As discussed previously, an alternative approach to development of the PWS is to develop a statement of objectives. There is no set format for a SOO, but FAR 37.602(c) states the following elements must be included:
Purpose
Scope or mission
Period and place of performance
Background
Performance objectives, i.e., required results; and
Any operating constraints
The Government-prepared SOO is usually incorporated into the RFP either as an attachment or as part of Section C. At contract award, the contractor-proposed statement of work (solution) must be incorporated into the contract, usually as Section C.