Prefabricated Bridge Elements and Systems in Japan and Europe
Summary Report-May 2004
FHWA International Technology Exchange Programs

PDF Version (1.4 mb)

Overview

The aging highway bridge infrastructure in the United States is being subjected to increasing traffic volumes and must be continuously renewed while accommodating traffic flow. The traveling public is demanding that this rehabilitation and replacement be done more quickly to reduce congestion and improve safety. Conventional bridge reconstruction is typically on the critical path because of the sequential, labor-intensive processes of completing the foundation, the substructure, the superstructure components (girders and decks), the railings, and other accessories. New bridge systems are needed that will allow components to be fabricated off-site and moved into place for quick assembly while maintaining traffic flow. Depending on the specific site conditions, the use of prefabricated bridge systems can minimize traffic disruption, improve work-zone safety, minimize disruption to the environment, improve constructibility, increase quality, and lower life-cycle costs. This technology is applicable and needed for both existing and new bridge construction. The focus of this initiative is on conventional routine bridges that make up the majority of the bridges in the United States.

To obtain information about technologies being used in other industrialized countries, a scanning tour of five countries was made in April 2004. The overall objectives of the scanning tour were to identify international uses of prefabricated bridge elements and systems and to identify decision processes, design methodologies, construction techniques, costs, and maintenance and inspection issues associated with use of the technology. The scanning team was, therefore, interested in all aspects of design, construction, and maintenance of bridge systems composed of multiple elements that are fabricated and assembled off-site. The elements consisted of foundations, piers or columns, abutments, pier caps, beams or girders, and decks. Bridges with span lengths in the range of 6 to 40 meters (20 to 140 ft) were the major focus, although longer spans were of interest if a large amount of innovative prefabrication was used.

The focus areas of the study were, therefore, prefabricated bridge systems that

  1. minimize traffic disruption,
  2. improve work zone safety,
  3. minimize environmental impact,
  4. improve constructibility,
  5. increase quality, and
  6. lower life-cycle costs.

The scanning tour was sponsored by the Federal Highway Administration (FHWA) and the American Association of State Highway and Transportation Officials (AASHTO) and organized by American Trade Initiatives, Inc. The eleven member team included three representatives from FHWA, four representatives from State DOTs, one representative from county engineers, one university representative, and two representatives from industry. The panel visited Japan, the Netherlands, Belgium, Germany, and France and held meetings and site visits with representatives of government agencies and private sector organizations. The countries were selected because of their known use of prefabricated systems. Visiting Japan was particularly important because of their seismic design requirements.

Summary of Initial Findings and Recommendations

At completion of the scanning tour, the team had identified 35 bridge technologies that, in one or more aspects, were different from current practices in the United States. Not all of these related to the primary objectives of the scanning tour. Using the six focus areas as selection criteria, the team identified nine overall technologies that are initially recommended for possible implementation in the United States. A brief description of each of the nine technologies is given in the following sections. The scanning team recommends that a detailed implementation plan be developed for these technologies.

Superstructure Systems

The typical sequence of erecting bridge superstructures in the United States is to erect the concrete or steel beams; place temporary formwork or stay-in-place steel or concrete panels, place deck reinforcement, cast deck concrete; and remove formwork if necessary. Elimination of the need to place and remove formwork for the deck can accelerate construction and improve safety. Two systems to accomplish this were identified during the tour.

Prefabricated deck panel cast monolithic with girder and cast-in-place reinforced deck.
Partial Depth Concrete Decks Prefabricated on Steel or Concrete Beams:

One system in Germany involved the casting of partial depth concrete decks on steel or concrete beams prior to erection of the beams. After the beams are erected, the edges of each deck unit abut the adjacent member and there is no need to place additional formwork for the cast-in-place concrete. This process speeds construction and reduces the potential danger of equipment falling onto the roadway below since a safe working surface is available immediately after beam erection.

2. Inverted T-beams with looped-bar connection
Poutre Dalle System:

Another method to eliminate formwork and provide a working surface is provided by a system known as the Poutre Dalle system. In this system, inverted T-beams are placed adjacent to each other and then made composite with cast-in-place concrete placed between the webs of the tees and over the tops of the stems to form a solid member.

Deck Systems

Four innovative ideas for bridge deck systems were identified and are recommended for implementation in the United States.

Full deck panel with closure pours
Full Depth Prefabricated Concrete Decks:

The use of full depth prefabricated concrete decks reduces construction time by eliminating the need to erect formwork and provide cast-in-place concrete. The deck panels are connected to steel beams through the use of studs located in pockets in the concrete deck slab. The use of full depth prefabricated concrete decks provides a means to accelerate bridge construction using a factory produced product.

