnote 13] For example, Mobile, Alabama, 

received about $450,000 to provide ground-handling services to an 

airline, and Caspar, Wyoming, received $500,000 to purchase and lease 

back an aircraft to an airline to ensure service to the community. The 

program also funded the same types of projects that many small 

communities have undertaken in recent years, such as evaluations of 

marketing activities and the use of financial incentives to encourage 

airlines to either start or enhance service. According to our analysis 

of similar approaches used by about 100 small communities, financial 

incentives offered the most promise for attracting new or additional 

service. However, the additional service typically ended with the 

incentives. The sustainability of such improvements in air service over 

the longer term appeared to depend on the community’s size and ability 

to demonstrate a commitment to that air service, either by providing a 

profitable passenger base or through direct financial assistance. As 

you know, the administration’s fiscal year 2004 budget proposal would 

eliminate the funding for this pilot program. It is too soon to 

determine how effective the various types of initiatives funded through 

this program might prove to be. Other options for making the national 

air transportation system more accessible to small communities might 

include intermodal initiatives such as those we proposed as 

alternatives to runway development.



Efforts to Improve the Efficiency of the Air Traffic Control System 

Face Ongoing Challenges:



Improving the efficiency of the air traffic control system will be 

important to accommodate the expected return to pre-September 11 air 

traffic levels. Efforts to achieve this improvement pose continuing 

challenges, as FAA attempts to put acquisition management and human 

capital reforms in place and establish an effective oversight and 

organizational structure to help ensure that resources are spent cost-

effectively and improvements are realized.



FAA’s Air Traffic Modernization Remains High Risk:



To increase the safety, capacity, and efficiency of the national 

airspace system, FAA undertook a major effort in 1981 to modernize and 

replace aging air traffic control equipment. This effort, which 

includes major projects in such areas as communications, surveillance, 

navigation, and weather, has been plagued by cost overruns, schedule 

delays, and performance shortfalls. As a result, we designated FAA’s 

air traffic modernization program as high risk in 1995, and we continue 

to designate it as such.[Footnote 14] Figure 4 combines our and the DOT 

Inspector General’s analysis of FAA’s progress in meeting cost and 

schedule goals for selected air traffic control projects--the Standard 

Terminal Automation Replacement System (STARS), Wide Area Augmentation 

System (WAAS), Next-Generation Air/Ground Communication (NEXCOM), free 

flight, Local Area Augmentation System (LAAS), and Integrated Terminal 

Weather System (ITWS).



Figure 4: Status of Selected FAA Air Traffic Control Projects:



[See PDF for image]



[End of figure]



FAA is making progress in managing the air traffic control 

modernization effort and has implemented some key projects. For 

example, the agency has replaced the automated color display equipment 

used by air traffic controllers to control traffic in some facilities 

(Display System Replacement); installed the initial phase of the 

computer that receives, processes, and tracks aircraft movement 

throughout the airspace system (HOST computer); and implemented some 

free flight technologies that are expected to allow for more efficient 

use of the system by improving operations in various segments of 

flight. Figure 5 shows an FAA representative using the Display System 

Replacement to monitor and handle air traffic.



Figure 5: Air Traffic Controller:



[See PDF for image]



[End of figure]



However, other key projects continue to experience cost, schedule, and 

performance problems. The Inspector General has reported that the costs 

of five acquisitions have grown by $3 billion--the equivalent of 1 

year’s budget for the modernization program--and the delay in 

completing these acquisitions has ranged from 3 to 5 years.[Footnote 

15] Problems in implementing the Standard Terminal Automation 

Replacement System are indicative of the problems that have plagued the 

modernization program. Since September 1996, FAA has been developing 

the STARS project to replace the outdated computer equipment that air 

traffic controllers currently use in some facilities to control air 

traffic within 5 to 50 nautical miles of an airport.



