DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Declaration of Intention and Soliciting Comments, 
Motions To Intervene, and Protests

February 8, 2000.
    Take notice that the following application has been filed with the 
Commission and is available for public inspection:
    a. Application Type: Declaration of Intention.
    b. Docket No.: DI00-2-000.
    c. Date Filed: December 3, 1999.
    d. Applicant: Garkane Power Association, Inc.
    e. Name of Project: Glen Canyon-Paria Transmission Project.
    f. Location: In Kane County, Utah, and Coconino County, Arizona. 
The project occupies lands of the United States managed by the 
Department of the Interior's Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. Sec. 791(a)-
825(r).
    h. Applicant Contact: Mr. Michael Avant, Engineering Manager, 
Garkane Power Association, Inc., 1802 South 175 East, Kanab, Utah 84741 
(435) 644-5026, and Glen L. Ortman, Esq., Adrienne E. Clair, Esq., 
Verner, Liipfert, Benhard, McPherson and Hand, Chartered, 901 15th 
Street, NW, Suite 700, Washington, DC 20005-6000, (202) 371-6000.
    i. FERC Contact: Any questions on this notice should be addressed 
to Etta Foster at (202) 219-2679, or e-mail address: 
etta.foster@ferc.fed.us.
    j. Deadline for filing comments and or motions: March 13, 2000.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE, Washington, DC 20426.
    Please include the docket number (DI00-2-000) on any comments or 
motions filed.
    k. Description of Project: The existing project works consists of: 
a 138-kilovolt transmission line, extending about 36.1 miles from the 
Bureau of Reclamation's Glen Canyon Dam Powerhouse Switchyard to 
Garkane Power Association, Inc.'s Paria Substation, and apapurtenant 
facilities.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street, NE, Room 2A, Washington, 
DC 20426, or by calling (202) 208-1371. This filing may be viewed on 
http://www.ferc.fed.us/online/rims.htm (call (202) 208-2222 for 
assistance). A copy is also available for inspection and reproduction 
at the address in item h above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    Agency Comments--Federal, state, and local agencies are invited to 
file comments on the described application. A copy of the application 
may be obtained by agencies directly from the Applicant. If an agency 
does not file comments within the time specified for filing comments, 
it will be presumed to have no comments. One copy of an agency's 
comments must also be sent to the Applicant's representatives.

David P. Boergers,
Secretary.
[FR Doc. 00-3316 Filed 2-11-00; 8:45 am]
BILLING CODE 6717-01-M