OSHA Instruction CPL 2-2.67 February 27, 1997 Directorate of Compliance
Programs
Subject: Brass and Bronze Ingot Manufacturing Industry Compliance
Requirements and Dates Under the Lead Standard (29 CFR 1910.1025).
A. Purpose. This instruction changes compliance requirements and
compliance dates for enforcement of the engineering and work practice
controls provisions of the Lead Standard (29 CFR 1910.1025(e)(1)) in the
brass and bronze ingot manufacturing industry.
NOTE: The stay on enforcement of paragraph (e)(1) of the Lead
Standard as it applies to the brass and bronze ingot manufacturing industry
has not yet been lifted by the court. Until the stay is lifted employers in
this industry must continue to control lead exposures to 200 ug/m(3) solely
by engineering and work practice controls, and to 50 ug/m(3) by some
combination of engineering and work practice controls and respiratory
protection. A follow-up instruction will be issued as soon as the stay is
lifted.
B. Scope. This instruction applies OSHA-wide.
C. References.
1. OSHA Instruction STP 2.22A, State Plan Policies and Procedures
Manual (SPM).
2. OSHA Compliance Instruction CPL 2-2.47, Compliance Directive
for Occupational Exposure to Lead.
3. OSHA Instruction STP 2-1.94, Federal Program Change
Transmittal: Occupational Exposure to Lead, Final Standard.
4. 29 CFR 1910.1025, paragraph (e)(1).
D. Action. Regional Administrators and Area Directors shall ensure
that the general inspection procedures in this instruction are followed and
that compliance officers are familiar with the changes in employers'
obligations under the engineering and work practice controls provisions of
the Lead Standard in the brass and bronze ingot manufacturing industry. In
addition, Regional Administrators and Area Directors shall ensure that
compliance officers are aware that follow-up instructions will be issued
informing them as to the date of the lifting of the judicial stay of
paragraph (e)(1) as it pertains to the brass and bronze ingot manufacturing
industry.
E. Federal Program Change. This instruction describes a Federal
Program Change which affects State Programs. Each Regional Administrator
(RA) shall:
1. Ensure that this instruction is promptly forwarded to each
State Designee using a format consistent with the Plan Change Two-Way
Memorandum in Appendix A, OSHA Instruction STP 2.22A, State Plan Policies and
Procedures Manual(SPM).
2. Explain to each State Designee as requested the technical
content of this change and the guidelines detailed in this
instruction
3. Advise the State Designee that this instruction provides the
current compliance requirements and compliance dates under paragraph (e)(1)
of the Lead Standard as it applies to the brass and bronze ingot
manufacturing industry.
4. Inform each State Designee that this instruction incorporates
the relevant provisions of the settlement agreement concerning the employers'
obligations to implement the engineering and work practice controls under the
Lead Standard that was signed with the Brass and Bronze Ingot Manufacturers,
Inc. (BBIM), and the Institute of Scrap Recycling Industries, Inc. (ISRI), on
June 27, 1995.
5. Ensure that the State Designee acknowledges receipt and
provides preliminary notification to the RA within 30 days from the date of
this instruction of their intent to adopt an identical or equivalent policy
or not to adopt such procedures.
6. Ensure that the State shall respond to this change within 70
days in accordance with paragraph I.1.a.(2)(a) and (b), Chapter III or Part I
of the SPM. If the State adopts identical compliance procedures, no further
plan change supplement need be submitted. If the State adopts different
compliance procedures, a copy of the procedures shall be provided to the RA
within six (6) months from the date of this directive for review.
7. Review the policies, procedures, and instruction issued by the
State and monitor their implementation.
F. Background.
1. On November 14, 1978, OSHA promulgated the Lead Standard (29
CFR 1910.1025)(43 FR 52952). The standard requires that employers achieve a
permissible exposure limit (PEL) of 50 ug/m(3) based on an 8-hour
time-weighted average (TWA)(29 CFR 1910.1025(c)), solely by means of
engineering and work practice controls (29 CFR 1910.1025(e)(1)). The
standard was challenged by industry and labor. Most aspects of the standard
were affirmed by the U.S. Court of Appeals for the District of Columbia,
including the PEL of 50 ug/m(3). United Steelworkers of America v.
Marshall, 647 F.2d 1189 (D.C. Cir. 1980), cert. denied, 453 U.S.
