[Federal Register: December 4, 2002 (Volume 67, Number 233)]
[Notices]               
[Page 72161-72162]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr04de02-63]                         


-----------------------------------------------------------------------


DEPARTMENT OF ENERGY


Federal Energy Regulatory Commission


[Project No. 4914]


 
Notice of Application Tendered for Filing With the Commission, 
Soliciting Additional Study Requests, and Establishing Procedural 
Schedule for Relicensing and a Deadline for Submission of Final 
Amendments


November 27, 2002.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 4914.
    c. Date Filed: November 20, 2002.
    d. Applicant: International Paper Company.
    e. Name of Project: Nicolet Mill Dam Project.
    f. Location: At the U.S. Army Corps of Engineers' DePere Dam, on 
the Fox River, in the City of DePere, Brown County, Wisconsin.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C.791(a)-825(r).
    h. Applicant Contacts: Licensee Contact: Thomas Piette, 
International Paper Company, 200 Main Avenue, De Pere, WI 54115, (920) 
336-4211.
    i. FERC Contact: Peter Leitzke, (202) 502-6059 or 
peter.leitzke@ferc.gov.
    j. Cooperating agencies: We are asking Federal, state, local, and 
tribal agencies with jurisdiction and/or special expertise with respect 
to environmental issues to cooperate with us in the preparation of the 
environmental document. Agencies who would like to request cooperating 
status should follow the instructions for filing comments described in 
item l below.
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: December 27, 2002.
    All documents (original and eight copies) should be filed with: 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Please include the project 
number (P-4914-010) on any documents filed.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    Additional study requests and requests for cooperating agency 
status may be filed electronically via the


[[Page 72162]]


Internet in lieu of paper. The Commission strongly encourages 
electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions 
on the Commission's Web sitehttp://www.ferc.govunder the ``e-Filing'' 
link.
    m. This application is not ready for environmental analysis at this 
time.
    n. The existing Nicolet Mill Dam Project consists of the following 
existing facilities: (1) A 13.6 foot-high, 400-foot-long diversion 
structure attached to the westerly end of the U.S. Army Corps of 
Engineers' DePere Dam; (2) intake works consisting of 28 gates screened 
with steel racks; (3) a powerhouse containing two generating units with 
a total installed capacity of 1,080 kW; and (4) other appurtenances.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``FERRIS'' link. 
Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, call 1-866-208-
3676 or for TTY, (202) 502-8659. A copy is also available for 
inspection and reproduction at the address in item h above.
    p. With this notice, we are initiating consultation with the 
Wisconsin State Historic Preservation Officer (SHPO), as required by 
Sec.  106, National Historic Preservation Act, and the regulations of 
the Advisory Council on Historic Preservation, 36 CFR 800.4.
    q. Procedural schedule and final amendments: The application will 
be processed according to the following Hydro Licensing Schedule. 
Revisions to the schedule will be made as appropriate.
    Issue Acceptance or Deficiency Letter: January 2003.
    Issue Scoping Document for comments: March 2003.
    Notice of Application is Ready for Environmental Analysis: June 
2003.
    Notice of the availability of the EA: October 2003.
    Ready for Commission's decision on the application: December 2003.
    Unless substantial comments are received in response to the EA, 
staff intends to prepare a single EA in this case. If substantial 
comments are received in response to the EA, a final EA will be 
prepared with the following modifications to the schedule.
    Notice of the availability of the final EA: February 2004.
    Ready for Commission's decision on the application: March 2004.
    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.


Linwood A. Watson, Jr.,
Deputy Secretary.
[FR Doc. 02-30715 Filed 12-3-02; 8:45 am]

BILLING CODE 6717-01-P