End-of-Year 2006 BRAC Program Snapshot



Base Realignment and Closure (BRAC) Information Summary

BRAC Federal Facilities by BRAC Round
Pie chart: BRAC 1 - 18% (19), BRAC 2 - 24% (26), BRAC 3 - 26% (28), BRAC  4 - 32% (34)

NPL Status of BRAC Facilities

NPL Status Number of BRAC Facilities
Proposed
3
Final
35
Deleted
0
Soon to be Proposed
1
Non NPL
68
Total
107

Back To Top

Current Site Work
Bar Graph Showing Current Site Work: Ongoing Removals – 51, Active TAGs – 6, Ongoing RI/FS Actions – 81, Ongoing RDs – 13, Ongoing RAs – 58, Ongoing O&M – 40

Completed Site Work
Bar Graph Showing Completed Site Work: Removed Comps – 447, Decision Documents 633, RD 214, RA 251, OPS 43, 5 Year Reviews 53, Partial Deletions 4

BRAC Federal Facility Site Cleanup Pipeline
Federal Facility Cleanup Pipeline: NPL Facilities – 107, Facilities with IAGs – 34, Active RABs/SSABs – 70, Final Remedy Selected – 25, All Construction Completed – 10, Deleted Facilities – 0


Notes: All data from 10/16/2006 CERCLIS 3 except where noted. BRAC cleanup data includes both Superfund and RCRA activity at Superfund Federal Facilities.

Back To Top


Interagency Agreements

% of BRAC Federal Facilities with Completed IAGs
Federal Agencies that have not acheived 100% of their IAGs/FFAs:
Agency # w/ IAG Total # Percent
Navy 9 35 26.0%
Army 11 40 28.0%
USAF 12 29 41.0%
DoD 0 1 0.0%
Federal Agencies that have acheived 100% of their IAGs/FFAs:
Agency # w/ IAG Total # Percent
DLA 2 2 100.0%

Land Reuse

Number of Acres at BRAC Facilities Made Available for Reuse (in Thousands)
(at 95 Facilities)
Bar Graph Showing the Number of Acres at BRAC Facilities Made for Reuse: FY 96 – 90.8, FY 97 – 18.8, FY 98 – 22.4, FY 99 – 30.8, FY 00 – 52.8, FY 01 – 7.8, FY 02 – 13.5, FY 03 – 75.3, FY 04 – 78.3, FY 05 – 6.6, FY 06 – 3.4

* Total # of acres made available for reuse at Facilities with EPA involvement (BRAC, NPL, and Non-NPL = 508.8). Does not include property transferred between Federal Agencies.

Back To Top


Institutional Controls at BRAC Facilities

Remedial Actions and Removal Actions with Institutional Controls

Bar Graph Showing Remedial and Removal Actions with ICs: Remedial Actions – 137, Removals – 8
Note: There are 45 BRAC Federal Facilities with Institutional Controls.

Back To Top


Status of 5 Year Review Protectiveness Statements

Status of Remedies Requiring Monitoring at BRAC Facilities
Total Number of Sites with Completed 5 Year Reviews = 35
(Latest Protectiveness Statement at Site)
Bar Graph Showing Post-Construction Completion Activity at BRAC Facilities: Protective – 9, Will be Protective by Remedy Complete – 3, Protective in the Short Term – 10, Not Protective – 0, Protectiveness Deferred – 4, Complete – 9
Note: In the second quarter of FY 2005, EPA implemented a change in the way 5 Year Review data is recorded.

Back To Top


Environmental Indicators at Federal Facilities

EI Status for Final NPL BRAC Federal Facilities (CERCLA)
(Total Facilities = 35)


Bar Graph Showing the EI Status for Final NPL Federal Facilities (CERCLA): Controlled – 30, Insufficient Data – 3, Not Controlled – 2, Controlled – 17, Insufficient Data - 9, Not Controlled – 8, Not a GW Site – 1
Note: 49% of Facilities have both Human Exposure and Groundwater controlled; 3% of Facilities have neither Human Exposure nor Groundwater controlled

Back To Top


Notes:

  • All data from 10/16/2006 CERCLIS 3 except where noted.
    BRAC cleanup data includes both Superfund and RCRA activity at Superfund Federal Facilities.