913 (1981). In addition, the court upheld the feasibility of meeting the PEL
solely by means of engineering and work practice controls for 10 industries,
but found that OSHA had failed to establish feasibility for 38 other
industries. The court remanded the record to OSHA for reconsideration of the
feasibility of complying with paragraph (e)(1) and stayed enforcement of that
paragraph for the 38 industries. (After recategorizing and adding other
industries, the remand industries total 45.)
2. In December 1981, OSHA published and filed with the court its
statement of reasons that compliance with paragraph (e)(1) is feasible for
all but nine of the remand industries (46 FR 60758). The nine industries
were: brass and bronze ingot manufacturing/production; collection and
processing of scrap (including independent battery breaking), lead chemicals,
lead chromate pigments, leaded steel, nonferrous foundries, secondary copper
smelting, shipbuilding and ship repairing, and stevedoring. In March 1987,
the court remanded the record to OSHA for further consideration of these nine
remand industries.
3. On July 11, 1989, after notice and public hearings, OSHA
published and filed with the court an additional statement of reasons that
compliance with the PEL solely by means of engineering and work practice
controls is feasible for eight of the remaining nine industries (54 FR
29142). In the ninth industry, nonferrous foundries, OSHA concluded that it
is feasible for large nonferrous foundries to comply with the PEL by means of
engineering and work practice controls. OSHA concluded, however, that it was
not economically feasible for small nonferrous foundries to comply with
paragraph (e)(1). On January 30, 1990, OSHA published and filed with the
court its determination that achieving an 8-hour TWA airborne concentration
of lead of 75 ug/m(3) is economically feasible for small nonferrous
foundries. (55 FR 3146). Six of the nine industries challenged OSHA's
finding (brass and bronze ingot manufacturing/production; collecting and
processing of scrap; lead chemicals; leaded steel; nonferrous foundries; and
secondary copper smelting). The remaining three industries (lead chromate
pigments, shipbuilding and ship repairing, and stevedoring) did not file
challenges.
4. On March 8, 1990, in response to OSHA's finding, the court
lifted the stay on paragraph (e)(1) for all remand industries (39
industries), except the six that challenged OSHA's feasibility findings.
These 39 industries were given until September 8, 1992, two and one-half
years after the lifting of the stay, to comply with the PEL by means of
engineering and work practice controls.
5. On July 19, 1991, the court affirmed OSHA's feasibility
findings for five the of six contested industries and lifted the stay on
paragraph (e)(1) as it applied to them. AISI v. OSHA, 939 F.2d 975
(D.C. Cir. 1991). These industries were nonferrous foundries (large and
small), secondary copper smelting, collection and processing of scrap
(including independent battery breaking), leaded steel manufacturing, and
lead chemicals manufacturing. Employers in the leaded steel and scrap
collection and processing industries were given until January 19, 1994, two
and one-half years after lifting of the stay, to achieve the PEL by means of
engineering and work practice controls. Employers in the three other
industries were given until July 19, 1996, to comply.
6. With regard to the brass and bronze ingot manufacturing (BBIM)
industry, the court concluded that while OSHA had shown it is technologically
feasible to achieve the PEL by means of engineering and work practice
controls, OSHA had not shown that it is economically feasible to do so. The
court remanded that portion of the record to OSHA for additional
consideration and continued the stay of paragraph (e)(1) for this
industry.
7. In response to the remand, OSHA reconsidered the existing
record and concluded that an 8-hour TWA airborne lead concentration of 75
ug/m(3) is the lowest economically feasible level that can be achieved by
means of engineering and work practice controls in the brass and bronze ingot
manufacturing industry as a whole (60 FR 52856). On June 27, 1995, BBIM and
ISRI (Institute of Scrap Recycling Industries) entered an agreement with OSHA
acknowledging that this level is economically feasible for the industry as a
whole.
8. Based on the existing record, OSHA also recognized that most
employers in the industry cannot achieve the 50 ug/m(3) PEL without the
supplemental use of respiratory protection. In addition, OSHA recognized
that it is probably not economically feasible to achieve even an 8-hour TWA
of 75 ug/m(3) in the briquetting and baghouse maintenance operations by means
of engineering and work practice controls. Therefore, OSHA would have the
burden of proving economic feasibility of materially reducing existing air
lead levels above 75 ug/m(3) by means of engineering and work practice
controls in any enforcement proceeding under paragraph (e)(1) of the Lead
Standard concerning these two operations.
9. In recognition of the economic feasibility constraints on the
brass and bronze ingot manufacturing industry, OSHA is allowing employers six
years from the date the court lifts the stay to comply with 75 ug/m(3) TWA by
engineering and work practice controls. As soon as the court lifts the stay,
the effective date for enforcement of the PEL will be six years from the date
the stay was lifted. A follow-up instruction listing the new compliance date
will be issued around that time.
