ExpectMore.gov


Detailed Information on the
Defense Housing Assessment

Program Code 10000066
Program Title Defense Housing
Department Name Dept of Defense--Military
Agency/Bureau Name Military Personnel
Program Type(s) Direct Federal Program
Assessment Year 2002
Assessment Rating Moderately Effective
Assessment Section Scores
Section Score
Program Purpose & Design 100%
Strategic Planning 100%
Program Management 72%
Program Results/Accountability 67%
Program Funding Level
(in millions)
FY2007 $4,022
FY2008 $2,413
FY2009 $3,196
*Note: funding shown for a program may be less than the actual program amount in one or more years because part of the program's funding was assessed and shown in other PART(s).

Ongoing Program Improvement Plans

Year Began Improvement Plan Status Comments
2003

Privatize government-owned housing, where feasible, so that military service members and their families can live in quality housing.

Action taken, but not completed Significant progress has been made. Program is on track to privatize all government-owned housing in the Continental United States by end of Q1 FY 2009.
2003

Work toward meeting yearly targets so that DoD can eliminate all inadequate housing by 2009.

Action taken, but not completed Over 170,000 inadequate units have been eliminated. Less than 8,500 inadequate units left to eliminate.
2008

Privatize an additional 5,000 units in FY08 bringing the total percentage oif Defense housing privatized to 98%.

Action taken, but not completed

Completed Program Improvement Plans

Year Began Improvement Plan Status Comments
2003

Eliminate all out-of-pocket housing expenses by providing an appropriate housing allowance.

Completed

Program Performance Measures

Term Type  
Long-term Outcome

Measure: Reduce the number of inadequate houses to zero by 2007


Explanation:

Year Target Actual
2002 153,249 163,195
2003 125,366 142,697
2004 98,953 117,341
2005 67,079 87,572
2006 49,181 28,615
2007 2,338 8,490
2008 2,338
2009 0
2010
2011
2012
Long-term Outcome

Measure: Increase number of housing units privatized


Explanation:

Year Target Actual
2002 13,905 10,284
2003 34,649 42,222
2004 41,258 68,999
2005 142,299 111,462
2006 148,244 141,901
2007 184,000 173,727
2008 191,000
2009 191,000
2010 191,000
2011 191,000
2012 191,000
Long-term Outcome

Measure: Percent of service members out-of-pocket housing expenses as a fraction of the national median housing costs


Explanation:

Year Target Actual
2002 11.3% 11.3%
2003 7.5% 7.5%
2004 3.5% 3.5%
2005 0% 0%

Questions/Answers (Detailed Assessment)

Section 1 - Program Purpose & Design
Number Question Answer Score
1.1

Is the program purpose clear?

Explanation: The purpose of the program is to provide service members with adequate housing. DoD either provides: 1) an allowance for service members to live in adequate housing in the private sector or 2) free government-owned military housing in lieu of a cash allowance.

Evidence: DoD's housing program is covered by several statutes. Authority to provide allowance is provided in 37 USC Sections 403, 403a, and 405 (b). Authority to construct military housing is provided in 10 USC, Subtitle A, Part IV, Chapter 169, Subchapter II & III. Authority to privatize military-owned housing is provided in 10 USC, Subtitle A, Part IV, Chapter 169, Subchapter IV.

YES 20%
1.2

Does the program address a specific interest, problem or need?

Explanation: Historically, providing adequate housing or housing allowance to military service members has been viewed by DoD as a necessity. DoD treats housing benefits as a part of service members' compensation package, which helps retain and recruit soldiers.

Evidence: Service members have, since the founding of the United States, normally been furnished living quarters without charge. The history of the cash allowances can be traced back to 1878. A Congressional Budget Office report states that the high quality of today's armed forces suggests that housing benefits have met the needs of the members.

YES 20%
1.3

Is the program designed to have a significant impact in addressing the interest, problem or need?

Explanation: About two-third of the budgetary costs cover allowances for living off-base in private housing. Currently, two-thirds of married members live off-base, and one-third live on-base. Approximately 60% of DoD's on-base housing is considered inadequate. Privatization has helped DoD utilize land and improvements to provide quality housing by soliciting private sector participation.

