Peer Exchanges, Planning for a Better Tomorrow, Transportation Planning Capacity Building

Transportation Planning Capacity Building Program

– Peer Roundtable Report –


Linking Planning and NEPA

Location: Pittsburgh, Pennsylvania
 
Date:
 
June 7, 2005
 
Roundtable Panelists: Diana Mendes, DMJM+Harris
Don Emerson, PB Consult
Toni Bates, SANDAG
Ralph Jackson, Utah Transit Authority
Carmen Clark, Carmen Clark Consulting
Liz Rao, Denver Regional Transportation District

I. Summary and Background

This Peer Roundtable was held as part of the Transportation Planning Capacity Building (TPCB) Program, which is jointly sponsored by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA). The event was a session at the American Public Transportation Association's (APTA) 2005 Rail Transit Conference. It focused on linking the transportation planning process with the requirements of the National Environmental Policy Act (NEPA). According to the Environmental Protection Agency (EPA) website, NEPA requires integration of environmental values into decision-making through consideration of environmental impacts of and reasonable alternatives to proposed federal actions. As federal transportation spending follows local plans and decisions, local agencies must comply with NEPA throughout project development. If a transportation project is determined to have a significant environmental impact, a detailed statement known as an Environmental Impact Statement (EIS) must be prepared. After a period of public review, the EIS can be approved by a record of decision (ROD) from a federal department of transportation agency, including the Federal Transit Administration (FTA) and the Federal Highway Administration (FHWA).

For this roundtable, Don Emerson and Diana Mendes served as facilitators. At the outset of the roundtable, attendees described their interests in attending the session:

  • Streamlining the NEPA process
  • Referenda, planning and FTA New Starts
  • Metropolitan Planning Organizations' (MPO) roles in increasing the deliverability of projects
  • Community impacts
  • Citizen outreach
  • Changes to the scope of work
  • Project management
  • Defensibility of planning and project development decision-making
  • Coordinating multiple projects in the same metropolitan area

Attendees discussed the concern that the NEPA process is not robust enough to address complex corridors with multimodal projects. It was stressed that NEPA requirements should be addressed early in a project's planning phase. Additionally, the context into which a project is built — more often than the project type — determines the course for NEPA.

back to top

II. Linking Planning and NEPA: Towards Streamlined Decision-making (Don Emerson)

Don Emerson gave a presentation that focused on the goal of streamlined decision-making and how linking planning and the NEPA process can help further this goal. Mr. Emerson described a project decision-making continuum that has four phases: Planning and Programming; Project Analysis/Refinement; Final Design; and Implementation. Mr. Emerson then discussed where NEPA requirements enter the decision-making continuum. NEPA requirements are often begun and completed in the second phase-the Project Analysis/Refinement phase. Mr. Emerson and attendees agreed that NEPA requirements should be considered from the beginning of the decision-making process and continue throughout the life of the project, including follow-up after implementation to ensure mitigation strategies promised as part of the ROD were carried out.

The goal of linking planning and NEPA is to implement a more integrated approach to planning and environmental concerns. Currently, planning and NEPA requirements are addressed separately. Often, planning does not adequately recognize environmental factors. The result is that planning decisions must be revisited during the NEPA process, increasing the project costs and time to completion. Because of the disconnect between planning and NEPA, the public and elected officials can become impatient, confused, and frustrated.

Mr. Emerson believes change will require a change in the transportation planning culture. This change can be achieved without regulation by using seminars and workshops. Mr. Emerson has led linking planning and NEPA workshops in the form of half day executive seminars or 3-day managers-level workshops. The result of these workshops is an Action Plan for change. The Action Plan is developed with a goal of parties improving their collaboration and data sharing.

Mr. Emerson discussed his observations from the various workshops he has led. Mr. Emerson felt that many practitioners do not understand the NEPA process well or the flexibility they could have in linking planning and NEPA. Systems planning is often weak and the focus is more on project planning. Resource agencies are willing to participate in planning, but their staff time is limited. There is a general lack of understanding of "how much environmental analysis is enough" to support various decisions. Data sharing between different transportation planning organizations — e.g. state departments of transportation (DOTs) and MPOs — is often a shortcoming. Mr. Emerson has observed that state DOTs often seem more interested than transit agencies in linking planning and the NEPA process. Transit agencies may feel that they do not have to concern themselves as much with the NEPA process. However, Mr. Emerson stressed that transit agencies should address NEPA questions early in the planning process.

Carmen Clark, who co-leads the workshops with Mr. Emerson, also discussed her observations. Ms. Clark agreed with Mr. Emerson about the lack of knowledge about the NEPA process among planning managers. Also, resource agency staff do not know about Transportation Improvement Programs (TIPs) or how a transportation project advances through the planning process to implementation. This ignorance from multiple parties leads to a lack of trust between individuals who could otherwise streamline both planning and NEPA. Information sharing between groups can result in an elevated level of trust.