G. Inspection Guidance. Not all provisions and paragraphs of the
Lead Standard are included in this instruction. Refer to the Compliance
Directive for Occupational Exposure to Lead CPL 2-2.47 and STP 2-1.94, the
Lead Standard, and its Preamble for further guidance on specific subjects not
covered here.
Inspections to assess compliance with the engineering and work
practice control provisions of the Lead Standard in general industry,
including the brass and bronze ingot manufacturing industry, must be done by
a Compliance Safety and Health Officer (CSHO) appropriately trained in
conducting inspections of the Lead Standard (e.g., thoroughly familiar with
the relevant provisions of 29 CFR 1910.1025, particularly paragraph (e)(1),
and with the guidelines in this instruction). Citations issued for
violations of 29 CFR 1910.1025(e)(1) must be reviewed by the Area Director,
Assistant Area Director, or Team Leader.
1. Current compliance--The CSHO shall determine whether the
employer in the brass and bronze ingot manufacturing industry is currently
in compliance with the following items:
a. The employer must be in compliance with all of the
provisions of the Lead Standard. Compliance with paragraph (e)(1) and the
PEL of 50 ug/m(3) must be achieved and maintained by some combination of
engineering controls, work practices, and respiratory protection in each
operation where there is lead exposure, as specified in paragraph
(c)(1).
b. The employer must be achieving and maintaining an 8-hour
TWA of 200 ug/m(3) solely by means of engineering and work practice controls
in each operation where there is lead exposure.
2. Compliance during years 1-6--Within the first six years
after the judicial stay of paragraph (e)(1) of the Lead Standard is lifted by
the court for the brass and bronze ingot manufacturing industry, the CSHO
shall determine whether the employer in this industry is also in compliance
with the following items:
a. The employer must provide interim and/or supplemental
respiratory protection throughout the period in which engineering and work
practice controls are being implemented where the employer cannot achieve and
maintain the PEL solely by means of engineering and work practice
controls.
b. Until the employer achieves and maintains control of air
lead exposures to a TWA of 75 ug/m(3), the employer must submit to BBIM
and/or ISRI air lead and blood lead monitoring data that is required to be
collected under the Lead Standard. (NOTE: ISRI and BBIM, jointly or
separately, shall annually provide the OSHA Office of Health Standards
Programs with the monitoring data submitted by employers, in accordance with
the terms of paragraph 12(F) of the settlement agreement.)
c. By the end of year 1--As soon as is practicable and, in
any event, within one year after the judicial stay of paragraph (e)(1) of the
Lead Standard is lifted for the brass and bronze ingot manufacturing
industry, the employer whose air lead levels are above an 8-hour TWA of
75 ug/m(3) must take the following steps to reduce those levels to or below
the 8-hour TWA of 75 ug/m(3), where doing so is low cost or no
cost:
- Conduct an industrial hygiene evaluation;
- Improve work practices, which are to be written,
communicated to employees and followed;
- Improve housekeeping and preventive maintenance of
ventilation and production systems;
- Control cross contamination.
3. Compliance after year 6--Six years after the judicial stay
of paragraph (e)(1) of the Lead Standard is lifted by the court, the CSHO
shall determine whether the employer in the brass and bronze ingot
manufacturing industry is in compliance with all provisions of the Lead
Standard, including the following items:
a. The employer must achieve and maintain an 8-hour TWA of 75
ug/m(3) solely by means of engineering and work practice controls. (NOTE:
In briquetting and baghouse maintenance operations, OSHA recognizes that it
is probably not economically feasible to achieve an 8-hour TWA of 75 ug/m(3)
by means of engineering and work practice controls. Therefore, OSHA would
have the burden of proving the economic feasibility of materially reducing
existing air lead levels above 75 ug/m(3) by engineering and work practice
controls in any enforcement proceeding under paragraph (e)(1) of the Lead
Standard for these two operations.)
b. The employer must provide supplemental respiratory
protection (APF sufficient enough to be in compliance with the PEL) to each
employee in every operation where the PEL of 50 ug/m(3) cannot be achieved
and maintained by engineering and work practice controls
alone.
Greg Watchman Acting Assistant Secretary
Distribution: National, Regional and Area Offices All Compliance Officers
State Designees NIOSH Regional Program Directors 7(c)(1) Consultation Project
Managers OSHA Training Institute
|