The current program presently bears little resemblance to the program 

envisioned in 1996. Initially FAA anticipated very little software 

development, planned to install STARS in 172 facilities at a cost of 

$940 million, and expected implementation to begin in 1998 and end in 

2005. In 1999, FAA modified its acquisition approach (from off-the-

shelf software to a combination of customized and off-the-shelf 

software) and increased to 188 the number of facilities scheduled to 

receive STARS. Then the agency concluded that it did not have adequate 

funding to deploy STARS to 188 facilities, and in March 2002, it 

received approval to deploy STARS at 74 facilities that had frequent 

equipment failures, were new, or had the digital radar needed to 

operate STARS.



FAA does not yet know to what extent its estimate of STARS’s remaining 

development costs is reliable because, as we reported in January 2003, 

FAA lacks accurate, valid, current data on the STARS program’s 

remaining costs and progress.[Footnote 16] Without such data, FAA is 

limited in its ability to effectively oversee the contractor’s 

performance and reliably estimate future costs. Although FAA has 

adopted clear procurement management policies and procedures, it did 

not consistently apply this guidance in managing the STARS contract. 

For example, the development cost estimate is based on the contractor’s 

projections, which FAA had not yet independently analyzed as its 

guidance directs. We made several recommendations to improve the 

management of STARS and subsequent terminal modernization programs and 

to provide the Congress with more reliable information for oversight. 

FAA agreed with our recommendations and is implementing them.



Acquisition Management System Is in Place, but Weaknesses Limit FAA’s 

Ability to Manage Its Investments Effectively:



As part of its procurement reforms, FAA introduced an acquisition 

management system in 1996 to reduce the time and cost to deploy new 

products and services. In 1999, we reported that this system provided a 

structured management approach for selecting and controlling 

investments, but still had weaknesses, such as incomplete data on 

projects’ costs, schedule, benefits, performance, and risks, that 

limited FAA’s ability to manage its investments effectively. We made 

several recommendations to address these weaknesses and FAA has made 

changes to better manage its investments. We have since found that FAA 

is overseeing investment risk and capturing key information from the 

investment selection process in a management information system and is 

also developing guidance for validating costs, benefits, and risks. 

However, FAA is not yet incorporating actual costs from related system 

development efforts in its processes for estimating the costs of new 

projects. Moreover, FAA has not yet implemented processes for 

evaluating projects after implementation in order to identify lessons 

learned and improve the investment management process. These weaknesses 

have impeded FAA’s ability to manage its investments effectively and 

make sound decisions about continuing, modifying, or canceling 

projects. Because its acquisition reform effort is not complete, major 

projects continue to face challenges that could affect their costs, 

schedule, and performance.



Human Capital Reform Initiatives Do Not Incorporate Elements Important 

for Effective Management:



In response to claims by FAA that burdensome governmentwide human 

capital rules impeded its ability to hire, train, and deploy personnel, 

the Congress exempted FAA from many federal laws[Footnote 17] governing 

human capital, and the agency began implementing sweeping human capital 

reforms in 1996.[Footnote 18] These reforms addressed three broad 

areas: (1) compensation and performance management, (2) workforce 

management, and (3) labor and employee relations. Figure 6 summarizes 

our analysis of FAA’s progress in implementing initiatives in each of 

these areas.



Figure 6: Implementation Status of Selected FAA Personnel Reform 

Initiatives:



[See PDF for image]



[End of figure]





While FAA has fully or partially implemented the initiatives in each of 

its three broad reform areas, it has not fully incorporated elements 

that are important to effective human capital management into its 

overall reform effort. These elements include data collection and 

analysis, performance goals and measures, and links between reform 

goals and program goals. Furthermore, as we reported in February 2003, 

FAA has not developed specific steps and time frames for building these 

missing elements into its human capital management and for using these 

elements to evaluate the effects of its personnel reform initiatives, 

make strategic improvements, and hold the agency’s leadership 

accountable.



