Sec. 8.8  Comprehensive environmental evaluation.

    (a) Preparation of a CEE. Unless a PERM or an IEE has been submitted 
and determined to meet the environmental documentation requirements of 
this part, the operator shall prepare a CEE. A CEE shall contain 
sufficient information to enable informed consideration of the 
reasonably foreseeable potential environmental effects of a proposed 
activity and possible alternatives to that proposed activity. A CEE 
shall include the following:
    (1) A description of the proposed activity, including its purpose, 
location, duration and intensity, and possible alternatives to the 
activity, including the alternative of not proceeding, and the 
consequences of those alternatives;
    (2) A description of the initial environmental reference state with 
which predicted changes are to be compared and a prediction of the 
future environmental reference state in the absence of the proposed 
activity;
    (3) A description of the methods and data used to forecast the 
impacts of the proposed activity;
    (4) Estimation of the nature, extent, duration and intensity of the 
likely direct impacts of the proposed activity;
    (5) A consideration of possible indirect or second order impacts 
from the proposed activity;
    (6) A consideration of cumulative impacts of the proposed activity 
in light of existing activities and other known planned activities;

[[Page 145]]

    (7) Identification of measures, including monitoring programs, that 
could be taken to minimize or mitigate impacts of the proposed activity 
and to detect unforeseen impacts and that could provide early warning of 
any adverse effects of the activity as well as to deal promptly and 
effectively with accidents;
    (8) Identification of unavoidable impacts of the proposed activity;
    (9) Consideration of the effects of the proposed activity on the 
conduct of scientific research and on other existing uses and values;
    (10) An identification of gaps in knowledge and uncertainties 
encountered in compiling the information required under this section;
    (11) A non-technical summary of the information provided under this 
section; and
    (12) The name and address of the person or organization which 
prepared the CEE and the address to which comments thereon should be 
directed.
    (b) Submission of Draft CEE to the EPA and Circulation to Other 
Parties. (1) Any operator who plans a nongovernmental expedition that 
would require a CEE must submit a draft of the CEE by December 1 of the 
preceding year. Within fifteen (15) days of receipt of the draft CEE, 
EPA will: send it to the Department of State which will circulate it to 
all Parties to the Protocol and forward it to the Committee for 
Environmental Protection established by the Protocol, and publish notice 
of receipt of the CEE and request for comments on the CEE in the Federal 
Register, and will provide copies to any person upon request. The EPA 
will accept public comments on the CEE for a period of ninety (90) days 
following notice in the Federal Register. The EPA, in consultation with 
other interested federal agencies, will evaluate the CEE to determine if 
the CEE meets the requirements under Article 8 and Annex I to the 
Protocol and the provisions of this part and will transmit its comments 
to the operator within 120 days following publication in the Federal 
Register of the notice of availability of the CEE.
    (2) The operator shall send a final CEE to EPA at least seventy-five 
(75) days before commencement of the proposed activity in the Antarctic 
Treaty area. The CEE must address and must include (or summarize) any 
comments on the draft CEE received from EPA, the public, and the 
Parties. Following the final response from the operator, the EPA will 
inform the operator if EPA, with the concurrence of the National Science 
Foundation, makes the finding that the environmental documentation 
submitted does not meet the requirements of Article 8 and Annex I of the 
Protocol and the provisions of this part. This notification will occur 
within fifteen (15) days of submittal of the final CEE by the operator 
if the final CEE is submitted by the operator within the time limits set 
out in this section. If no final CEE is submitted or the operator fails 
to meet these time limits, EPA will provide such notification sixty (60) 
days prior to departure of the expedition. If EPA does not provide such 
notice, the operator will be deemed to have met the requirements of this 
part provided that procedures, which include appropriate monitoring, are 
put in place to assess and verify the impact of the activity. The EPA 
will transmit the CEE, along with a notice of any decisions by the 
operator relating thereto, to the Department of State which shall 
circulate it to all Parties no later than sixty (60) days before 
commencement of the proposed activity in the Antarctic Treaty area. The 
EPA will also publish a notice of availability of the final CEE in the 
Federal Register.
    (3) No final decision shall be taken to proceed with any activity 
for which a CEE is prepared unless there has been an opportunity for 
consideration of the draft CEE by the Antarctic Treaty Consultative 
Meeting on the advice of the Committee for Environmental Protection, 
provided that no expedition need be delayed through the operation of 
paragraph 5 of Article 3 to Annex I of the Protocol for longer than 15 
months from the date of circulation of the draft CEE.
    (c) Decisions based on CEE. The decision to proceed, based on 
environmental documentation that meets the requirements under Article 8 
and Annex I to the Protocol and the provisions of this part, rests with 
the operator. Any decision by an operator on whether to proceed with or 
modify a

[[Page 146]]

proposed activity for which a CEE was required shall be based on the CEE 
and other relevant considerations.