Question: What must an operator consider in prioritizing pipe segments for assessment and re-assessment?
Answer: The risk posed by each pipeline segment covered by this rule must be considered in scheduling baseline assessments and periodic re-assessments. Risks must be evaluated using a risk assessment that meets ASME/ANSI B31.8S, Section 5, as required by 192.917(c). Section 5.10 of the standard specifically addresses use of risk assessment for prioritizing pipe segments for assessment.