New Structure for Improving the Performance of the Air Traffic Control 

System Has Not Been Fully Implemented:



In 2000, AIR-21 and an executive order established a new structure to 

accelerate the modernization and improve the performance of the air 

traffic control system. This structure was to consist of (1) a five-

member board, called the Air Traffic Services Subcommittee 

(Subcommittee), to oversee the air traffic control system, (2) a chief 

operating officer to manage the air traffic control system, and (3) a 

new performance-based organization, to be known as the Air Traffic 

Organization, to operate the air traffic control system. Under the act, 

the Subcommittee provides oversight by, among other things, reviewing 

and approving strategic plans, large contracts, and budget requests for 

the air traffic control system.



The Subcommittee has been meeting since January 2001, but a chief 

operating officer has not yet been appointed, and FAA is waiting for an 

appointment before putting the new air traffic organization in place. 

To date, the Subcommittee has focused on bringing performance 

management, accountability, and a more businesslike structure to the 

air traffic control system, and it has taken some specific actions, 

including reviewing and approving performance metrics, a budget, and 

three large procurements that FAA initiated. However, without a chief 

operating officer or a performance-based organization, the new 

structure is not functioning as intended.



FAA and other stakeholders have suggested reasons for the difficulties 

in implementing the new structure and have proposed changes to AIR-21 

that they believe would address these reasons. For example, they have 

noted that the Subcommittee’s authority to approve the budget request 

for the air traffic control system challenges the administration’s 

prerogative to submit a budget request reflecting its priorities, and 

they have cited uncertainties in the responsibilities and reporting 

relationships of the chief operating officer, the FAA Administrator, 

and the Subcommittee that, they say, have made it difficult to hire a 

chief operating officer. To address these issues, the administration’s 

reauthorization proposal would (1) eliminate the Subcommittee’s 

approval authority, making the Subcommittee an advisory body, and (2) 

designate the FAA Administrator as the chair of the Subcommittee, 

thereby strengthening the Administrator’s authority over, and 

accountability for the performance of, the chief operating officer. 

While these changes would eliminate the challenge that the 

Subcommittee’s approval authority poses to the administration’s 

prerogatives; would clarify the lines of authority between the chief 

operating officer, the FAA Administrator, and the Subcommittee; and 

could make it easier to hire a chief operating officer, they would also 

limit the power of the Subcommittee. The Senate’s reauthorization 

proposal would also designate the FAA Administrator as the chair of the 

Subcommittee, but it would retain the Subcommittee’s approval 

authority. The merits of these and other proposed changes depend, in 

large part, on the extent to which approval authority is viewed as 

necessary or desirable to bring about improvements in the performance 

of the air traffic control system.



FAA Is Implementing Safety Initiatives and Faces New Challenges in 

Ensuring That Security Enhancements Maintain Aircraft Safety:



Safety has always been and continues to be FAA’s highest priority. FAA 

has taken a number of important steps to improve aviation safety; 

however, its planning and implementation could sometimes be more 

effective. In addition, with the transfer of most aviation security 

responsibilities to the Transportation Security Administration (TSA), 

FAA faces the challenge of maintaining close coordination with TSA to 

ensure that aircraft safety is maintained as TSA implements new 

security enhancements.



FAA and Industry Have Taken Actions to Reduce the Fatal Accident Rate:



Reducing fatal aviation accidents is key to improving aviation safety. 

FAA’s centerpiece for reaching this goal is Safer Skies, an initiative 

that dates back to 1998, when FAA and aviation industry representatives 

worked together to identify the major causes of fatal accidents and to 

design and implement actions to prevent future accidents. Safer Skies 

is intended to reduce the fatal accident rate for commercial aviation 

by 80 percent and to reduce the number of fatal accidents for general 

aviation to 350 a year by 2007.[Footnote 19] Because many preventive 

actions have not yet been fully implemented, it may be too early to 

assess their effectiveness. Achieving the initiative’s goals will 

require FAA to systematically implement preventive actions, such as 

requiring additional safety inspections of aircraft, and to maintain 

good data to monitor the progress of these actions and evaluate their 

effectiveness. As of February 2003, 44 preventive actions had been 

undertaken--of which 16 are completed and 28 are under way, according 

to FAA.



