[Federal Register: February 28, 2005 (Volume 70, Number 38)]
[Rules and Regulations]               
[Page 9532]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr28fe05-8]                         

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[CGD08-05-011]

 
Drawbridge Operation Regulations; Port Aransas Channel--Tule 
Lake, TX

AGENCY: Coast Guard, DHS.

ACTION: Notice of temporary deviation from regulations.

-----------------------------------------------------------------------

SUMMARY: The Commander, Eighth Coast Guard District, has issued a 
temporary deviation from the regulation governing the operation of the 
Tule Lake Vertical Lift Span Highway and Railroad Bridge across the 
Corpus Christi--Port Aransas Channel, mile 14.0, at Corpus Christi, 
Nueces County, Texas. This deviation allows the bridge to remain closed 
to navigation for four hours on two consecutive days. This temporary 
deviation is necessary for the removal of scaffolding used during the 
maintenance of the rope sheaves and for the cleaning and lubrication of 
the haul and counterweight ropes of the drawbridge.

DATES: This deviation is effective from 7 a.m. on Wednesday, March 16, 
2005, through 11 a.m. on Thursday, March 17, 2005.

ADDRESSES: Materials referred to in this document are available for 
inspection or copying at the office of the Eighth Coast Guard District, 
Bridge Administration Branch, Hale Boggs Federal Building, room 1313, 
501 Magazine Street, New Orleans, Louisiana 70130-3396 between 7 a.m. 
and 3 p.m., Monday through Friday, except Federal holidays. The 
telephone number is (504) 589-2965. The Bridge Administration Branch of 
the Eighth Coast Guard District maintains the public docket for this 
temporary deviation.

FOR FURTHER INFORMATION CONTACT: David Frank, Bridge Administration 
Branch, telephone (504) 589-2965.

SUPPLEMENTARY INFORMATION: The Port of Corpus Christi Authority has 
requested a temporary deviation in order to remove scaffolding from the 
bridge that was required to perform scheduled maintenance on the Tule 
Lake vertical lift span bridge across Corpus Christi--Port Aransas 
Channel, mile 14.0 at Corpus Christi, Nueces County, Texas. This 
temporary deviation will allow the bridge to remain in the closed-to-
navigation position from 7 a.m. to 11 a.m. on Wednesday, March 16, 
2005, and from 7 a.m. to 11 a.m. on Thursday, March 17, 2005.
    The vertical lift span bridge has a vertical clearance of 9.0 feet 
above mean high water, elevation 1.0 feet Mean Sea Level and 11.0 feet 
above mean low water, elevation -1.0 Mean Sea Level in the closed-to-
navigation position. Navigation at the site of the bridge consists 
mainly of oil tankers and tows with barges. There is no recreational 
pleasure craft usage at the bridge site. Due to prior experience, as 
well as coordination with waterway users, it has been determined that 
this two-day partial closure will not have a significant effect on 
these vessels. The bridge normally opens to pass navigation an average 
of 850 times per month. The bridge opens on signal as required by 33 
CFR 117.5. The bridge will be able to open for emergencies during the 
closure period. Alternate routes are not available.
    In accordance with 33 CFR 117.35(c), this work will be performed 
with all due speed in order to return the bridge to normal operation as 
soon as possible. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.

    Dated: February 15, 2005.
Marcus Redford,
Bridge Administrator.
[FR Doc. 05-3761 Filed 2-25-05; 8:45 am]