Significant Changes in the Asbestos Standard for Construction 29 CFR 1926.1101
|
This handout is designed to acquaint interested persons with significant changes
to OSHA's new Asbestos Standard for Construction, 29 CFR 1926.1101. It is not
intended to be a comprehensive review of the entire standard. Persons who wish
to learn more about the specific provisions of the standard should consult the
preamble and regulatory text of the standard as published in the Federal
Register.
The issues that are discussed here are the Permissible Exposure Limit (PEL);
duties of building/facility owners; duties and training of the competent person;
aspects of exposure monitoring; and control measures, especially for the 4
classes of asbestos work defined by the standard. Basic definitions that are
important to understanding these issues are presented.
Definitions
Asbestos-Containing Material (ACM) - means any
material containing more than one percent asbestos.
Presumed Asbestos-Containing Material (PACM) - means
thermal system insulation and surfacing material found in buildings constructed
no later than 1980. The designation of a material as "PACM" may be
rebutted following procedures specified in the standard.
Surfacing ACM - means material that is sprayed,
troweled-on or otherwise applied to surfaces (such as acoustical plaster on
ceilings and fireproofing materials on structural members, or other materials on
surfaces for acoustical, fireproofing, and other purposes) and that contains
more than 1% asbestos.
Thermal System Insulation (TSI) ACM - means ACM
applied to pipes, fittings, boilers, breeching, tanks, ducts or other structural
components to prevent heat loss or gain and that contains more than 1% asbestos.
Class I Asbestos Work - means activities involving
the removal of TSI and surfacing ACM and PACM.
Class II Asbestos Work - means activities involving
the removal of ACM which is not thermal system insulation or surfacing material.
This includes, but is not limited to, the removal of asbestos-containing
wallboard, floor tile and sheeting, roofing and siding shingles, and
construction mastics.
Class III Asbestos Work - means repair and
maintenance operations, where "ACM," including TSI and surfacing ACM
and PACM, may be disturbed.
Class IV Asbestos Work - means maintenance and
custodial construction activities during which employees contact but do not
disturb ACM or PACM and activities to clean up dust, waste and debris resulting
from Class I, II and III activities.
NOTES: 1. The removal of intact cements, coatings,
mastics, and flashings during roofing work is not covered by the class system.
2. The installation of asbestos-containing products is covered by the standard
but does not fall into any of the four classes.
Building/Facility Owner -
means the legal entity, including a lessee, which exercises control over
management and recordkeeping functions relating to a building and/or facility in
which activities covered by this standard take place.
Permissible Exposure Limit (PEL)
The time-weighted average (TWA) permissible exposure limit has been reduced to
0.1 fibers per cubic centimeter. The Excursion Limit remains at 1.0 fibers per
cubic centimeter averaged over 30 minutes. Both of these values are considered
PELs.
There is no established action level in the new standard because the sampling
and analytical method is not reliable below the time-weighted average limit of
0.1 fibers per cubic centimeter.
Requirements for Building/Facility Owners
Most asbestos-related construction activities involve previously installed
building materials. Building owners often are the only and/or best sources of
information concerning them. Therefore they are assigned specific information
conveying and retention duties under the new asbestos standard. Where a
building/facility owner also is an employer with employees who may be exposed to
asbestos-containing materials, the duties of employers also apply.
The following materials must be treated as asbestos-containing, unless specified
procedures are followed to determine otherwise:
- TSI and surfacing materials in buildings or substrates constructed no
later than 1980
- Asphalt and vinyl flooring material installed not later than 1980
- Any other materials that the building owner has actual knowledge that it
is, or should have known it to be, asbestos-containing
Notification Requirements
Before work is begun, building/facility owners must
identify the presence, location, and quantity of ACM/PACM and notify the
following persons:
- Prospective employers applying for or bidding for work whose employees
reasonably can be expected to work in or adjacent to areas containing such
material
- Employees of the owner who will work in or adjacent to areas containing
such material
- On multi-employer worksites, all employers of employees who will be
performing work within or adjacent to areas containing such materials
- Tenants who will occupy areas containing such materials
Notification may be in writing or by personal
communication to the affected person(s) or their authorized representatives.
NOTE: When materials labeled as containing asbestos
according to the requirements of this standard are installed on
non-residential roofs, the contractor must notify the building owner of the
presence and location of such asbestos-containing materials. This facilitates
the owner's future notification requirements.
