When an operator has information that the area around a pipeline segment not previously identified as a high consequence area could satisfy any of the definitions in ยง192.903, the operator must complete the evaluation using method (1) or (2). If the segment is determined to meet the definition as a high consequence area, it must be incorporated into the operator's baseline assessment plan as a high consequence area within one year from the date the area is identified.