Milltown Reservoir Sediments

Confluence of the Blackfoot and Clark Fork Rivers

View of the project area at the confluence of the BlackFoot and Clark Fork Rivers

Bonner Public Meeting, October 14, 2008 (PDF, 5.3 M, about PDF files)

Thompson Falls Public Meeting, October 15, 2008 (PDF, 3.2 M)

Read EPA's bi-weekly Cleanup Updates
These updates are intended to provide you with the latest information about remediation, restoration, and redevelopment of the Milltown Reservoir Sediments Superfund Site.

What's happening with the 3Rs: Remediation, Restoration, and Redevelopment?

Currently:

Clark Fork Coalition hosts the "Dam Cam", Live Milltown Reservoir WebCam exit EPA

Site Information
Site Description
Site Risk
Cleanup Progress
Community Involvement
Site Documents
Redevelopment
Contacts

View pictures and videos of the Milltown Dam removal and Clark Fork River diversion

Press releases on the Milltown Dam breach and the Clark Fork River diversion:

January 28, 2008: Demolition of Milltown Dam Powerhouse near Missoula, Mont.

Milltown Dam is breached!
The Milltown Dam was completed in 1908 and around noon on Friday, March 28, 2008, a century later, the Milltown Dam was officially breached. This was an historical moment in both the cleanup of the Milltown Reservoir Sediments Superfund Site and in the rich cultural and natural history of the Milltown-Bonner area.

Approximately 1000 people, including Montana Governor Schweitzer, Senators Baucus and Tester, local legislators, city council members, tribal, state, federal, and local officials, community groups, and members of the public, gathered on the bluff overlooking the reservoir and near the dam. Everyone anxiously watched and waited as an excavator scooped out the last bit of soil and the dam was officially breached. Water trickled through slowly at first, gathering speed as more and more of the river flows were captured. The chasm deepened as more and more of the coffer dam eroded away. Then, just before dark Friday night, the Blackfoot River flows had been completely captured. Now the Clark Fork and Blackfoot Rivers are flowing freely downstream for the first time in over a century.

While much as been accomplished, more remains to be done. For the next year and a half, work crews will continue to excavate and load contaminated sediments onto rail cars (45 cars/day) en route to the Anaconda Smelter Superfund Site nearly 100 miles away. Later this summer, when river flows drop, workers will begin removing the rest of the Milltown Dam (divider block, radial gate and spillway). As the cleanup (remediation) continues, restoration and redevelopment of the site are beginning. The remediation should be done in 2010 and restoration should be completed by 2012. Redevelopment is ongoing. Hopefully, this Superfund site will one day become a state park.

Cleanup Progress

This innovative cleanup integrates remediation, restoration, and redevelopment and will:

Cleanup is underway!

Artist's rendition of the restored confluence of the Clark Fork and Blackfoot Rivers (PDF, 205 K; about PDF files)

Public Involvement the Cleanup Design

EPA has convened a Design Review Team to to work on the remedial design. The Design Review Team has been meeting periodically since the fall of 2005. Along with EPA, the State of Montana, the US Fish and Wildlife Service, and the Confederated Salish and Kootenai Tribes, Missoula County and the Clark Fork River Technical Assistance Committee are representing the public in design discussions. The Design Review Team continues to meet regularly to review and discuss site cleanup plans.

A number of new design documents and other site-related documents are available to the public. You can download the documents from this website (do not try to open them from the ftp site): ftp://publicmtpub05@64.25.133.122 and Clark Fork River Technical Assistance Committee.

Monitoring data (downloadable spreadsheet) is available in this ftp folder.

Background and Cleanup Goals

In December 2004, EPA, with the concurrence of the Montana Department of Environmental Quality, issued the Milltown Reservoir Sediments Record of Decision (ROD). ROD Summary fact sheet

The ROD contains 3 parts: Part One: The Declaration (8 page legal summary which EPA and DEQ signed); Part Two: Decision Summary (fully describes the selected remedy, including information leading to this decision); and Part Three: Responsiveness Summary (public comments and responses to those comments). The US Department of Interior/Fish and Wildlife Service and the Confederated Salish and Kootenai Tribes also concur with the Milltown Reservoir Record of Decision. There is no public comment on the Record of Decision. It is a final document.