4. Hybrid steel deck system ready for concrete placement
Hybrid Steel-Concrete Deck Systems:

The Japanese have developed hybrid steel-concrete slab systems for bridge decks. This steel component of the system consists of transverse beams that span between the longitudinal girders and cantilever beyond the edge girders. The bottom flanges of the transverse beams support steel formwork for the bottom of the slab while the top flanges support the longitudinal deck reinforcement. When filled with cast-in-place concrete, the system acts as a composite deck system. The system allows rapid placement of a lightweight deck formwork system complete with reinforcement without the use of heavy lifting equipment.

Deck joint details with looped bars connection
Deck Joint Closure Details:

Prefabricated deck systems require that longitudinal and transverse joints be provided to make the deck continuous for live load distribution. This is accomplished by using special loop bar reinforcement details in the joints. Various joint details observed during the tour should be developed for use in the United States to facilitate the use of prefabricated full depth deck systems.

Multiple corrosion protection system with sealer, membrane and asphalt layers
Multiple Level Corrosion Protection Systems:

In Japan, Germany, and France, concrete bridge decks are covered with a multiple level corrosion protection system to prevent the ingress of water and deicing chemicals. The systems generally involve providing adequate concrete cover to the reinforcement, a concrete sealer, waterproof membrane, and two layers of asphalt. This type of corrosion protection system may be beneficial with prefabricated systems as a means of protecting the joint regions from potential corrosion damage, thereby ensuring a longer service life.

Substructure Systems

One substructure system is recommended for implementation in the United States.

Prefabricated pier segment, form panels
The SPER System:

The SPER system is a method of rapid construction of piers using precast concrete panels as both structural elements and formwork for cast-in-place concrete. Tall hollow piers use panels for inner and outer formwork, while shorter solid piers use panels for the outer formwork only. Testing has shown that the system provides similar seismic resistance as a conventional cast-in-place system. The system has the advantage of more rapid construction with improved constructibility and quality.

Movement Systems

During the tour, many different methods that can be used to remove partial or complete existing bridges and move bridge components or complete bridges into place were observed. These methods allow a new bridge to be built at one location near or adjacent to the existing structure and then moved to its final location in a short period of time. Construction can, therefore, take place in an environment where construction operations are completely separated from the traveling public. These methods reduce traffic disruption times from months to hours or days, restore the use of existing highways in significantly less time, improve work zone safety, minimize environmental impact, and improve constructibility. This concept of building bridges off line and then moving them into place needs to be developed for use in the United States. Various systems for moving bridges and their components were identified during the tour.

Self propelled modular trailer moving a complete superstructure span into place
Self Propelled Modular Trailers:

In Europe, it was observed that large bridge components or even complete bridges weighing several thousand metric tons have been built at one location and then lifted and transported to their final location using a series of vehicles known as self propelled modular trailers (SPMTs). These multi-axle computer-controlled vehicles have the capability of moving in any horizontal direction while maintaining their payload geometry undeformed or distorted, horizontally, and keeping equal axle loads.

Other Bridge Installation Systems:

A completed concrete bridge constructed adjacent to an existing railroad embankment waiting to be launched transversely into place.

In addition to using conventional land and/or barge mounted cranes to erect large structures, special load frames have been developed to erect prefabricated components. One example is the modular jacking system used to erect prefabricated pylons on the Millau cable stayed bridge in France. The other methods of moving bridge components included the following:

  1. horizontally skidding or sliding bridges into place,
  2. incremental launching longitudinally over valleys or above existing highways,
  3. floating bridges into place using barges or by building a temporary dry dock,
  4. building bridges alongside an existing roadway and rotating them into place, and
  5. vertically lifting bridges.

These systems can be used to minimize the time that an existing bridge is out of service while it is replaced, many within 3 to 48 hours.

Planned Implementation Actions

The scanning team has already scheduled 17 presentations at national technical meetings sponsored by FHWA, AASHTO, and other organizations to disseminate information from the scanning tour. In addition, the team has formed a group to prepare Scanning Technology Implementation Plans for the technologies described above. Initial drafts of these plans will be reviewed during a meeting of the team in June 2004 prior to completion of the first draft of the scanning report.

Events

More Information

Contact

Vasant Mistry
Office of Bridge Technology
202-366-4599
E-mail Vasant

 
 
PDF files can be viewed with the Acrobat® Reader®
This page last modified on 05/12/08
 

FHWA
United States Department of Transportation - Federal Highway Administration