[Federal Register: November 18, 2002 (Volume 67, Number 222)]
[Notices]               
[Page 69515-69516]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr18no02-38]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2197-056]

 
Alcoa Power Generating Inc.; Notice Granting Late Intervention

November 8, 2002.
    On September 6, 2002, the Commission issued a notice of the request 
for a temporary license amendment to deviate from reservoir drawdown 
schedules and refill requirements, filed August 29, 2002, by Alcoa 
Power Generating Inc., for the Yadkin Project No. 2197, located on the 
Yadkin/Pee Dee River in Montgomery, Stanley, Davidson, Rowan, and Davie 
Counties, North Carolina. The notice established October 7, 2002, as 
the deadline for filing motions to intervene in the proceeding.
    On October 16, 2002, a motion to intervene was filed late by Mr. 
Jim L. Shuping. Granting the late motion to intervene will not unduly 
delay or disrupt the proceeding or prejudice other parties to it. 
Therefore, pursuant to Rule 214,\1\ the late motion to intervene filed 
in this proceeding by Mr.

[[Page 69516]]

Jim L. Shuping is granted, subject to the Commission's rules and 
regulations.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.214 (2001).

Magalie R. Salas,
Secretary.
[FR Doc. 02-29138 Filed 11-15-02; 8:45 am]

BILLING CODE 6717-01-P