FAA’s New Safety Inspection System Offers Promise, but Problems Still 

Need to Be Addressed:



Improving the effectiveness of FAA’s inspections of airline operations 

is key to improving aviation safety. The FAA Administrator has noted 

that perhaps the greatest support the agency can provide to the 

industry is a robust safety oversight role that will not waver in 

difficult times. FAA’s new inspection program, the Air Transportation 

Oversight System, is central to this oversight role. This program, 

which was implemented in 1998, aims to ensure not only that airlines 

comply with FAA’s safety requirements but also that they have operating 

systems to control risks and prevent accidents. Figure 7 shows an FAA 

inspector inspecting an aircraft for compliance with FAA’s safety 

requirements.



Figure 7: FAA Safety Inspection in Progress:



[See PDF for image]



Source: FAA.



[End of figure]:



We reported in 1999 that FAA had not completed many critical steps, 

such as developing guidance for inspectors and creating databases to 

use in prioritizing inspection resources, before implementing the new 

inspection system in 1998.[Footnote 20] As a result, the agency’s 

ability to conduct effective inspections remains limited. FAA has begun 

to address some of the problems that we identified with the guidance 

and the databases. However, according to a 2002 review by the DOT 

Inspector General, many of the problems that we identified persist, and 

the program’s implementation remains inconsistent because FAA has not 

established strong oversight and accountability procedures.[Footnote 

21] This situation limits FAA’s ability to conduct more systematic, 

structured inspections; analyze the resulting data to identify safety 

trends; and target its resources to the greatest aviation safety risks.



Aviation Safety and Security Require Close Coordination between FAA and 

TSA:



Some key efforts under way to improve aviation security require 

interagency coordination between FAA and TSA because they could also 

affect aircraft safety. While TSA is responsible for most issues 

related to aviation security, FAA retains responsibility for those 

related to aviation safety, including approving the initial aircraft 

design, structural modifications, and procedures for emergency 

evacuation and the transportation of hazardous cargo.[Footnote 22] For 

example, strengthening cockpit doors to increase cockpit security 

during flights was one of the government’s earliest responses to the 

September 11 terrorist attacks. Because the modifications could 

increase the weight of the doors and change the way they are attached 

to the aircraft, FAA has been certifying these modifications to ensure 

that they will not cause decompression during flight or affect the 

aircraft’s structural integrity. In addition, new security procedures 

require that the cockpit door remain locked during flight and that 

access to the cockpit be restricted to the flight crew. As a result, 

senior flight attendants will no longer carry keys to the cockpit, and 

FAA is approving changes to the procedures for rescuing the flight crew 

in an emergency.



FAA is also responsible for the safe transport of dangerous materials 

onboard aircraft. Dangerous goods are chemical (including infectious) 

substances (or anything containing such substances) that pose a threat 

to public safety or the environment during transportation. When these 

goods are properly packaged, labeled, and stowed onboard, they can be 

transported safely, but when they are not, they can pose significant 

threats to people and property. TSA is responsible for screening all 

passengers and property, including cargo, that will be carried aboard 

an aircraft. If, during the screening of passengers or baggage, TSA 

discovers dangerous goods that are not properly packaged or labeled, 

TSA will need to coordinate and share information with FAA, which is 

responsible for enforcing any regulatory violations.



In addition, aircraft crashes could fall under the jurisdiction of 

either FAA or TSA, depending on whether they were the results of 

accidents (FAA) or deliberate acts (TSA). It will be important for the 

two agencies to work together closely during the initial stages of 

crash investigations. To facilitate coordination on these and other 

security issues that affect aviation safety, TSA and FAA signed a 

memorandum of agreement on February 28, 2003. In addition, on March 4, 

2003, the Secretary of Transportation agreed to assign a senior 

official within the Office of the Secretary to serve as DOT’s primary 

liaison to TSA. It is important that both FAA and TSA remain committed 

to coordinating closely on safety and security issues and that 

congressional oversight ensures that the memorandum of agreement is 

implemented.