Signs and Labels
Building/facility owners must post signs at the entrance
to mechanical rooms/areas in which employees reasonably can be expected to enter
and which contain TSI and surfacing ACM/PACM. The signs must identify the
material which is present, its location, and appropriate work practices that
will ensure ACM/PACM will not be disturbed.
Previously installed PACM/ACM that is identified by a building owner or employer
must be labeled in areas where the label will clearly be noticed. Posting of
signs may be used as an alternative to labels.
The wording for labels is
DANGER
CONTAINS ASBESTOS FIBERS
AVOID CREATING DUST
CANCER AND LUNG DISEASE HAZARD |
Labels must also contain a warning statement against
breathing asbestos fibers.
Records Retention
Where a building/facility owner has communicated and/or
received notification concerning the identification, location, and quantity of
ACM/PACM, written records of such notifications and their content must be
maintained by the building owner for the duration of ownership and transferred
to successive owners.
Where a building/facility owner has relied on data to demonstrate that PACM is
not asbestos-containing, such data must be maintained for as long as they are
relied upon to rebut the presumption.
Competent Person
The new standard requires that a competent person be
designated for all worksites covered by the
standard. The competent person must have the qualifications and authority
required by 29 CFR 1926.20-32, the basic construction requirements.
The standard specifies additional duties and training for the competent person
on asbestos worksites.
Duties
The competent person must make frequent and regular
inspections of the job site, materials, and equipment. On jobsites where Class I
or II work is being performed, the competent person must perform or supervise
the following duties:
- Set-up the regulated area, enclosure, or other containment
- Ensure (by on-site inspection) the integrity of the enclosure or
containment
- Set up procedures to control entry to and exit from the enclosure and/or
area
- Supervise all employee exposure monitoring
- Ensure that employees working within the enclosure and/or using glove bags
wear protective clothing and respirators
- Ensure through on-site supervision, that employees set up and remove
engineering controls, use work practices and personal protective equipment
in compliance with all requirements
- Ensure that employees use the hygiene facilities and observe the
decontamination procedures
- Ensure through on-site inspection that engineering controls are
functioning properly and employers are using proper work practices
- Ensure that notification requirements are met
For Class I jobs, on-site inspections must be made at
least once during each work shift, and at any time at employee request.
For Class II and III jobs, on-site inspections must be made frequently enough to
assess whether conditions have changed, as well as at any reasonable time at
employee request.
Training
For Class I and II asbestos work, training of the
competent person must include all aspects of asbestos removal and handling,
including:
- abatement, installation, removal, and handling
- contents of the standard
- identification of asbestos
- removal procedures, where appropriate
- other practices for reducing the hazard
This training will be obtained in a comprehensive course
for supervisors that meets the criteria of EPA's Model Accreditation Plan (40
CFR Part 763), or a course equivalent in stringency, content, and length.
For Class III and IV, training of the competent person must include aspects of
asbestos handling appropriate to the work, including:
- procedures for setting up glove bags and mini-enclosures
- use of wet methods
- contents of the standard
- identification of asbestos
Training must include successful completion of a course
meeting EPA requirements for training local education agency maintenance and
custodial staff [40 CFR 763.92(a)(2)], or its equivalent in stringency, content,
and length.
Training required for Class I and II competent persons also satisfies the
requirements for Class III and IV.
Exposure Monitoring
Initial Exposure Assessment
A competent person must make an "initial exposure
assessment" before or at the initiation of all covered operations to
determine expected exposures. An initial exposure assessment is not the same as
initial exposure monitoring. Initial employee exposure monitoring cannot
adequately predict all future exposures on construction jobs. First-day
exposures may reflect set-up activities and thus be lower than later exposures.
In addition, results of monitoring are not instantaneously available. Therefore,
the initial exposure assessment will identify jobs likely to exceed the PEL in
time for employers to install and implement the extra controls required to
reduce exposures.
The bases for the initial exposure assessment are:
1) Employee exposure monitoring, if feasible, and
2) All observations, information, or calculations that indicate employee
exposure to asbestos; this includes any previous monitoring conducted in the
workplace, or of the operations of the employer that indicate the levels of
airborne asbestos likely to be encountered on the job.
