|
|
Purpose and Need for the Proposed Project...
INTRODUCTION
The Federal Highway Administration (FHWA) is responsible for the development
of this project as administrator of the Forest Highway Program (FHP) federal funds, and is the action agency
under the National Environmental Policy Act of 1969 (NEPA), as revised.
The U.S. Forest Service (USFS) and the Wyoming Department of Transportation
(WYDOT) are cooperating FHP agencies. Highways designated for projects
under the FHP in Wyoming are selected at an annual Program Agency
meeting of the FHWA, USFS, and WYDOT. The routes selected are those
that serve both the national forests and the state (or counties where
appropriate), and have the greatest need for improvement. The FHP
agencies authorized the scoping and planning for the project design
and construction.
The FHWA, under NEPA and USC Title 23, is required to balance transportation
needs, costs, environmental resources, safety, and public input in
order to arrive at objective, responsible transportation decisions.
This statement of Purpose and Need has been developed by the FHWA
and cooperating agencies from the viewpoint of defining transportation
needs for this project.
PURPOSE AND NEED
The purpose of this proposed project is to provide a safe roadway
for access to the Forest and the multiple use opportunities it offers
Forest visitors. This includes accommodating the projected increase
in traffic volumes from growth of recreational use of the Forest,
consistent with the Forest Land and Resource Management Plan, and
constructing an environmentally sensitive roadway to modern standards
which can be reasonably maintained by public revenues.
The route is inadequate for present traffic volumes and characteristics,
and is substandard for its entire length. It was also determined that
in its present condition, WY FH 23 cannot satisfy future traffic demands
or safety requirements, or Forest resource management objectives and
maintenance capabilities.
The needs for the road were refined through a series of public meetings,
agency partnering meetings with the Social, Economic, and Environmental
Team and Loop Road Steering Committee, and public surveys. Local,
county, state, and Federal branches of the government, resource management
agencies, environmental groups, and local citizens all contributed
to the process. The purpose of this project, agreed upon through these
meetings, includes:
|
Improving road safety |
|
Accommodating increased traffic volumes for projected
growth in USFS multiple use activities |
|
Providing an easily maintained, engineered roadway |
The proposed project would address five general types of needs: roadway
deficiencies, traffic volume and road users,
maintenance issues, roadway
safety issues , and social and economic conditions.
Roadway Deficiencies
The geometrics of WY FH 23 were designed
to accommodate vehicles and traffic volumes of the early 1930's and
display characteristics of the era when it was constructed. The nature
of accident history, current and projected traffic volumes and characteristics,
and existing maintenance requirements render existing WY FH 23 substandard
for current and future needs. Specific roadway deficiency concerns,
include the following:
|
Steep grades, especially in the first half of
the proposed project, are unable to hold gravel surfacing in
place, which has left the roadway without any gravel surfacing,
leaving a native dirt surface with exposed rocks; |
|
Roadway shoulders or adequate drainage ditches
cannot be provided in many locations due to limited width; |
|
No roadside area is available to accommodate
driver error or to install safety devices, such as guardrails; |
|
The road surface cannot be maintained in a crowned
condition to shed water and, with steep grades and inadequate
ditches, erosion of the road surface occurs causing washboard
surfaces and sedimentation of surface water and wetlands; |
|
Roadway widths are too narrow in many locations
to safely accommodate passing of oncoming vehicles, especially
school buses, recreational vehicles, and trucks with livestock
trailers; |
|
Impaired sight distance in several locations
causes reduced traffic capacity and passing difficulties, and
excessive dust further reduces the sight distance along the
roadway; |
|
The roadway lacks designed scenic-vista or slow-traffic
pullouts; and |
|
The switchback curves were originally constructed
with small turning radii that do not accommodate today's larger
vehicles. |
Traffic Volume and Road Users
Data for 1992 indicated that the SADT
volume was approximately 350 vehicles per day (vpd) at Bruce's Bridge.