FAA Faces Challenges in Implementing Controls over Its Costs:



As the administration and the Congress focus on increasing aviation 

capacity, efficiency, and safety, they do so in an extremely 

challenging fiscal environment--the federal budget deficit has 

increased and competition for federal resources has intensified. 

Moreover, as we mentioned previously in this statement, revenues to the 

aviation Trust Fund, which is the source of funding for most of FAA’s 

operations, facilities and equipment, and grant programs, have declined 

in recent years while outlays have increased. It is, therefore, 

especially important that FAA control or reduce costs, run its programs 

efficiently, and detect and prevent fraudulent activities. We and DOT’s 

Inspector General have reported that improvements are needed in these 

areas.



For example, in March 2003, we reported that weaknesses in FAA’s 

purchase card[Footnote 23] controls resulted in instances of improper, 

wasteful, and questionable purchases, as well as missing and stolen 

assets.[Footnote 24] These internal control weaknesses included 

inadequate segregation of duties (i.e., the cardholder requested the 

purchase, placed the order, and picked up or received the goods without 

any other review or approval), lax supervisory review and approval, 

missing purchase documents, inadequate training, and insufficient 

program monitoring activities, all of which created an environment 

vulnerable to fraud, waste, and abuse. During fiscal year 2000, these 

weaknesses contributed to $5.4 million in improper purchases by FAA 

employees and over $630,000 in purchases that were considered wasteful 

or questionable because they were missing a receipt to show what was 

actually purchased. To reduce the likelihood of improper and wasteful 

purchases, we recommended a number of actions to strengthen the 

internal controls over FAA’s purchase card program, such as developing 

detailed procedures that specify the type and extent of review or 

approval that is expected. FAA agreed with our recommendations.



In addition, DOT’s Inspector General reported in January 2003 that FAA 

needs to contain increases in its operating costs and improve its 

internal controls over costs.[Footnote 25] Over the past 6 years, FAA’s 

operations budget, which is 73 percent personnel costs, increased by 

over 41 percent, from $5.3 billion in fiscal year 1998 to $7.5 billion 

in fiscal year 2003. The Inspector General noted that FAA has made 

extensive use of its human capital flexibilities to substantially 

increase salaries, but has done little to reduce operating costs. FAA 

has improved its ability to track its costs by partially implementing a 

new cost accounting system that the Congress directed it to develop in 

1996. The new system, which FAA expects to be fully operational by the 

end of 2003, now tracks 70 percent of the personnel, overhead, and 

other costs related to air traffic services. However, DOT’s Inspector 

General has reported problems with the labor distribution system, which 

is part of the cost accounting system and is used to account for and 

distribute air traffic controller labor costs of about $3.1 billion 

annually to specific facilities and functions. The Inspector General 

noted that the system omitted important internal controls needed to 

ensure that the time worked by air traffic controllers would be 

accurately recorded in the accounting system and paid from the proper 

account. The Inspector General brought these deficiencies to the 

attention of FAA, and the Administrator agreed to correct them. The 

Inspector General further noted that the system as designed could 

provide workforce data that would help determine how many controllers 

are needed and where. These data would assist FAA in planning for the 

anticipated retirement of large numbers of air traffic controllers in 

the near and long term. [Footnote 26] Congressional oversight is 

important to ensure that FAA follows through and corrects the problems 

that we and the Inspector General have identified so that FAA can spend 

its resources on projects and services that will provide the greatest 

return on the public’s investment.



Scope and Methodology:



This statement is based primarily on issued reports that are listed 

under Related GAO Products. However, the sections on the Airport and 

Airway Trust Fund and the Air Traffic Services Subcommittee reflect our 

ongoing work for this Committee. As a result, the results of this work 

that we discuss in this testimony are still preliminary.