For Class I jobs, exposures are to be assumed to exceed
the PELs until and unless the employer is able to make a "negative exposure
assessment."
If a "negative exposure assessment" has been made, the "initial
exposure assessment" is not required.
Negative Initial Exposure Assessment
A "negative initial exposure assessment" is a
demonstration by the employer that employee exposure during an operation is
expected to be consistently below the PELs.
The determination of a "negative exposure assessment" is job-specific.
It can apply only to jobs performed by trained
employees.
An employer may demonstrate that exposure will be below the PELs by data
conforming to the following criteria:
1) Objective data - demonstrating that the product or
material containing asbestos minerals or the activity involving such product
or material cannot release airborne fibers in concentrations in excess of the
PELs (TWA or Excursion Limit) under those work
conditions having the greatest potential for releasing asbestos (the worst
case), or
2) Prior exposure monitoring results - for both PELs; within the previous 12
months; using the sampling and analytical methods of the asbestos standard in
effect; work operations closely resemble current or projected operations in
terms of processes, types of material, control methods, work practices,
environmental conditions, and employee training;
results indicate that employee exposures will not exceed PELs, or
3) Results of initial exposure monitoring of the current job - cover
operations that are most likely during the performance of the entire asbestos
job to result in exposures over the PELs.
Periodic Monitoring
Daily monitoring is required for Class I and II operations
unless the employer has made a negative exposure assessment for the entire
operation.
For Class I work, daily monitoring may be dispensed with only if all employees
are equipped with supplied-air respirators operated in the pressure demand mode
(or other positive pressure mode respirator) and
only control methods listed in the standard are used.
For Class II work, daily monitoring may be dispensed with if all employees are
equipped with supplied-air respirators operated in the positive-pressure mode.
All work operations, other than Class I and II work, where exposures are
expected to exceed a PEL, must be monitored at intervals sufficient to document
the validity of the exposure prediction.
Methods of Compliance
Some methods of compliance specified in the new standard apply to all covered
asbestos jobs. Others are Class-specific.
Requirements Applying to All Jobs
Controls and practices that must always be used, regardless
of the level of exposure, are
1) Vacuum cleaners with HEPA filters to collect
asbestos-containing debris and dust
2) Wet methods or wetting agents during handling, mixing, removal, cutting,
application, and clean-up (unless infeasible or creates a greater hazard) -
see paragraph (g)(8)(ii) for roofing exceptions
3) Prompt clean-up and disposal of wastes and debris contaminated with
asbestos in leak-tight containers
Controls and work practices that may never
be used, regardless of the level of exposure, are
1) High-speed abrasive disc saws that are not equipped
with point of cut ventilator or enclosures with HEPA filtered exhaust air
2) Compressed air to remove asbestos-containing materials, unless used in
conjunction with an enclosed ventilation system to capture the dust cloud
3) Dry sweeping, shoveling or other dry clean-up of dust and debris containing
ACM and PACM
4) Employee rotation to reduce employee exposure
For all work covered by the standard, one or more of the
following controls must be used, as necessary, to
achieve compliance with the PELs:
- Local exhaust ventilation equipped with HEPA filter dust collection
systems
- Enclosure or isolation of processes producing asbestos dust
- Ventilation of the regulated area to move contaminated air away from the
employee's breathing zone to a filtration or collection device equipped with
a HEPA filter
- Other work practices and engineering controls that the Assistant Secretary
for OSHA can show to be feasible.
NOTE: Where the above controls are not sufficient to achieve compliance
with the PELs, they must still be used and then supplemented with
respiratory protection.
Requirements Applying to Specific Classes of Asbestos
Work
Requirements for controls and work practices that apply to a specific Class
or type of asbestos work are found in the sections of the Standard as
indicated in the following table:
Class or
Type of Asbestos Work |
Paragraph
of the Standard |
Class I Requirements |
(g)(4) (g)(5) (g)(6) |
Class II Requirements |
(g)(7) (g)(8) |
Class III Requirements |
(g)(9) |
Class IV Requirements |
(g)(10) |
Installing, removing,
repairing, or maintaining intact pipeline asphaltic wrap |
(g)(11) |
Installing, removing,
repairing, or maintaining intact roof flashings which contain asbestos
fibers encapsulated or coated by bituminous or resinous compounds |
(g)(11) |
|
|
|