30 CFR § 75.223
Evaluation and revision of roof control plan.
(a) Revisions of the roof control plan shall be proposed by the
operator--
(1) When conditions indicate that the plan is not suitable
for controlling the roof, face, ribs, or coal or rock bursts; or
(2) When accident and injury experience at the mine
indicates the plan is inadequate. The accident and injury experience at each
mine shall be reviewed at least every six months.
(b) Each unplanned roof fall and rib fall and coal or rock burst that
occurs in the active workings shall be plotted on a mine map if it--
(1) Is above the anchorage zone where roof bolts are
used;
(2) Impairs ventilation;
(3) Impedes passage of persons;
(4) Causes miners to be withdrawn from the area affected;
or
(5) Disrupts regular mining activities for more than one
hour.
(c) The mine map on which roof falls are plotted shall be available
at the mine site for inspection by authorized representatives of the
Secretary and representatives of miners at the mine.
(d) The roof control plan for each mine shall be reviewed every six
months by an authorized representative of the Secretary. This review shall
take into consideration any falls of the roof, face and ribs and the adequacy
of the support systems used at the time.
[53 FR 2375, Jan. 27, 1988; 53 FR 11395, Apr. 6, 1988; 60 FR 33719, June 29, 1995]