To assess the current and projected financial status of the Airport and 

Airway Trust Fund, we obtained financial data from FAA and interviewed 

FAA officials familiar with the information. To assess the status of 

efforts to implement the new structure established under AIR-21 to 

improve the oversight, management, and operation of the air traffic 

control system, we analyzed the legislation and related executive 

order, the administration’s reauthorization proposal, and the first 

report of the Air Traffic Services Subcommittee. We also interviewed 

officials from FAA, the Air Traffic Services Subcommittee, and aviation 

industry organizations. We performed our work in accordance with 

generally accepted government auditing standards.



Contact Information:



[End of section]



For further information on this testimony, please contact Gerald 

Dillingham at (202) 512-2834. Individuals making key contributions to 

this testimony include Tammy Conquest, Howard Cott, Elizabeth 

Eisenstadt, Edward Laughlin, Belva Martin, Maren McAvoy, John W. 

Shumann, Teresa Spisak, and Richard Swayze.



[End of section]



Related GAO Products:



FAA Purchase Cards: Weak Controls Resulted in Instances of Improper and 

Wasteful Purchases and Missing Assets. GAO-03-405. Washington, D.C.: 

March 21, 2003.



Commercial Aviation: Issues Regarding Federal Assistance for Enhancing 

Air Service to Small Communities. GAO-03-540T. Washington, D.C.: March 

11, 2003.



Airport Finance: Past Funding Levels May Not Be Sufficient to Cover 

Airports’ Planned Capital Development. GAO-03-497T. Washington, D.C.: 

February 25, 2003.



National Airspace System: Reauthorizing FAA Provides Opportunities and 

Options to Address Challenges. GAO-03-473T. Washington, D.C.: February 

12, 2003.



Aviation Finance: Implementation of General Aviation Entitlement 

Grants. GAO-03-347. Washington, D.C.: February 11, 2003.



Human Capital Management: FAA’s Reform Effort Requires a More Strategic 

Approach. GAO-03-156. Washington, D.C.: February 3, 2003.



National Airspace System: Better Cost Data Could Improve FAA’s 

Management of the Standard Terminal Automation Replacement System. GAO-

03-343. Washington, D.C.: January 31, 2003.



Aviation Infrastructure: Challenges Related to Building Runways and 

Actions to Address Them. GAO-03-164. Washington, D.C.: January 30, 

2003.



Aviation Safety: Undeclared Shipments of Dangerous Goods and DOT’s 

Enforcement Approach. GAO-03-22. Washington, D.C.: January 10, 2003.



High-Risk Series: An Update. GAO-03-119. Washington, D.C.: January 

2003.



Air Traffic Control: Impact of Revised Personnel Relocation Policies Is 

Uncertain. GAO-03-141. Washington, D.C.: October 31, 2002.



Airport Finance: Using Airport Grant Funds for Security Projects Has 

Affected Some Development Projects. GAO-03-27. Washington, D.C.: 

October 15, 2002.



National Airspace System: Status of FAA’s Standard Terminal Automation 

Replacement System. GAO-02-1071. Washington, D.C.: September 17, 2002.



Options to Enhance the Long-term Viability of the Essential Air Service 

Program. GAO-02-997R. Washington, D.C.: August 30, 2002.



Air Traffic Control: FAA Needs to Better Prepare for Impending Wave of 

Controller Attrition. GAO-02-591. Washington, D.C.: June 14, 2002.



Aviation Finance: Distribution of Airport Grant Funds Complied with 

Statutory Requirements. GAO-02-283. Washington, D.C.: April 30, 2002.



Department of Transportation, Transportation Security Administration: 

Aviation Security Infrastructure Fees. GAO-02-484R. Washington, D.C.: 

March 11, 2002.



Applying Agreed-upon Procedures: Airport and Airway Trust Fund Excise 

Taxes. GAO-02-380R. Washington, D.C.: February 15, 2002.



National Airspace System: Long-Term Capacity Planning Needed Despite 

Recent Reduction in Flight Delays. GAO-02-185. Washington, D.C.: 

December 14, 2001.