One issue that Mr. Emerson highlighted with linking planning and NEPA is the differences between FTA and FHWA project development processes. FTA through its alternatives analysis requirement for New Starts permits project sponsors to drop unreasonable alternatives prior to the formal notice of intent for the NEPA process. FHWA however traditionally leverages NEPA to consider all project alternatives. Mr. Emerson presented the following list of different FTA and FHWA approaches to the NEPA process:

FHWA Emphases FTA Emphases
Retaining all reasonable alternatives through the draft environmental impact statement (DEIS)
  • Alternatives Analysis (AA)/DEIS or Preliminary Engineering (PE)/DEIS
  • PE approval
  • Restricting PE/DEIS to Locally Preferred Alternative (LPA) and baseline
Adequacy of environmental analysis and coordination Adequacy of travel forecasting
  • Comparable levels of detail
  • Highway performance — primarily congestion — is basis for purpose and need
Comparable transit service between New Start and baseline
Evaluation in terms of "meeting" purpose and need Evaluation in terms of cost effectiveness
Financial planning after the record of decision (ROD) Financial planning before the record of decision (ROD)

back to top

III. Roundtable Discussion

Diana Mendes and Don Emerson facilitated a roundtable discussion after the initial presentation. Panelists were invited to share their experiences and attendees were invited to ask questions and offer comments and suggestions. The following summary covers the four primary areas of discussion.

Responsibility for Linking Planning and NEPA

As described above, there are many issues that arise from separate planning and NEPA processes. The decision-making process can be slowed and become more costly. Linking planning and NEPA can help streamline overall project implementation. However, there is a question of who bears the responsibility for linking the planning and NEPA processes. Ms. Mendes raised this issue and facilitated discussion of it.

Attendees offered a variety of opinions including that state DOTs and MPOs should be responsible for solving some of the issues surrounding separate planning and NEPA processes. Others felt that leadership within these agencies would need to prioritize linking planning and NEPA to solve the issues of separate processes. Some attendees commented that if local planners did link planning and NEPA, there would still be difficulty because the federal agencies approach the processes differently.

Methods of Integration and Project Examples

The discussion focused on methods on linking planning and NEPA and project examples of integrated approaches. Attendees agreed that transportation should be viewed as a system consisting of all modes as opposed to transit versus highways. Panelist Toni Bates explained that San Diego has combined its transit agency with the MPO. The new agency has planning responsibilities for all modes of transportation in the region. Ms. Bates believes that a planning process can be developed that satisfies the ways both FTA and FHWA approach NEPA with the federal funding process for multi-modal projects.

The panelists stressed that integration of planning and NEPA should be a collaborative and multi-agency approach. Panelist Ralph Jackson offered a project example from the Salt Lake City area. He described a light rail transit project and a highway project that had the same EIS document. In the Salt Lake City region, the NEPA process is completed for the entire regional plan which includes both highway and transit projects.

Panelist Liz Rao described the Southeast Corridor Project in Denver for which transit was initially the preferred alternative. However, the highway alternative was reconsidered at a later date resulting in an integrated EIS. The transit project and the highway project also shared the right-of-way costs.

Attendees agreed that formal case studies covering projects similar to those discussed above would be useful on how to apply NEPA requirements. Lessons learned and advantages and disadvantages would be useful in understanding how to implement the NEPA process.

Different FTA and FHWA approaches

The group discussed the difference in the planning and NEPA processes for FTA funded transit projects and FHWA funded highway projects. The funding source affects the planning and NEPA processes because FHWA funding is formula funding and FTA provides discretionary grants that are highly competitive. FTA New Starts projects must compete for limited funds; thus the selection of the alternative is governed by the NEPA process, but also by its likelihood of meeting competitive cost-effective thresholds for all projects nationwide. Funding for FHWA is not competitive and FHWA designates money through formulas for specific purposes.

Some attendees felt that linking planning and NEPA would be easier if FTA and FHWA had more integrated approaches. Transit agencies should then try to find commonality between FTA and FHWA decision processes and frameworks. However, some felt that transit agencies should be careful about promoting FHWA and FTA working together on NEPA requirements. Some flexibility could be lost because FHWA might control the process more if there were an integrated approach.

NEPA Purpose

Panelists and attendees discussed the purpose of the NEPA requirements. Attendees felt that the purpose of NEPA is to serve as a decision-making tool. Ms. Mendes explained that NEPA documents are being used in ways that were never intended. The NEPA process has become too long, too complex, and too expensive. This is due to how courts have interpreted NEPA legislation. NEPA documents should be short and very high-level strategic documents produced for the public.

