DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application for Amendment of License and Soliciting 
Comments, Motions To Intervene, and Protests

March 30, 2007.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Request for Temporary Variance of Minimum 
Flow Requirement.
    b. Project No.: 618-137.
    c. Date Filed: March 30, 2007.
    d. Applicant: Alabama Power Company.
    e. Name of Project: Jordan Dam.
    f. Location: On the Coosa River, in Elmore, Chilton, and Coosa 
Counties, Alabama.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. Sec. Sec.  791a-
825r.
    h. Applicant Contact: Alan L. Peeples, Alabama Power Company, 600 
N.18th Street, P.O. Box 2641, Birmingham, AL 35291, (205) 257-1401.
    i. FERC Contact: Peter Yarrington, peter.yarrington@ferc.gov, (202) 
502-6129.
    j. Deadline for filing comments, motions to intervene and protests: 
April 16, 2007.
    All documents (original and eight copies) should be filed with: 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency. A copy 
of any motion to intervene must also be served upon each representative 
of the Applicant specified in the particular application.
    k. Description of Request: The Alabama Power Company (APC) is 
requesting a temporary variance of the minimum flow requirement of the 
project license. Because of persistent drought conditions in the 
project area and the need to conserve water, APC requests that it be 
allowed to release from the Jordan Dam Project 3,000 cubic feet per 
second (cfs) April 1-June 15, 2007, instead of the 4,000 cfs required 
in the project license. Further, APC proposes to suspend the pulse flow 
release of 8,000 cfs during this period. Beginning June 16, 2007, the 
APC would return to flow release requirements specified in the license. 
Included in APC's request were concurrences received from the state and 
federal resource agencies.
    l. Location of the Application: The filing is available for 
inspection and reproduction at the Commission's Public Reference Room, 
located at 888 First Street, NE, Room 2A, Washington, DC 20426 or by 
calling (202) 502-8371, or by calling (202) 502-8371. This filing may 
also be viewed on the

[[Page 16784]]

Commission's Web site at http://ferc.gov using the ``eLibrary'' link. 

Enter the docket number excluding the last three digits in the docket 
number field to access the document. You may also register online at 
http://www.ferc.gov/docsfiling/esubscription.asp to be notified vial e-

mail or new filings and issuances related to this or other pending 
projects. For assistance, call 1-866-208-3676 or e-mail 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 

also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Any filings must bear in all capital letters the title 
``COMMENTS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, 
and the Project Number of the particular application to which the 
filing refers.
    p. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.
    q. Comments, protests and interventions may be filed electronically 
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(I)(iii) and 
the instructions on the Commission's Web site at http://www.ferc.gov 

under the ``e-Filing'' link.

Philis J. Posey,
Acting Secretary.
 [FR Doc. E7-6327 Filed 4-4-07; 8:45 am]