National Airspace System: Free Flight Tools Show Promise, but 

Implementation Challenges Remain. GAO-01-932. Washington, D.C.: August 

31, 2001.



Air Traffic Control: Role of FAA’s Modernization Program in Reducing 

Delays and Congestion. GAO-01-725T. Washington, D.C.: May 10, 2001.



Aviation Safety: Safer Skies Initiative Has Taken Initial Steps to 

Reduce Accident Rates by 2007. GAO/RCED-00-111. Washington, D.C.: June 

30, 2000.



National Airspace System: Problems Plaguing the Wide Area Augmentation 

System and FAA’s Actions to Address Them. GAO/T-RCED-00-229. 

Washington, D.C.: June 29, 2000.



National Airspace System: Persistent Problems in FAA’s New Navigation 

System Highlight Need for Periodic Reevaluation. GAO/RCED/AIMD-00-130. 

Washington, D.C.: June 12, 2000.



Federal Aviation Administration: Challenges in Modernizing the Agency. 

GAO/T-RCED/AIMD-00-87. Washington, D.C.: February 3, 2000.



Air Traffic Control: Status of FAA’s Implementation of the Display 

System Replacement Project. GAO/T-RCED-00-19. Washington, D.C.: 

October 11, 1999.



Aviation Safety: FAA’s New Inspection System Offers Promise, but 

Problems Need to Be Addressed. GAO/RCED-99-183. Washington, D.C.: June 

28, 1999.



General Aviation Airports: Oversight and Funding. GAO/T-RCED-99-214. 

Washington, D.C.: June 9, 1999.



Passenger Facility Charges: Program Implementation and the Potential 

Effects of Proposed Changes. GAO/RCED-99-138. Washington, D.C.: May 19, 

1999.



Airport Improvement Program: Analysis of Discretionary Spending for 

Fiscal Years 1996-98. GAO/RCED-99-160R. Washington, D.C.: May 18, 1999.



Air Traffic Control: FAA’s Modernization Investment Management Approach 

Could Be Strengthened. GAO/RCED/AIMD-99-88. Washington, D.C.: April 30, 

1999.



Air Traffic Control: Observations on FAA’s Air Traffic Control 

Modernization Program. GAO/T-RCED/AIMD-99-137. Washington, D.C.: March 

25, 1999.



Federal Aviation Administration: Financial Management Issues. GAO/T-

AIMD-99-122. Washington, D.C.: March 18, 1999.



Airport Financing: Smaller Airports Face Future Funding Shortfalls. 

GAO/T-RCED-99-96. Washington, D.C.: February 22, 1999.



Airport Financing: Annual Funding As Much As $3 Billion Less Than 

Planned Development. GAO/T-RCED-99-84. Washington, D.C.: February 10, 

1999.



FOOTNOTES



[1] See the Aviation Investment and Revitalization Vision Act, a Senate 

bill to reauthorize federal aviation programs and the administration’s 

draft reauthorization proposal, the Centennial of Flight Aviation 

Authorization Act, or “Flight 100.”



[2] U.S. General Accounting Office, Aviation Safety: FAA’s New 

Inspection System Offers Promise, but Problems Need to Be Addressed, 

GAO/RCED-99-183 (Washington, D.C.: June 28, 1999). 



[3] U.S. Department of Transportation, Office of Inspector General, 

Report on the Air Transportation Oversight System: Federal Aviation 

Administration, AV-2002-088 (Washington, D.C.: Apr. 8, 2002).



[4] Over the past 5 years, the amount of funding available to airports 

for planned capital development ranged from about $7 billion to $13 

billion annually. 



[5] The Airport and Airway Trust Fund was established by the Airport 

and Airway Revenue Act of 1970 (P.L. 91-258) to aid in funding the 

development of a nationwide airport and airway system and to fund FAA 

investments in air traffic control facilities. The Trust Fund is 

supported by a number of excise taxes, including taxes on passenger 

tickets, fuel, and cargo.