Evidence: Currently, military household out-of- pocket costs for housing are 11.3% in '02 (7.5% projected in '03) when receiving an allowance and 0% when housed in government or privatized housing. Furthermore, DoD is using privatization to provide service members with larger, well-maintained housing units that are adequate.

YES 20%
1.4

Is the program designed to make a unique contribution in addressing the interest, problem or need (i.e., not needlessly redundant of any other Federal, state, local or private efforts)?

Explanation: Allowances provide for housing without the government being the landlord. DoD conducts market analysis which indicates whether there is a need for government- provided housing or whether the private housing market is adequate. DoD uses this survey to determine the need for military construction and/or privatization, where suitable private housing is not available.

Evidence: A recent RAND study, a research firm, shows that most military members prefer military housing when it is cheaper. However, if members are housed in the private sector, it is a lower cost alternative, even if DoD increases the housing allowance. It is expected that the increase in allowance will increase the reliance on the private sector.

YES 20%
1.5

Is the program optimally designed to address the interest, problem or need?

Explanation: Quality housing can be provided efficiently by the private sector. To this end, DoD is increasing allowances and privatization and reducing military construction. DoD also spends around $4 billion per year constructing and maintaining government-owned housing. Under an ideal economic situation, the government would principally rely on allowances (eventually making it part of salary) and allow most of the service members to live in the private sector or privatized housing.

Evidence: DoD provides good quality housing in two ways: 1) DoD provides a cash allowance, which allows service members to rent from the local market or privatized housing; and 2) DoD provides free-government housing in lieu of a cash allowance.

YES 20%
Section 1 - Program Purpose & Design Score 100%
Section 2 - Strategic Planning
Number Question Answer Score
2.1

Does the program have a limited number of specific, ambitious long-term performance goals that focus on outcomes and meaningfully reflect the purpose of the program?

Explanation: The goal of the program is to provide quality housing or to provide allowances for members to find adequate housing in the private sector. For government-owned housing, DoD's goal is to eliminate inadequate houses by 2007. DoD is also increasing reliance on the private sector to eliminate inadequate housing by privatizing government-owned housing. DoD is increasing the allowance each year to reduce out-of-pocket housing expense to 0% by 2005.

Evidence: These goals are clearly stated in the President's budget and the Secretary's Planning Guidance.

YES 20%
2.2

Does the program have a limited number of annual performance goals that demonstrate progress toward achieving the long-term goals?

Explanation: DoD has a goal to decrease members' out-of-pocket housing costs to 11.3% in FY02 and 7.5% in FY03. For on-base housing, DoD has a year by year plan to eliminate inadequate housing. DoD plans to use both military construction and privatization to achieve this goal, with an increasing reliance on privatization.

Evidence: The allowance goal is published in the President's Budget. Each year, DoD determines the annual amount of inadequate housing it plans to eliminate.

YES 20%
2.3

Do all partners (grantees, sub-grantees, contractors, etc.) support program planning efforts by committing to the annual and/or long-term goals of the program?

Explanation: Contractors do not participate in program planning efforts. Military construction and privatization projects are only competed if there is a need to construct houses. Once the need is determined, and the goals of the project are set by DoD, the contractor is expected to deliver as required by the contract.

Evidence:

NA 0%
2.4

Does the program collaborate and coordinate effectively with related programs that share similar goals and objectives?

Explanation: The military housing program is not related to any other federal program with a similar goal. No other program is funded to meet the same needs, directly or indirectly.

Evidence:

NA 0%
2.5

Are independent and quality evaluations of sufficient scope conducted on a regular basis or as needed to fill gaps in performance information to support program improvements and evaluate effectiveness?

Explanation: General Accounting Office (GAO), Congressional Budget Office, Congress, and DoD Inspector General have evaluated the program and DoD has taken action to improve the program. In addition, DoD relies on private sector financial experts to assist in the privatization program and to ensure privatization deals are valid and accurate.