Data collected from 1997 indicated that weekend volumes were 468 vpd
just south of Bruce's Bridge and 314 vpd just south of Worthen Meadow
Road. The growth rate of traffic on WY FH 23 between 1989 and 1999
was 2.3 percent annually.
The WYDOT forecasts an annual growth rate of 2.5 percent for traffic
volumes on SH 131. Using this forecasted annual growth rate, the 2023
SADT (twenty years after construction) is expected to range between
1090 vpd in Sinks Canyon and 240 vpd south of Worthen Meadow Road
with no provision of additional or improved facilities or resource
management activities within the Forest.
Individuals using Forest resources for recreational purposes constitute
the majority of traffic on WY FH 23. The Forest Plan contains specific
management prescriptions along the WY FH 23 corridor. Resources are
to be managed for emphasis on "rural and roaded natural recreation
opportunities" in this area. Motorized and non-motorized recreational
activities, such as driving for pleasure, viewing scenery and wildlife,
picnicking, fishing, hiking, horseback riding, cross-country biking,
and cross-country skiing, are possible. Thus, vehicle characteristics
are expected to be a mix of passenger cars, RVs, bicycles, school
buses, commercial and recreational car/truck and trailer combinations,
and passenger vans modified for the physically disadvantaged. National
trends indicate an increasing percentage of traffic will consist of
senior drivers (AASHTO, 1994).
WY FH 23 provides the only access to Fremont County Youth Camp on
Worthen Meadow Road. A safe and adequate transportation route is essential
for youth camp employees, attendees, and suppliers. The youth camp
served more than 1,200 youths in 13 camps in 1992 and more than 1,600
youths in 15 camps in 1996. Camp sessions range from a weekend to
2 or 3 weeks in length, beginning in June of each year until the end
of August. The youth are transported to the camp by school bus or
car, and are taken to camp activity destinations by bus on WY FH 23.
WY FH 23 is used on a regular basis by bus drivers, delivery persons,
and other vehicles servicing the youth camp.
Maintenance Issues
With the exception of some minor modifications
and re-graveling in some areas, WY FH 23 has received only minimal
maintenance to sustain a nominal surface and marginal drainage structures
and ditches. The existing roadside soils are highly erodible, resulting
in an eroded driving surface and hazardous washout conditions over
segments of the road.
The road's poor surface condition and narrow width make it difficult
to provide a continually free-draining and moderate-quality riding
surface. In order to provide a serviceable roadway with a reasonable
surface given current conditions, WY FH 23 should receive very frequent
maintenance.
The USFS's annual maintenance budget for WY FH 23 varies from $2,000
to $6,000 per year. Due to this constrained budget, the northern 11.6
km (7.2 mi) is graded approximately three times per year and the remainder
is graded once per year. Ditch and culvert clearing is conducted every
3 years. The USFS does not recommend increasing their annual maintenance
schedule because the absence of surface material negates the return
on any increased maintenance expenditure. Due to the intense maintenance
requirements of the existing roadway, there is a significant need
for road improvements to provide a facility that could be maintained
in a serviceable condition with a reasonable expenditure of public
funds.
Early in the project development process Fremont County signed an
agreement with the FHWA to operate and maintain Louis Lake Road pending
reconstruction of the roadway. In 2000, they reaffirmed their commitment
to accept jurisdiction for maintenance once the road was reconstructed.
Fremont County rescinded their decision to accept jurisdiction for
maintenance in March 2001, and accepted jurisdiction again in July
2001.
Roadway Safety Issues
The design deficiencies, projected traffic
volumes, and maintenance limitations of WY FH 23, coupled with the
accident history on the roadway, suggest that a roadway constructed
to modern highway standards would provide a safer traveling environment
for the user with the potential to reduce accident rates (accidents
per million vehicle-miles traveled).
Accident data for WY FH 23 from May 1989 to May 1992 indicate 27 reported
accidents. Eleven accidents involved injuries, but no fatalities.