[6] Under the Passenger Facility Charge program, airports with FAA’s 

approval may charge passengers up to $4.50 for boarding airplanes at 

their facilities.



[7] U.S. General Accounting Office, Airport Finance: Using Airport 

Grant Funds for Security Projects, GAO-03-27 (Washington, D.C.: Oct. 

15, 2002).



[8] Letters of intent represent a nonbonding commitment from FAA to 

provide multiyear funding to an airport beyond the current AIP 

authorization period.



[9] This was the average for 1998 through 2002.



[10] In addition to runways, the plan addresses capacity enhancements 

designed to make more efficient use of the airspace.



[11] U.S. General Accounting Office, Aviation Infrastructure: 

Challenges Related to Building Runways and Actions to Address Them, 

GAO-03-164 (Washington, D.C.: Jan. 30, 2003).



[12] U.S. General Accounting Office, National Airspace System: Long-

term Capacity Planning Needed Despite Recent Reduction in Flight 

Delays, GAO-02-185 (Washington, D.C.: Dec. 14, 2001).



[13] U.S. General Accounting Office, Commercial Aviation: Issues 

Regarding Federal Assistance for Enhancing Air Service to Small 

Communities, GAO-03-540T (Washington, D.C.: Mar. 11, 2003).



[14] U.S. General Accounting Office, High-Risk Series: An Update, 

GAO-03-119 (Washington, D.C.: Jan. 2003).



[15] These five programs are the Wide Area Augmentation System, 

Standard Terminal Automation Replacement System, Airport Surveillance 

Radar-11, Weather and Radar Processor, and Operational, Supportability, 

and Implementation System. See U.S. Department of Transportation, 

Office of Inspector General, Reauthorization of the Federal Aviation 

Administration, CC-2003-058 (Washington, D.C.: Feb. 12, 2003). 



[16] U.S. General Accounting Office, National Airspace System: Better 

Cost Data Could Improve FAA’s Management of the Standard Terminal 

Automation Replacement System, GAO-03-343 (Washington, D.C.: Jan. 31, 

2003).



[17] This is a result of 1995 legislation that granted FAA broad 

exemptions from laws governing federal civilian personnel management 

found in title 5 of the United States Code.



[18] U.S. General Accounting Office, Human Capital Management: FAA’s 

Reform Effort Requires a More Strategic Approach, GAO-03-156 

(Washington, D.C.: Feb. 3, 2003).



[19] Commercial aviation includes both large air carrier operations and 

smaller commuter operations. General aviation includes a wide variety 

of aircraft, ranging from corporate jets to small piston-engine 

aircraft as well as helicopters, gliders, and aircraft used in 

operations such as firefighting and agricultural spraying.



[20] U.S. General Accounting Office, Aviation Safety: FAA’s New 

Inspection System Offers Promise, but Problems Need to Be Addressed, 

GAO/RCED-99-183 (Washington, D.C.: June 28, 1999).



[21] U.S. Department of Transportation, Office of Inspector General, 

Report on the Air Transportation Oversight System: Federal Aviation 

Administration, AV-2002-088 (Washington, D.C.: Apr. 8, 2002). 



[22] FAA has responsibility for maintaining the security of its air 

traffic control facilities and computer systems.



[23] As of January 2002, over 8,000 FAA employees (17 percent of its 

workforce) had been issued commercial purchase cards. In fiscal year 

2001, FAA made over 364,000 purchases using these cards.



[24] U.S. General Accounting Office, FAA Purchase Cards: Weak Controls 

Resulted in Instances of Improper and Wasteful Purchases and Missing 

Assets, GAO-03-405 (Washington, D.C.: Mar. 21, 2003).



[25] Department of Transportation, Office of Inspector General, DOT’s 

Top Management Challenges (Washington, D.C.: Jan. 21, 2003).



[26] U.S. General Accounting Office, Air Traffic Control: FAA Needs to 

Better Prepare for Impending Wave of Controller Attrition, GAO-02-591 

(Washington, D.C.: June 14, 2002).