Jump to main content.


Superfund Quick Finder

 

Remedial Design - RD

AF AS BR CL CR DL DO DP
EM ER FE FI GU HE HI LG
LP NA ND NL NM NP OF OM
OP RA RD RI RR RT SA WP
Confidential Documents
BC CC DC FC LC NC PC SC

Glossary of terms relating to file structure phase activities and file categories

Descriptions of 22.00 - 22.99 SRC Folder Code HZ/SF/RE/RD NARA General Records Schedule  N1-412-99-23

Definition

The Remedial Design (RD) is a series of engineering reports, documents, specifications, and drawings that detail the steps to be taken during the Remedial Action (RA) to meet the goals established in the Record of Decision (ROD) and remove the site from the National Priorities List.  The RD development phase includes all activities relating to the review and approval of all design efforts, including preliminary, intermediate, pre-final, and final design phase submittals.



SDMS Keyword  (Click on keyword to see description)

22.11 Contractor Selection Information
22.26 Field Documentation
22.25 General Correspondence
22.15 Modeling Study
22.01 Monthly Site Status Summary (Unless Confidential)
22.24 Natural Resource Trustee [Moved to RT phase]
22.14 Pilot Study
22.21 Remedial Design Cost Estimate
22.23 Remedial Design Final Design
22.22 Remedial Design Supporting Calculations
22.17 Remedial Design Specifications (30%)
22.18 Remedial Design Specifications (60%)
22.19 Remedial Design Specifications (95%)
22.20 Remedial Design Specifications (Other)
22.06 Sampling and Analysis Done by EPA
22.09 Sampling and Analysis Done by Other than EPA, PRP, or State
22.08 Sampling and Analysis Done by PRP
22.07 Sampling and Analysis Done by State
22.10 Statement of Work
22.02 Technical Progress Report, EPA Contractor
22.05 Technical Progress Report, Oversight Contractor
22.04 Technical Progress Report, PRP Contractor
22.03 Technical Progress Report, State Contractor
22.13 Treatability Study
22.16 Value Engineering
22.12 Workplan and/or Amendment

22.99 Other



SDMS Keyword Descriptions

22.01 Monthly Site Status Summary (Unless Confidential)
;This is the monthly summary of work done on the site prepared by the Remedial Project Manager (RPM) during the Remedial Design phase.

22.02 Technical Progress Report, EPA Contractor
These are the monthly progress reports or other reports required of the EPA contractor doing work during the Remedial Design phase.  These reports cover the technical information about work performed.  If the report includes detailed cost information, the cost information  should be filed in Contractor Confidential (CC) [91.01].

22.03 Technical Progress Report, State Contractor
When the state is doing the Remedial Design under a Cooperative Agreement, they often provide EPA with a copy of their contractor's monthly progress report.  This report details the technical work performed, community relations activities, change orders, problems encountered, projected work for the next period, and daily reports.

22.04 Technical Progress Report, PRP Contractor
When the contractor is hired directly by the PRP to do Remedial Design work, a monthly progress report must be submitted to EPA.  This report details work performed, community relations activities, change orders, problems encountered, projected work for the next period, and daily reports.

22.05 Technical Progress Report, Oversight Contractor
These are any formal reports filed by EPA's oversight contractor concerning the Remedial Design work being performed by the PRP or their contractor.

22.06 Sampling and Analysis Done by EPA
These are reports summarizing  raw data related to any samples taken at the site by EPA or their contractors and sent to the Contract Lab Program (CLP), EPA Lab, ARC Lab, etc. for analysis during the Remedial Design phase.  Sampling and Analysis are stored in house until QA/QC done, then sent to off-site storage; only transmittals, analytical summaries, and chain-of-custody forms should be placed in the phase/activity file.  Target sheets with the accession numbers of the boxes containing full packages should be placed with copied documents.  The entire packages will stay intact for off-site storage.

22.07 Sampling and Analysis Done by State
These are reports summarizing  raw data related to any samples taken at the site by the state or their contractors for analysis during the Remedial Design phase. Sampling and Analysis are stored in house until QA/QC done, then sent to off-site storage; only transmittals, analytical summaries, and chain-of-custody forms should be placed in the phase/activity file.  Target sheets with the accession numbers of the boxes containing full packages should be placed with copied documents.  The entire packages will stay intact for off-site storage.