Some attendees felt that NEPA must be part of the New Starts process, because transit agencies must choose projects that will receive funding and be affordable. However, others believed that funding issues should not be part of the NEPA process and that New Starts should be kept as a separate rating tool.

back to top

IV. For More Information

Key Contact(s):
Don Emerson
PB Consult
703-742-5804
emerson@pbworld.com

Diana Mendes
DMJM+Harris
202-251-4930
diana.mendes@dmjmharris.com

Toni Bates
SANDAG (San Diego's MPO and Transit Agency)
619-699-6950
tba@sandag.org

Ralph Jackson
Utah Transit Authority
801-809-4108
rjackson@uta.cog.ut.us

Liz Rao
Denver Regional Transportation District (RTD)
303-299-2485
liz.rao@rtd-denver.com

Carmen Clark
Carmen Clark Consulting
415-242-0302
ccconsult@earthlink.net

back to top

V. Attachments/Links

Attendee List

Name Organization Phone Email
Michael Gatje Wickwire Gavin P.C. 703-790-8750 mgatje@wickwire.com
David J. Sands Urban Engineers 215-922-8080 djsands@urban-hq.com
Steve Brooks Jones & Stokes 213-627-5376 sbrooks@jsanet.com
Charlie Hales HDR 503-957-4063 Charles.hales@hdrinc.com
Jayne Whitney HRT 757-222-6000 jwhitney@hrttransit.org
Greg Walker DMJM Harris 267-210-9261 Greg.walker@dmjmharris.com
David Vozzolo FTA 202-366-9612 David.vozzolo@fta.dot.gov
Rich Weaver APTA 202-496-4809 rweaver@apta.com
Bob Cone HDR 407-420-4210 Rcone@hdrinc.com
Tiffany Gallegos FTA 720-963-3312 Tiffany.Gallegos@fta.dot.gov
Rick Pilgrim URS 303-299-2833 Richard_pilgrim@urscopr.com
Ed Coven Florida DOT 850-414-4522 Ed.coven@dot.state.fl.us
David Wilson Schlickman and Associates 312-920-0112 Dwilso1@uic.edu
Ernie Baisden Maryland Transit Administration 410-767-3752 ebaisden@mtamaryland.com
Doug Moore COTA 614-308-4231  
Stephen Beard S.R. Beard and Associates 602-793-8001 sbeard@srbeard.com
Trip Brizell DART 214-749-2764 tbrizell@dart.org
Sam Carnaggio Virginia Dept. of Rail - Dulles Metrorail 702-288-5900 Sam.carnaggio@dullesmetro.com
Mysore Nagaraja MTA NYCT 646-252-4277 mnagaraja@nyct.com
Jerry Gold Carter & Burgess 212-354-3675  
Nicolas Bosonetto Allegheny County 412-350-1025  
Renee Haider NTI 732-932-1700 rhaider@nh.rutgers.edu
Richard Bradman Metro (Portland) 503-797-1749 brandmanr@metro.dstpu.gov
Carl Bausch FTA 202-366-1626 Carl.Bausch@fta.dot.gov
Paul Christner US DOT Volpe Center 617-494-3142 Paul.christner@volpe.dot.gov
Mike Marchelletta DMJM Harris 917-282-0460 Michael.marchelletta@dmjmharris.com
Bill Tsiforas Jacobs Civil Inc 702-676-1568 William.tsiforas@jacobs.com
David Swallow RTC of Southern Nevada 702-676-1616 swallowd@rtcsnv.com
Ray Amoruso URS Corp 757-499-4224 Ray_amoruso@urscopr.com
Sharyn LaCombe Parsons Transportation 513-899-9430 Sharyn.Lacombe@parsons.com
Jeff Boothe Holland and Knight LLP 202-955-3000 Jeff.boothe@hklaw.com
Frank Harscher Jacobs 770-673-6650 Frank.harscher@jacobs.com
Debbie Tilley Jacobs/ FTA PMO Consultant 312-612-6030 Deborah.tilley@jacobs.com
Gail Moran Maryland MTA 410-767-3767 Gmoran1@mtamaryland.com
Cheryl King Wilbur Smith Associates 770-936-8650 cking@wilbursmith??.com
Kari Watkins Wilbur Smith Associates 203-865-2191  
Vince Gallagher Hill International Inc. 609-970-0949 vincegallagher@hillintl.com
Sallye Perrin Parsons 410-340-4413 Sallye.perrin@parsons.com

back to top

Appendix A

Mr. Emerson presented a slide called the "NEPA Umbrella" that listed the legislation and other factors that the NEPA process must consider. The list includes the following:

  • Title VI of Civil Rights Act of 1964
  • Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970
  • Americans with Disabilities Act
  • Executive Order 12898 (Environmental Justice)
  • Section 4(f) of US DOT Act (49 USC 303)
  • Clean Air Act
  • Safe Water Drinking Act
  • Farmland Protection Policy Act
  • Solid Waste Disposal Act
  • Resource Conservation and Recovery Act of 1976
  • Comprehensive Environmental Response, Compensation and Liability Act
  • Emergency Planning and Community Right to Know Act of 1986
  • National Historic Preservation Act
  • Economic, Social and Environmental Effects
  • Noise
  • Public Hearings
  • Archaeological and Historic Preservation Act

back to top

Peer Exchanges, Planning for a Better Tomorrow, Transportation Planning Capacity Building