Skip to main content
Skip to sub-navigation
About USAID Our Work Locations Policy Press Business Careers Stripes Graphic USAID Home
USAID: From The American People Assistance For Iraq Cat Ba Island, once a sleepy fishing village, is now a resort town - Click to read this story
Accomplishments »
Acquisition and Assistance Activities »
Contracts and Grants »
Annexes, Attachments and Other Documents for Solicitations »
Success Stories »
Employment Opportunities »
Acquisition & Assistance Notices »
Global Development Alliance »
Sectoral Consultations »
Press Information »
Testimony & Speeches »
Audio/Video »
USAID Photo Gallery »
State Department Photo Gallery »
Iraq's Legacy of Terror: Mass Graves »
Inspector General »
U.S. Embassy - Baghdad »
USAID: EspaƱol - Irak »

Iraq Updates

Get Acrobat Reader...

Iraq Photo Gallery
USAID Funds Renovation of Iraq's Electrical System: Baghdad South Power Plant
Iraq
October 2003

Several US armored vehicles help guard the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system. Baghdad South, like many other power facilities, is in great disrepair. Iraqi plant managers were forced to keep them online at any cost, often foregoing maintenance and safety procedures.
Several units of the Baghdad South power plant are offline for seasonal maintenance. USAID is funding the repair of Iraq's nationwide electrical system, which consist of some 29 major generating plants, transmission grids and local substations.  Much of the electrical system has been damaged by looting.
An engineer makes a site visit to the Baghdad South Power Plant. USAID is funding the repair of Iraq's nationwide electrical system, which consist of some 29 major generating plants, transmission grids and local substations.  Much of the electrical system has been damaged by looting.
Cracked insulation can be seen on equipment at the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system, which consist of some 29 major generating plants, transmission grids and local substations.  Baghdad South, like many other power facilities, is in great disrepair. Much of the electrical system has been damaged by looting, and Iraqi plant managers were forced to keep plants online at any cost, often foregoing maintenance and safety procedures.
Engineers make a site inspection at the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system, which consist of some 29 major generating plants, transmission grids and local substations.  Baghdad South, like many other power facilities, is in great disrepair.  Damage to a parts storage facility was caused when a welders spark set off an explosion.
Engineers make a site inspection at the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system, which consist of some 29 major generating plants, transmission grids and local substations.  Baghdad South, like many other power facilities, is in great disrepair.
General view of the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system.  Baghdad South, like many other power facilities, is in great disrepair.  Iraqi plant managers were forced to keep plants online at any cost, often foregoing maintenance and safety procedures.
Iraqi engineers monitor controls at the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system.  Baghdad South, like many other power facilities, is in great disrepair.  Iraqi plant managers were forced to keep plants online at any cost, often foregoing maintenance and safety procedures.
A control monitor displays the output of one unit at the Baghdad South power plant. USAID is funding the repair of Iraq's nationwide electrical system, which consist of 29 major generating plants, transmission grids and local substations.
General view of the Baghdad South power plant with two units running. USAID is funding the repair of Iraq's nationwide electrical system, which consist of 29 major generating plants, transmission grids and local substations.  Baghdad South, like many other power facilities, is in great disrepair, and units are now being shut down for repairs.

Electricity

Expanding Access to Electricity

In 2002 Baghdad had access to electricity on a near continuous basis while the rest of Iraq was limited to 3 to 6 hours daily. The U.S. government has made significant progress in improving electricity supply in Iraq and distributing it more equitably throughout the country. USAID recently completed its three-year, $2.3 billion Iraq Infrastructure Reconstruction Program. Through its overall program, USAID has added 1,292 megawatts of electric generating capacity to Iraq's power grid, serving over 7 million Iraqis.

Expanding Access to Electricity

Restoring and improving Iraq's electricity supply has been USAID's biggest and most costly challenge. In April 2003, Iraq's usable electrical generation capacity was 2,500 MW - 58 percent of the pre-conflict level. Before the conflict, access to power was unreliable and varied greatly throughout the country. USAID worked to restore electricity to homes, public facilities, and business throughout Iraq.

USAID has helped increase electrical generation to an average daily peak of approximately 4,500 MW. However, estimated total demand in Iraq is 8,500 MW and the looting of cables, destruction of hightension towers, and sabotage of fuel lines persist. Decades of operation without regular maintenance have resulted in increased breakdown and a need for significant rehabilitation.

ACCOMPLISHMENTS

  • Repaired thermal units, replaced/ added turbines, rehabilitated the transmission network, and installed and restored generators.
  • USAID has rehabilitated or added 1,292 MW of generation capacity, through new generation, maintenance and rehabilitation work, to the grid through 42 projects, supplying power to approx 8.5 million people.
  • Repaired the 400 KV Khor az Zubayr-Nasiriyah transmission line.
  • USAID and partners rehabilitated or constructed 25 distribution substations in Baghdad to improve the distribution and reliability of electricity for more than two million residents.
  • Over 240 Ministry of Electricity officials, plant managers, and engineers underwent USAID training to properly operate and maintain the power plants.