[Federal Register: September 12, 2002 (Volume 67, Number 177)]
[Notices]               
[Page 57806-57807]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr12se02-60]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application Accepted for Filing and Soliciting Motions 
To Intervene, Protests, and Comments

September 6, 2002.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12209-000.
    c. Date filed: June 6, 2002.
    d. Applicant: Three Mile Falls Hydro, LLC.
    e. Name of Project: Three Mile Falls Diversion Dam Hydroelectric 
Project.
    f. Location: At an existing diversion dam owned by the U.S. Bureau 
of Reclamation (USBR) on the Umatilla River in Umatilla County, Oregon. 
Part of the project would be on lands administered by the USBR.
    g. Filed pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Brent L. Smith, Northwest Power Services, 
Inc., P.O. Box 535, Rigby, Idaho 83442 (208) 745-0834.
    i. FERC Contact: Regina Saizan, (202) 502-8765.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE, Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12209-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
interveners filing a document with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project would be located at 
an existing diversion dam owned by the USBR and would consist of: (1) A 
proposed 84-inch-diameter steel penstock approximately 300 feet long, 
(2) a proposed powerhouse containing one turbine generator having a 
total installed capacity of 1 MW, (3) a proposed 1-mile-long, 15 kV 
transmission line, and (4) appurtenant facilities. The project would 
have an annual generation of 4.8 GWh.
    l. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
http://www.ferc.gov using the ``FERRIS'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, call ( 202) 502-8222 or for TTY, (202) 
208-1659. A copy is also available for inspection and reproduction at 
Three Mile Falls Hydro, LLC, 975 South State Highway, Logan, UT 84321, 
(435) 752-2580.
    m. Competing Preliminary Permit--Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 
4.30(b) and 4.36.
    n. Competing Development Application--Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    o. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit if such an application may be filed, either a preliminary permit 
application or a development application (specify which type of 
application). A notice of intent must be served on the applicant (s) 
named in this public notice.
    p. Proposed Scope of Studies under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to

[[Page 57807]]

intervene in accordance with the requirements of Rules of Practice and 
Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate 
action to take, the Commission will consider all protests or other 
comments filed, but only those who file a motion to intervene in 
accordance with the Commission's Rules may become a party to the 
proceeding. Any comments, protests, or motions to intervene must be 
received on or before the specified comment date for the particular 
application.
    r. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the Project 
Number of the particular application to which the filing refers. Any of 
the above-named documents must be filed by providing the original and 
the number of copies provided by the Commission's regulations to: The 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. An additional copy must be sent to Director, 
Division of Hydropower Administration and Compliance, Federal Energy 
Regulatory Commission, at the above-mentioned address. A copy of any 
notice of intent, competing application or motion to intervene must 
also be served upon each representative of the Applicant specified in 
the particular application.
    s. Agency Comments--Federal, State, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Magalie R. Salas,
Secretary.
[FR Doc. 02-23208 Filed 9-11-02; 8:45 am]
BILLING CODE 6717-01-P