[Code of Federal Regulations]
[Title 40, Volume 8]
[Revised as of July 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR62.15400]

[Page 505]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 62_APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES 
AND POLLUTANTS--Table of Contents
 
    Subpart JJJ_Federal Plan Requirements for Small Municipal Waste 
        Combustion Units Constructed on or Before August 30, 1999
 
Sec. 62.15400  When must I submit a title V permit application for my 
existing small municipal waste combustion unit?

    (a) You must submit a complete title V permit application within 12 
months of when your source first becomes subject to a title V permitting 
program. See 40 CFR 70.3(a) and (b), 70.5(a)(1), 71.3(a) and (b), and 
71.5(a)(1). As provided in section 503(c) of the Clean Air Act, 
permitting authorities may establish permit application deadlines 
earlier than the 12-month deadline.
    (b) If your existing small MWC unit is not subject to an earlier 
permit application deadline, a complete title V permit application must 
be submitted not later than the date 36 months after promulgation of 40 
CFR part 60, subpart BBBB (December 6, 2003), or by the effective date 
of the applicable State, tribal, or Federal operating permits program, 
whichever is later. For any existing small MWC unit not subject to an 
earlier application deadline, this final application deadline applies 
regardless of when this Federal plan is effective, or when the relevant 
State or Tribal section 111(d)/129 plan is approved by EPA and becomes 
effective. See sections 129(e), 503(c), 503(d), and 502(a) of the Clean 
Air Act.
    (c) A ``complete'' title V permit application is one that has been 
determined or deemed complete by the relevant permitting authority under 
section 503(d) of the Clear Air Act and 40 CFR 70.5(a)(2) or 71.5(a)(2). 
You must submit a complete permit application by the relevant 
application deadline in order to operate after this date in compliance 
with Federal law. See sections 503(d) and 502(a); 40 CFR 70.7(b) and 
71.7(b).

                         Delegation of Authority