Consent Decree negotiations (to determine who pays for and performs the work) were completed in the summer of 2005. Consent Decree fact sheet.

The 3 Rs: Remediation. Restoration. Redevelopment. The Milltown Reservoir Sediments cleanup (remediation) is being carefully planned and coordinated with the State of Montana's Natural Resource Damages Program, integrating remediation and restoration activities.

Redevelopment: Envisioning the Future

The Superfund cleanup (remediation) portion should be complete in 2009. The restoration work should be completed about 2 years later (2011). What will the area look like once the remediation and restoration are complete? What do we want to see in 5, 10, 20, or 50 years?

This is the question the commuity-based Milltown Redevelopment Working Group seeks to answer. This group of citizens was appointed by the Missoula County Commissioners in 2003 to work with their neighbors and other community members to examine possible land re-use and redevelopment options for the Milltown Superfund Site. In early 2005, after many meetings, public outreach and public comment, the Milltown Redevelopment Working Group presented a Conceptual Redevelopment Plan to the Missoula County Commissioners for consideration. The redevelopment plan (PDF, 58 pp, 8 MB) was adopted by the County in March 2005. Highlights of this plan include walking, biking, and equestrian trails in the Bonner-Milltown area, upgrading the Bonner pedestrian bridge over the Blackfoot River, and looking at ways to tell the stories of the area's rich history through historic preservation activities.

There are currently 3 Workgroup subcommittees:

Over the past couple of years, the Redevelopment Working Group has been raising funds to implement parts of the Conceptual Plan. The Working Group currently has about $4 million for various redevelopment projects. Recent examples include:

During the summer of 2007, the Working Group made presenatations to various area groups and neighbors about the Conceptual Plan and gathered some ideas about how to refine the "concepts" and move more towards designing what may one day become a state park or other state-managed property (e.g., fishing access site or wildlife management area). In September 2007, the Working Group hosted a "Design Workshop" where 30 participants (community members, experts from agencies, and volunteer landscape architects) spent 2 days talking and dreaming and ultimately coming up with designs for 3 potential park areas::

As currently envisioned, the lands owned by NorthWestern Energy Corporation in the area in and around the Milltown Reservoir Sediments Superfund Site would be converted to a publicly-owned park with trails, river access sites, bridges, interpretative signage, viewing area on the bluff overlooking the confluence of the Clark Fork and Blackfoot Rivers, and possibly an interpretative center. Ideally, a trail system would link the Milltown Gateway, Confluence and former Reservoir areas along the Blackfoot and Clark Fork Rivers as well as connecting to Missoula's Riverfront Trail system, extending the Kim Williams Trail along the Clark Fork River.

An interpretative center/signage is also envisioned, describing the history of the area from Glacial Lake Missoula to the Native Americans' road to the buffalo, Lewis and Clark's voyage of discovery, the mining and logging history, the construction of the Milltown Dam and Powerhouse, area poets and artists, to the present-day Superfund cleanup, river restoration and area redevelopment.

The Redevelopment Group meets the 4th Tuesday of each month at Our Saviour's Lutheran Church in Bonner. Meetings run from 6:30-9:00 pm, are free and open to the public. For more information, please contact Peter Nielsen, Missoula City-County Health Department, at (406) 258-4968 or Diana Hammer, EPA, at (406) 457-5040. Read the Redevelopment Working Group newsletter (PDF, 6 pp, 1.9 MB). More information about the Working Group.

Top of Page


Community Involvement

EPA strives to keep the community involved and informed about site activities through on-going community outreach and education efforts.

We welcome your ideas and comments!

Top of Page


Site Description

The Milltown Reservoir Sediments Site (Milltown Site) is an Operable Unit within a larger Superfund Site, the Milltown Reservoir Sediments/Clark Fork River Superfund Site. This Site includes approximately 120 miles of the Clark Fork River upstream of the Milltown Dam and Reservoir. The Milltown Dam and Reservoir are located at the confluence of the Clark Fork and Blackfoot Rivers, a few miles upstream of Missoula, in western Montana.