Evidence: GAO has completed its third evaluation of the privatization efforts (June 2002). Moreover, each privatization project is evaluated by OMB and the Congress to ensure that they are scored and evaluated properly. Companies such as Ernst and Young (consultants), Jones Lang LaSalle (construction/financing) have added value by evaluating privatization projects.

YES 20%
2.6

Is the program budget aligned with the program goals in such a way that the impact of funding, policy, and legislative changes on performance is readily known?

Explanation: The results of increasing the housing allowance to the national median housing expenditure can be readily observed. Any funding provided for military construction or privatization is allocated by project since each project requires congressional authorization.

Evidence: For the allowance, annual decreases in out-of-pocket housing expense reflects budget alignment. DoD's budget justification materials sent to Congress with the 2003 President's budget displays military construction funding project by project.

YES 20%
2.7

Has the program taken meaningful steps to address its strategic planning deficiencies?

Explanation: Every year, DoD undertakes a program review effort to evaluate the program and then links the review to the budgetary decisions. In addition, DoD periodically assesses its program when an audit reveals criticisim or suggestions.

Evidence: Two years ago, DoD was criticized for having allowances that did not take into account high and low cost areas. Thus, service members were paying a higher percentage of housing expenses out of their pocket than others. DoD took steps to improve the allowance program by adjusting the allowance formula. GAO has criticized DoD for not having a robust methodology for computing housing needs. DoD has taken steps to improve the methodology by standardizing the models among services. Furthermore, DoD judges on-base housing requirement by looking to the local market instead of basing it on demand for on-base housing. Recently, the privatization program did not have a program evaluation in place and DoD now semi-annually evaluates performance and the lessons learned from on-going projects for use in upcoming privatization efforts.

YES 20%
Section 2 - Strategic Planning Score 100%
Section 3 - Program Management
Number Question Answer Score
3.1

Does the agency regularly collect timely and credible performance information, including information from key program partners, and use it to manage the program and improve performance?

Explanation: For every project, the Service requesting the project has to justify the expenditure based on housing market analysis. Once the project is awarded, project supervisors in the supervision and administration office (Corp of Civil Engineers or Air Force Civil Engineers) monitor the project to ensure that the project is proceeding as planned (from architectural drawings to foundation).

Evidence: DoD publishes a master plan each year to assess the need for housing and the number of current inadequate housing units and everytime construction is required, it must be supported with current market analysis. For instance in the Kirkland privatization project, the scope of the construction project was reduced based on the timely data DoD collected. In government construction, DoD uses supervisors to monitor the projects by adjusting drawings to meet government needs or reworking the contract to deal with mold and asbestos issues. Thereby, ensuring that the program purchases good housing.

YES 14%
3.2

Are Federal managers and program partners (grantees, subgrantees, contractors, etc.) held accountable for cost, schedule and performance results?

Explanation: Some projects contain incentives to improve the performance or delivery of the project. These include cash bonuses for contractors for completing projects on/ahead of time or below cost. Furthermore, past performance is a criteria on when construction/privatization projects are awarded. Construction contracts have to comply with Federal Acquisition Regulation (FAR) and anti-deficiency rules.

Evidence: FAR and anti-deficiency rules hold contractors accountable. Legal documents spell out the incentive awards. Construction contracts are subject to random reviews by internal auditors at DoD. In privatization, the relationship is primarily between developer and the renter. However, government interests are protected.

YES 14%
3.3

Are all funds (Federal and partners') obligated in a timely manner and spent for the intended purpose?

Explanation: Housing allowances are paid to service members every month. Military construction funds expire in five years and DoD closely monitors the funds and progress of various projects.

Evidence: DoD spends all allocated funds in a timely manner. The obligation/outlays rates are monitored through monthly reporting. Any funds that are not spent are re-allocated yearly through the reprogramming, reappropriation, or reauthorization process.

YES 14%
3.4

Does the program have incentives and procedures (e.g., competitive sourcing/cost comparisons, IT improvements) to measure and achieve efficiencies and cost effectiveness in program execution?

Explanation: The on-base housing program makes effort to privatize government-owned housing. DoD has used IT (i.e. the internet) to improve the housing referral system to help service members with relocation efforts.

