Page vi, | INTRODUCTION Add the following paragraph at the end of the page: "Some bridge owners are collecting bridge condition ratings for items included in this Guide (Items 58-Deck, 59-Superstructure, 60-Substructure, and 62-Culvert) using the American Association of Highway and Transportation Officials' (AASHTO) Guide for Commonly Recognized (CoRe) Structural Elements. CoRe element inspection ratings provide detailed condition assessments that can serve as input into a comprehensive bridge management system (BMS). The FHWA has provided bridge owners with a computer program for translating bridge condition data in the CoRe element format to National Bridge Inventory (NBI) condition ratings for the purpose of NBI data submittal to FHWA. The purpose of the program is to permit bridge inspectors to record condition information in a format that satisfies both BMS and NBI data collection requirements." |
||||||||||||||||||||||||||||
Page x, | DEFINITION OF TERMS "(s)) Commonly recognized (CoRe) Structural Elements.) A group of structural elements endorsed by AASHTO as a means of providing a uniform basis for data collection for any bridge management system, to enable the sharing of data between States, and to allow for a uniform translation of data to NBI Items 58, 59, 60, and 62." | ||||||||||||||||||||||||||||
Page 5 | Item 6B, Critical Facility Indicator, will no longer be coded. Blank space will be inserted in its place. | ||||||||||||||||||||||||||||
Page 12 | Item 21 and Item 22 - The following additional codes will be added to the list of maintenance responsibility and owner codes: 61 - Indian Tribal Government 72 - Air Force 73 - Navy/Marines 74 - Army 75 - NASA 76 - Metropolitan Washington Airports Service | ||||||||||||||||||||||||||||
Page 16: | Item 32 - Approach Roadway Width, the example on the title line should be (XXX.X meters). On the first line of text it should read "Code a 4-digit number . . .". | ||||||||||||||||||||||||||||
Page 17 | Item 32 - Approach Roadway Width, in the examples the column showing the coding should read from top to bottom 0078, 0162, 0450, and 0288. |
||||||||||||||||||||||||||||
Page 22 | Item 39 - Navigation Vertical Clearance, the example on the title line should be (XXX.X meters). On the 4th line of text it should read ". . . as a 4-digit number . . .". In the examples the column showing the coding should read from top to bottom: 0500, 0206,and 0242. |
||||||||||||||||||||||||||||
Page 22 | Item 40 - Navigation Horizontal Clearance, the example on the title line should be (XXXX.X meters). On the 6th line of text it should read ". . . as a 5-digit number . . .". In the Examples the column showing the coding should read from top to bottom: 00535, 00950, and 02020. | ||||||||||||||||||||||||||||
Page 37 | Items 58 through 62 - Add the following sentence to the first paragraph: |
||||||||||||||||||||||||||||
Page 39 | Item 60 - Substructure, The 2nd paragraph is changed to the following:"All substructure elements should be inspected for visible signs of distress including evidence of cracking, section loss, settlement, misalignment, scour, collision damage, and corrosion. The rating factor given to Item 60 should be consistent with the one given to Item 113 whenever a rating factor of 2 or below is determined for Item 113 - Scour Critical Bridges." | ||||||||||||||||||||||||||||
Page 63 | Item 92C - Other Special Inspection, Guideline for maximum allowable interval between inspections will be changed to 60 months. | ||||||||||||||||||||||||||||
Page 67 | Item 100 - STRAHNET Highway Designation, The coding for this item is changed to the following:
|
||||||||||||||||||||||||||||
Page 75 | Item 113 - Scour Critical Bridges,the Item has been changed to the following:
Item 113 - Scour Critical Bridges1 digit Use a single-digit code as indicated below to identify the current status of the bridge regarding its vulnerability to scour. Evaluations shall be made by hydraulic/geotechnical/structural engineers.Guidance on conducting a scour evaluation is included in the FHWA Technical Advisory T 5140.23 titled, "Evaluating Scour at Bridges. "1Detailed engineering guidance is provided in the Hydraulic Engineering Circular 18 titled "Evaluating Scour at Bridges. "2Whenever a rating factor of 2 or below is determined for this item, the rating factor for Item 60 -- Substructure and other affected Items (i.e., load ratings, superstructure rating) should be revised to be consistent with the severity of observed scour and resultant damage to the bridge. A plan of action should be developed for each scour critical bridge (see FHWA Technical Advisory T 5140.23, HEC 18 and HEC 233). A scour critical bridge is one with abutment or pier foundation rated as unstable due to (1) observed scour at the bridge site (rating factor of 2, 1, or 0) or (2) a scour potential as determined from a scour evaluation study (rating factor of 3). It is assumed that the coding of this Item has been based on an engineering evaluation, which includes consultation of the NBIS field inspection findings.
1 FHWA Technical Advisory T 5140.23, Evaluating Scour at Bridges, dated October 28, 1991. | ||||||||||||||||||||||||||||
Page 77 | Item 116 - Minimum Navigation Vertical Clearance, Vertical Lift Bridge, the example on the title line should be (XXX.X meters). On the 1st line of text it should read ". . . code a 4-digit number . . .". In the examples the column showing the coding should read from top to bottom: 0106, and 0242. | ||||||||||||||||||||||||||||
Page B-5 | For the computation of "Y" (Width / Lane)the following will be added:
*A value of 10.9 meters will be substituted when Item 51 is coded "0000" or not numeric |
||||||||||||||||||||||||||||
Page B-8 | For the computation of "H" the following correction is for the electronic copy
If X > 1350 and Y > 4.6 < 4.9 Then H = 15((4.9-Y) / 0.3) % |
||||||||||||||||||||||||||||
Page B-13 | The scanned image in early printings was not scanned correctly. See A-1 for correct layout | ||||||||||||||||||||||||||||
Page D-1 | Definition of Items should read "Definition of Terms". | ||||||||||||||||||||||||||||
Page D-1 | Under Definition of Terms Item (b) should read "Culvert." | ||||||||||||||||||||||||||||
Page D-1 | Under Definition of Terms item (i) should read "Strategic Highway Corridor Network (STRAHNET). Replaces Defense Items,which were dropped." | ||||||||||||||||||||||||||||
Page E-1 | For Item No. 2 the Item Name should read "Highway Agency District". | ||||||||||||||||||||||||||||
Page E-1 | For Item No. 11 the Item Name should read "Kilometer Point". | ||||||||||||||||||||||||||||
Page E-4 | For Item No. 116 the Item Position should read "386 - 389" and the Item Length/Type should read "4/N". | ||||||||||||||||||||||||||||
Page E-4 | --Washington Headquarters Use Item Position should read "390 - 427". |