[Federal Register: April 12, 2002 (Volume 67, Number 71)]
[Notices]               
[Page 17990-17991]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr12ap02-60]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application Accepted for Filing and Soliciting Motions 
To Intervene, Protests, and Comments

April 5, 2002.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12134-000.
    c. Date filed: October 12, 2001.
    d. Applicant: South Dakota Conservancy District.
    e. Name of Project: Dakota Pumped Storage Project.
    f. Location: On the Missouri River in Charles Mix and Gregory 
Counties, South Dakota.
    g. Filed Pursuant to: Federal Power Act, 16 USC Secs. 791(a)-
825)
    h. Applicant Contact: Gregg Greenfield, Chairman, South Dakota 
Conservancy District, 523 East Capitol Ave., Pierre, South Dakota 
57501-3181, (605) 773-4216.
    I. FERC Contact: Elizabeth Jones (202) 208-0246.
    j. Deadline for filing motions to intervene, protests and comments: 
60 days from the issuance date of this notice. This application is 
being noticed as a result of the Commission's Order Extending Filing 
Deadline For Notice of Intent issued on April 1, 2002 (99 FERC para. 
61,009).
    k. Competing Application: Project No. 12055-000.
    All documents (original and eight copies) should be filed with: 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426.
    Please include the Project Number (12134-000) on any comments, 
protests, or motions filed.
    The Commission's rules of practice and procedure require all 
interveners filing a document with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    l. Description of Project: The proposed project would use Lake 
Francis Case created by the U.S. Corps of Engineers' Fort Randall Dam 
as the lower reservoir and would consist of : (1) A proposed upper 
reservoir having a maximum surface area of 540-acres and a storage 
capacity of 24,000 acre-feet; a proposed forebay power intake; a 
proposed deflector dike extending 3,000 feet from the bankline outward 
and another 4,000 feet downstream in Lake Frances Case, (2) two 
proposed power tunnels, each 24-feet in diameter, with the lower, high 
pressure tunnel 7,665 feet long and the upper, low pressure tunnel 
1,250 feet long, (3) a proposed powerhouse containing four reversible 
turbines with capacities of 300 MW each for a total installed capacity 
of 1200 MW, (4) proposed minimum of two 345 kV transmission lines, and 
(5) appurtenant facilities.
    The project would have an estimated annual generation of 2.36 GWh.
    m. Copies of this filing are on file with the Commission and are 
available for public inspection. This filing may be viewed on the 
Commission's web site at http://www.ferc.gov using the ``RIMS'' link, 
select ``Docket #'' and follow the instructions ((202) 208-2222 for 
assistance). Comments, protests and interventions may be filed 
electronically via the Internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link.
    n. Preliminary Permit--Anyone desiring to file a competing 
application for preliminary permit for a proposed project must submit 
the competing application itself, or a notice of intent to file such an 
application, to the Commission on or before the specified comment date 
for the particular application (see 18 CFR 4.36). Submission of a 
timely notice of intent allows an interested person to file the 
competing preliminary permit application no later than 30 days after 
the specified comment date for the particular application. A competing 
preliminary permit application must conform with 18 CFR 4.30(b) and 
4.36.
    o. Preliminary Permit--Any qualified development applicant desiring 
to file a competing development application must submit to the 
Commission, on or before a specified comment date for the particular 
application, either a competing development application or a notice of 
intent to file such an application. Submission of a timely notice of 
intent to file a development application allows an interested person to 
file the competing application no later than 120 days after the 
specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    p. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    q. Proposed Scope of Studies under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    r. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of rules of practice and procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.

[[Page 17991]]

    s. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the Project 
Number of the particular application to which the filing refers. Any of 
the above-named documents must be filed by providing the original and 
the number of copies provided by the Commission's regulations to: The 
Secretary, Federal Energy Regulatory Commission, 888 First Street, 
NE.,Washington, DC 20426. An additional copy must be sent to Director, 
Division of Hydropower Administration and Compliance, Federal Energy 
Regulatory Commission, at the above-mentioned address. A copy of any 
notice of intent, competing application or motion to intervene must 
also be served upon each representative of the Applicant specified in 
the particular application.
    t. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Magalie R. Salas,
Secretary.
[FR Doc. 02-8920 Filed 4-11-02; 8:45 am]