Evidence: For each privatization project, DoD assesses the cost having the government vs. the private sector construct a home. Construction costs for privatized housing are cheaper and of better quality than government-owned housing. DoD is working with the private sector to create a web-based referal system, thereby, reducing the need for housing personnel.

YES 14%
3.5

Does the agency estimate and budget for the full annual costs of operating the program (including all administrative costs and allocated overhead) so that program performance changes are identified with changes in funding levels?

Explanation: DoD has not yet budgeted for the complete elimination of out-of pocket housing expenses. However, the goal is to achieve it by 2005. For military construction, the budget fails to completely include operation and maintenance costs and thus the buildings are not completely sustained and restored.

Evidence: In order to properly account for the full cost of the program, DoD has to track direct and indirect costs to judge the performance of the program. In order to budget completely for operations and maintenance, sufficient funds have to be allocated for this effort. The master plan indicates that adequate funds are not set aside because of other priorities.

NO 0%
3.6

Does the program use strong financial management practices?

Explanation: DoD continues to receive disclaimers by auditors on the financial statements for the agency as a whole.

Evidence: Though there are no audit reports of the housing program that illustrate management deficiencies, it is not clear that the financial data is accurate and compliant with federal management standards. DoD has yet to receive a clean audit.

NO 0%
3.7

Has the program taken meaningful steps to address its management deficiencies?

Explanation: DoD operates its housing program from three different offices (allowances, construction, privatization). However, each office reviews their data collection methods and quality control systems each year and coordinates public policy efforts. DoD is currently considering ways of improving management by placing all three areas of the program together.

Evidence: DoD issues an internal report and takes steps to improve management deficiencies such as undertaking program evaluations, housing requirement studies, and increasing housing allowances. Given budgetary constraints, DoD is forced to manage and plan wisely.

YES 14%
Section 3 - Program Management Score 72%
Section 4 - Program Results/Accountability
Number Question Answer Score
4.1

Has the program demonstrated adequate progress in achieving its long-term outcome goal(s)?

Explanation: DoD has a challenging goal of eliminating inadequate housing units by 2007. DoD is making progress toward this goal by increasing privatization and the cash allowance. Out-of-pocket housing expenses are being reduced annually.

Evidence: DoD's budget documents show DoD's progress toward eliminating inadequate houses, the level of privatization, and increases in allowance.

LARGE EXTENT 17%
4.2

Does the program (including program partners) achieve its annual performance goals?

Explanation: Out-of-pocket housing expenses decreases annually. The two ways in which DoD plans to eliminate inadequate DoD housing is to increase construction spending and increase privatization. Construction funding has been limited given other pressing needs. Thus, DoD has increased privatization.

Evidence: Performance measures reflect Administration goals and objectives. The Secretary's Planning Guidance continue to track DoD's performance. Progress has been made.

LARGE EXTENT 17%
4.3

Does the program demonstrate improved efficiencies and cost effectiveness in achieving program goals each year?

Explanation: DoD has increased privatization and created projects that are individually self-funding projects that require minimal government capital. The government through privatization is able to buy 8 houses for the same price of buying one house through government construction.

Evidence: Recent market surveys done for privatization projects indicate that surplus housing exist on bases and thus projects have been reduced in scale (e.g. draft of the Kirkland project). Less government housing means less costs to the taxpayer.

LARGE EXTENT 17%
4.4

Does the performance of this program compare favorably to other programs with similar purpose and goals?

Explanation: There is no other program in the federal government in scale that is comparable to the military housing program.

Evidence:

NA 0%
4.5

Do independent and quality evaluations of this program indicate that the program is effective and achieving results?

Explanation: DoD's program performance is audited by GAO periodically.

Evidence: GAO overall believes the housing privatization program to be sucessful. However, it believes that the housing requirement process has faults and thinks that privatization and construction may be occurring in locations that are unnecessary. DoD has taken technical steps to improve the calculation of project life-cycle costs and is conducting a privatization program evaluation every six months.

LARGE EXTENT 17%
Section 4 - Program Results/Accountability Score 67%


Last updated: 09062008.2002SPR