Most of the accidents involved either one or two vehicles on sharp
curves. Of these, accident reports indicate that the narrowness and
impaired sight distance of the turns were a contributing factor. Other
accident reports identified soft shoulders, loose gravel, driver inexperience,
and driver inattention as causes. Four were related to alcohol and
only two cited excessive speed. It is likely that many one-vehicle
accidents go unreported due to the road's remote location. It appears
that the narrow, winding roadway, washboard roadway surface, and no
roadside recovery area contribute to the accident rate.
If no changes are made to the roadway, the frequency of accidents
and near misses due to road deficiencies could reasonably be expected
to increase as traffic volume increases. This traffic increase, coupled
with the national trend of more drivers operating larger RVs would
likely exacerbate the accident problem on WY FH 23.
Inadequate operational characteristics of WY FH 23 also cause safety
problems. Road widths are too narrow to safely accommodate passing
by opposing larger vehicles, such as school buses or trucks with livestock
trailers. Steep grades and impaired sight distance at curves and switchbacks,
which is further reduced by excessive dust, cause operational problems
and capacity difficulties, especially when passenger vehicles become
queued behind larger, slow-moving vehicles. There are few scenic vista
or slow-moving vehicle pullouts to mitigate these operational problems.
USFS records indicate that firefighters respond six to twelve times
a year to fires within the boundaries of the Forest. Search and rescue
operations are called into the Forest on an average of once a month.
The most timely access to the Fremont County Youth Camp for emergency
ambulance service is on the proposed project route. Current roadway
design and conditions impair expedient emergency response. Steep grades,
narrow widths, and poor road surface conditions can cause delays for
emergency service providers responding to potential resource and personal
losses.
Social and Economic Conditions
The roadway is essential to the USFS
for the use, protection, and multiple use management of Forest resources.
Reconstruction of WY FH 23 to improve accessibility to Forest resources
would result in better overall resource development and administration,
as well as improved ecosystem management of the Forest. Reconstruction
of WY FH 23 would be in conformance with implementation of the Forest
Plan.
WY FH 23 contributes to the economies of Fremont County and Lander,
Wyoming. In an effort to strengthen the local economy, the Lander
Chamber of Commerce has made an investment in promoting the recreational
opportunities of the Wind River Mountains.
Individuals utilizing the Forest resources for recreational purposes
generate the majority of traffic on WY FH 23. The Forest Plan contains
specific management prescriptions along the WY FH 23 corridor. Resources
are to be managed for emphasis on "rural and roadbed natural
recreation opportunities" in this area. The Louis Lake Road provides
direct roadside access to an abundance of recreational opportunities,
including driving for pleasure, viewing scenery and wildlife, dispersed
camping, picnicking, lake and stream fishing, hunting, hiking, nature
trails, backpacking, rock climbing, cross-country biking, snowmobiling,
cross-country skiing, or driving for pleasure. There are areas of
historic significance, including the CCC-constructed facilities, mining
sites, and Blue Ridge Historic Lookout.
WY FH 23 is the primary local access from Lander to these recreational
opportunities in the Forest. A recent survey shows that of the visitors
arriving in Lander, only 28 percent continue on to Yellowstone and
Jackson Hole (Wind River Visitors Council, 1997). This provides evidence
that there is increasing interest in the recreational activities within
the Wind River Mountains and could indicate a subsequent increase
in usage of WY FH 23 if this upward trend continues. Increasing interest
in the recreational opportunities provided along WY FH 23 indicates
a potential for local economic growth in the form of lodging, restaurants,
outfitters, sporting goods retailers, and other recreational related
businesses and services.
WY FH 23 provides the only access to Fremont County Youth Camp on
Worthen Meadow Road. A safe and adequate transportation route is essential
for youth camp employees, attendees, and suppliers. The youth camp
served more than 1,200 youths in 13 camps in 1992 and more than 1,600
youths in 15 camps in 1996. Camp sessions range from a weekend to
2 or 3 weeks in length, beginning in July of each year until the end
of August.
Louis Lake Road also provides access to non-recreational resources
of the Forest, which contribute to the local economy. These resources
include a managed timber harvest program, pole fencing materials harvest,
commercial and residential firewood harvest, community watershed management,
and livestock management.
|
|
|