Behind the Dam are approximately 6.6 million cubic yards of contaminated sediments. Arsenic in the sediments has polluted the local drinking water aquifer and release of copper in the sediments threatens downstream fish and other aquatic life. These sediments were deposited over the past century, the result of historical mining operations upstream in Butte.

There are Superfund cleanup activities on-going throughout the Clark Fork Basin. EPA issued a Record of Decision in December 2004, calling for removal of the Milltown Dam and the most highly contaminated sediments. There was broad public support for this cleanup plan some 98% of the nearly 5,000 comments received during the public comment periods supported EPA's proposed plans.

The Milltown Site is located adjacent to the unincorporated communities of Milltown and Bonner. Other nearby unincorporated communities in the "Two Rivers Area" are Piltzville, West Riverside, Pine Grove, and East Missoula. Missoula, the county seat is 6 miles west of the Site. There are approximately 60,000 people in Missoula and 95,000 people in Missoula County.

Top of Page


Site Risk

Immediate risks to public health from a contaminated drinking water supply have been temporarily addressed .With the implementation of the Milltown Reservoir Sediments Record of Decision, EPA expects the Milltown drinking water supply to be cleaned up permanently. The groundwater should be clean within a decade following removal of the source of pollution (reservoir sediments contaminated with arsenic) and the Milltown Dam (which provides hydraulic pressure, driving the pollution into the Milltown groundwater).  

Media Affected Contaminants Source of Contamination
Groundwater, reservoir sediments arsenic, copper historic mining activity

Top of Page


Site Documents

To keep the public up to date about cleanup activities at the Milltown Reservoir Superfund Site, EPA produces weekly updates and maintains a site photo gallery.
cleanup activities. To plan and carryout the cleanup, EPA produces a number of technical documents such as the Record of Decision (ROD), monitoring plans, design work plans, etc.

Click on the links below to access the Milltown Reservoir site documents:

Note: many of the documents below are Adobe PDF files (about PDF files)

December 2007 Update: Cleanup Need and Cleanup Progress

Spring 2007 Update: Site Activities and Public Meeting (PDF, 12 pp, 918K)

Arsenic levels drop in Milltown water


It's been 16 years since residents of Milltown received official notice their arsenic-contaminated aquifer might be purified someday. Now well water test results indicate that process may have finally begun. Read more. Exit EPA disclaimer

Top of Page


Milltown Reservoir/Clark Fork River Contacts

EPA

Montana

Russ Forba, Project Manager, Milltown
Region 8, Montana Office
Federal Building
10 West 15th St., Suite 3200
Helena, MT 59626
(406) 457-5042
Email: forba.russ@epa.gov

Diana Hammer,
Community Involvement Coordinator
(406) 457-5040
Email: hammer.diana@epa.gov

Keith Large, Montana DEQ Project Officer
P.O. Box 200901
Helena, MT 59620
(406) 841-5039; or e-mail: klarge@mt.gov

   

View Documents at:

Technical Assistance Grant Group:

U.S. EPA, Montana Office
10 West 15th Street, Suite 3200
Helena, MT 59626
(406) 457-5046

EPA Butte Office
155 W. Granite
Butte, MT 59701
Ph:406-782-3838

Mansfield Library, University of Montana
Missoula, MT 59812
(406) 243-6860

Missoula Public Library
301 East Main
Missoula, MT 59802
(406) 721-2665

Hearst Free Library
3rd and Main
Anaconda, MT 59711
(406) 563-6932

Montana Tech Library
West Park
Butte, MT 59701
(406) 496-4281

Grant-Kohrs Ranch, National Historic Site
National Park Service
266 Warren Lane
Deer Lodge, MT 59722
Ph: 406-846-2070

Powell County Courthouse
Planning Office
409 Missouri
Deer Lodge, MT 59722
Ph: 406-846-3680

Clark Fork River Technical Assistance Committee
Mike Kustudia, President
P.O. Box 9086
Missoula, MT 59807
http://www.cfrtac.org


Local Navigation


Jump to main content.