[Federal Register: May 29, 2001 (Volume 66, Number 103)]
[Notices]               
[Page 29110-29111]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr29my01-50]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EG01-214-000, et al.]

 
Desert Power, L.P., et al.; Electric Rate and Corporate 
Regulation Filings

May 21, 2001.
    Take notice that the following filings have been made with the 
Commission:

1. Desert Power, L.P.

[Docket No. EG01-214-000]

    Take notice that on May 17, 2001, Desert Power, L.P.(Applicant), a 
limited partnership with its principal place of business at 5847 San 
Felipe, Suite 2900, Houston, TX 77057, filed with the Federal Energy 
Regulatory Commission (Commission) an application for determination of 
exempt wholesale generator status pursuant to Part 365 of the 
Commission's regulations.
    Applicant proposes to construct, own and operate a natural gas-
fired power plant with a nameplate rating of 80 MW in Rowley, Tooele 
County, Utah. The proposed power plant is projected to commence 
commercial operation on or about July 1, 2001. All output from the 
plant will be sold by Applicant exclusively at wholesale.
    Comment date: June 11, 2001, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

2. Deseret Generation & Transmission Co-operative

[Docket No. ER01-2057-000]

    Take notice that on May 16, 2001, Deseret Generation & Transmission 
Co-operative tendered for filing an informational filing in compliance 
with its rate schedules. The filing sets forth the revised approved 
costs for member-owned generation resources and the revised approved 
reimbursements under its Resource Integration Agreements with two of 
its members, Garkane Power Association, Inc., and Moon Lake Electric 
Association, Inc. A copy of this filing has been served upon all of 
Deseret's members.
    Comment date: June 6, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

3. Sierra Pacific Power Company, Nevada Power Company

[Docket No. ER01-1527-001, and ER01-1529-001]

    Take notice that on May 15, 2001, Sierra Pacific Power Company 
(SPPC)

[[Page 29111]]

and Nevada Power Company (NPC) tendered for filing revised tariff 
sheets as required by Ordering Paragraph (B) of the Commission's May 
11, 2001 Order in the above noted dockets.
    Comment date: June 5, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

4. Consumers Energy Company

[Docket Nos. ER92-331-008, and ER92-332-008]

    Take notice that on May 16, 2001, Consumers Energy Company 
(Consumers) tendered for filing the following substitute tariff sheets 
as part of its FERC Electric Tariff No. 5 in compliance with the April 
16, 2001 order, and previous orders, issued in these proceedings:

Sub Original Sheet Nos. 2.00, 10.00, 11.00 and 12.00.

    The first sheet listed is to have an effective date of June 
21,1993. The remaining three sheets are to have an effective date of 
May 2, 1992. Copies of these sheets were served upon the Michigan 
Public Service Commission and upon those on the official service lists 
in these proceeding.
    Comment date: June 6, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

5. Pilot Power Group, Inc.

[Docket No. ER01-1699-001]

    Take notice that on May 14, 2001, Pilot Power Group, Inc. (Pilot) 
tendered for filing for acceptance of Pilot Rate Schedule FERC No. 1 
(the Rate Schedule); the granting of certain blanket approvals, 
including the authority to sell electricity at market-based rates; and 
the waiver of certain Commission regulations. In its Petition, Pilot 
also requested that the Commission grant blanket authority for retail 
end-use customers of Pilot to sell to Pilot excess electricity not 
required for delivery to said customers at market-based rates pursuant 
to the Rate Schedule, and grant waiver of certain Commission 
regulations.
    By letter order dated April 30, 2001, the Commission granted 
Pilot's petition, conditioned upon Pilot re-filing with the Commission 
its Rate Schedule with the proper designations, within 30 days of the 
order. On May 10, 2001, Pilot filed with the Commission its Rate 
Schedule amended to include the proper designations.
    Comment date: June 4, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

6. Arizona Public Service Company

[Docket No. ER01-2055-000]

    Take notice that on May 16, 2001, Arizona Public Service Company 
(APS) tendered for filing an Interconnection and Operating Agreement 
with Pinnacle West Energy under APS' Open Access Transmission Tariff.
    A copy of this filing has been served on Pinnacle West Energy and 
the Arizona Corporation Commission.
    Comment date: June 6, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

7. Avista Corporation

[Docket No. ER01-2056-000]

    Take notice that on May 16, 2001, Avista Corporation tendered for 
filing a Service Agreement assigned Rate Schedule FERC No. 65, 
previously filed with the Federal Energy Regulatory Commission by 
Avista Corporation, formerly known as The Washington Water Power 
Company, under the Commission's Docket No. ER95-806-000 with Dynegy 
Power Marketing, Inc., formerly dba Electric Clearinghouse, Inc., is to 
be terminated, effective May 7, 2001 by the request of Dynegy Power 
Marketing, Inc., per its letter dated April 30, 2001. Notice of the 
cancellation has been served upon the following:
    Comment date: June 6, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

8. Entrust Energy, L.L.C.

[Docket No. ER01-2059-000]

    Take notice that on May 16, 2001, Entrust Energy, L.L.C. (EEPM) 
tendered for filing to the Commission for acceptance of Entrust Energy 
Rate Schedule FERC No. 1; the granting of certain blanket approvals, 
including the authority to sell electricity at market-based rates; and 
the waiver of certain Commission regulations.
    Entrust Energy intends to engage in wholesale electric power and 
energy purchases and sales as a marketer. Entrust Energy is not in the 
business of generating or transmitting electric power. Entrust Energy 
is a Limited Liability Company.
    Comment date: June 6, 2001, in accordance with Standard Paragraph E 
at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest such filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be considered by the Commission in determining the appropriate action 
to be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of these filings are on file with the Commission and 
are available for public inspection. This filing may also be viewed on 
the Internet at http://www.ferc.fed.us/ online/rims.htm (call 202-208-
2222 for assistance). Comments, protests, and interventions may be 
filed electronically via the internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's web site 
at http://www.ferc.fed.us/efi/doorbell.htm.

David P. Boergers,
Secretary.
[FR Doc. 01-13350 Filed 5-25-01; 8:45 am]
BILLING CODE 6717-01-P