22.08 Sampling and Analysis Done by PRP
These are reports summarizing  raw data related to any samples taken at the site by the PRP or their contractors during the Remedial Design phase. Sampling and Analysis are stored in house until QA/QC done, then sent to off-site storage; only transmittals, analytical summaries, and chain-of-custody forms should be placed in the phase/activity file.  Target sheets with the accession numbers of the boxes containing full packages would be placed with copied documents.  The entire packages would stay intact for off-site storage.

22.09 Sampling and Analysis Done by Others
These are reports summarizing raw data related to any samples taken at the site during the Remedial Design phase by some party other than EPA or the PRP or their contractors.  Could be sampling done by the state or local government, environmental green groups, etc. Sampling and Analysis are stored in house until QA/QC done, then sent to off-site storage; only transmittals, analytical summaries, and chain-of-custody forms should be placed in the  phase/activity  file.  Target sheets with the accession numbers of the boxes containing full packages should be placed with copied documents.  The entire packages will stay intact for off-site storage.

22.10 Statement of Work
This is an EPA document outlining work to be performed.  This is the technical direction from the EPA.  It also includes an Independent Government Cost Estimate (IGCE) of the time and costs for each task.

22.11 Contractor Selection Information
Theses are any documents related to the selection of a contractor which includes qualifications information about the contractor and EPA approval as specified in the Consent Decree for a PRP contractor.

22.12 Workplan and/or Amendment
A workplan outlines the approach for studies or activities as submitted by those responsible for undertaking the work for RD.  There is generally a draft submitted for review and a final based on comments received back.  Following final approval to the workplan, amendments are used to change what was originally designated or agreed upon.  Workplans can include plans for sampling plans, the Health and Safety plan, Contingency plan, QA/QC plans, etc.  If the workplan is for an EPA contractor and includes detailed cost information the entire, the Workplan should be filed in Contractor Confidential [91.01]. 

22.13 Treatability Study
This is a test, study, or sampling and analysis to optimize the required treatment and/or disposal operations and systems.

22.14 Pilot Study
This is a test of the equipment or system to ensure that it is operating properly.  This is considered a sample run.  This study can also be referred to as a bench or scale study.

22.15 Modeling Study
This is an investigative technique using a mathematical or physical representation of a system or theory that accounts for all or some of the known properties.  Models are often used to test the effect of changes of system components on the overall performance of the system.

22.16 Value Engineering
These are documents related to the review of the plans and specifications for potential cost savings through the replacement or modification of high-priced design items.

22.17 Remedial Design Specifications (30%)
This is a preliminary design that addresses not less than 30% of the total design and is based on data furnished for this project.

22.18 Remedial Design Specifications (60%)
If the design is complex, an intermediate design is submitted for review when the design is 60% complete.

22.19 Remedial Design Specifications (95%)
This is a pre-final design submitted for approval and revisions at 95% completion of the design.  This submittal includes the plan, specifications, an Operation and Maintenance (O&M) Plan, Quality Assurance Project Plan (QAPP), and Site Safety Plan (SAP).

22.20 Remedial Design Specifications - Other
This is a design submitted for approval and revisions at other stages of completion of the design.  This could be a draft design, 40% complete, 50% complete, 100% complete, etc

22.21 Remedial Design Cost Estimate
This is an estimate of construction costs which is submitted with the final design.  This estimate is used to evaluate bids.

22.22 Remedial Design Supporting Calculations
These are worksheets, sketches, and calculations related to design but not covered in other reports.

22.23 Remedial Design Final Design
Final Design documents include specifications, cost estimates, backup calculations, conceptual designs, etc.  All addendum to the final design will be filed with the final.  (Reduced-size copy of drawings are filed with specifications, full-size are filed in map drawers with cross-references made). Final or complete design packages  include plans, specifications, O&M plan, QAPP, and SAP.  All of the pieces should coordinate.  This is the documentation that is released with the bid package.

22.25 General Correspondence

22.26 Field Documentation
Consistent documentation and accurate recordkeeping procedures are critical to record any data anomalies.  Documentation involved in maintaining field sample inventories and proper chain-of-custody reports may include the sample identification matrix, sample tag, traffic report, high-hazard traffic report, SAS packing list, receipt for samples form, Central Regional Laboratory (CRL) sample data report, shipping airbill, etc.

22.99  Other
If the needed keyword code is not available, code to 22.99.


Local Navigation


Jump to main content.