Mercury Studies in the Florida Everglades
Anticipated Schedule
March 1995:
Begin sampling in northern Everglades Sites (ENR,L-39 canal, WCA2)
July-December 1995:
Continue sampling northern everglades sites, and add sites in L-67 canal and WCA3. Initiate intensive, short-term sampling in WCA2.
March-June 1996:
Continue sampling at established sites. Publish data on World Wide Web (WWW) and
write manuscripts for scientific journal publication.
October 1996-September 1997:
Continue sampling, and add more southern sites in WCA3and Taylor Slough. Write up annual reports and keep WWW database current.
October 1997-September 1998:
Continue sampling southern Everglades sites and add sites in Big Cypress National Preserve.
October 1998-Septerber 1999:
Write synthesis papers on basis of project result.
Return to Main Fact Sheet Page
Click here for a printable version of this fact sheet page (note: document will
open in a new browser window)
For more information contact:
David Krabbenhoft
U.S. Geological Survey
6417 Normandy Lane
Madison, WI 53719
(608) 276-3843
dpkrabbe@usgs.gov
Related information:
SOFIA Project: Aquatic Cycling of Mercury in the Everglades (ACME)
|