Topic: Baseline Assessment Plan (BAP)

Topic Hierarchy:

Topical Index
 » Assessment
   » Baseline Assessment Plan (BAP)

Related Rule Sections:

Related Protocol Questions:

B.03 Use of Prior Assessments

If prior assessments are used in the BAP, verify that the assessment methods used meet the requirements of §192.921(a) and that remedial actions have been carried out to address conditions listed in §192.933. Prior assessments are those that were completed prior to December 17, 2002. [§192.921(e)]

B.04 New HCAs/Newly Installed Pipe

Verify that the operator updates the baseline assessment plan for new HCAs and newly installed pipe. [§192.905(c), §192.921(f), §192.921(g)]