| | ![](https://webarchive.library.unt.edu/eot2008/20081104013041im_/http://www.state.gov/images/clearpixel.gif) Applying for Presidential Permits for Liquid PipelinesThe Secretary of State has the authority to issue Presidential Permits for cross-border liquid (water as well as petroleum product) pipelines and other cross-border infrastructure. The Office of International Energy and Commodity Policy receives and processes permit applications.
If you plan to request a Presidential Permit for a cross-border liquid pipeline, please call 202-647-1291. (For information on the permit submitted for the Keystone TransCanada project, please see www.keystonepipeline.state.gov )
In consultation with the Department of State, the Department of Energy is responsible for permitting cross-border electricity transmissions lines, and the Federal Energy Regulatory Commission (FERC) issues cross-border natural gas pipeline permits.
E.O. 13337 of April 30, 2004
| |