Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Construction

ACTT

<< PreviousContentsNext >>

ACTT Workshop: Iowa/Illinois
I-74 Corridor Study - Bridging the Future

Appendix C (continued): Skill Set Recording Forms
Innovative Contracting/Financing

Innovative Contracting/Financing Team
Facilitator: Gene Hoelker, FHWA
FHWA National Experts: Prabhat Diksit, FHWA Craig McDaniel, Washington DOT
Illinois DOT, Iowa DOT, Local FHWA, or Local Experts: Jim Ent, FHWA
Kris Tobin, Illinois DOT
Jay Howell, Illinois DOT
Dan Long, Illinois DOT
Eric Johnsen, Iowa DOT
Krandel Jack, Iowa DOT
Jim Rost, Iowa DOT
Bruce Kuehl, Iowa DOT
Dan Franklin, Iowa DOT
Kick Kautz, Iowa DOT
Fred Dean, Iowa DOT
D-B
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
If financing wasn't an issue
  • Consider options for funding construction. D-B provides more options; the contractor has more latitude; he/she chooses construction type; etc. More cooperative.
  • Need legislation to allow D-B (project specific-IA).
  • Contractors have more resources available, i.e., workforce.
  • How involved the States want to be is a factor; too much involvement can inhibit progress.
  • Cost is not the main driver.
  • Project delivery time is faster; in some cases D-B can cut costs.
Alliance contracting
  • Consolidate environmental and ROW contracts.
  • Create a team; set a target price with a fee on top of that; provide an incentive to stay under the set price.
  • If you use the incentive to fix things with, you lose control.
  • There's not a lot of public involvement; changes are sensitive under D-B.
  • The development process is 35 percent complete, the footprint is set and the corridor limits are established.
  • If you go outside the footprint, it is the contractor's responsibility.
D-B
  • Transfers risk, provides overall help. While it doesn't necessarily save money or give better quality, it does shorten the project delivery timeframe.
  • Cost effective: award is based not only on price.
  • There is less disruption of traffic.
  • Can provide merit points on aesthetics.
  • Strong public involvement is a challenge.
  • The contractor can make decisions with responsibility for risks.
  • The ability to get this project done quicker is there, but the funding is not: we don't have funding currently available, so D-B is a theoretical concept.
  • To the Illinois abutment would be the limit of the D-B.
  • If Iowa were to get legislative approval, you could go incrementally down the line based on partnering between the States.
  • Illinois would likely be in favor of this.
D-B: operate and maintain without charging tolls
  • Another party would build but would expect payback through bonds or State appropriations; more needs than money; public/private cooperation.
Shifting risk
  • Shift risk to the contractor as far as staging, public involvement, etc.; currently rigid in approach.
Working with local agencies (D-B)
  • Require contractors to deal with the local agencies.
  • Once contract is set, it can't be changed: the footprint is set.
  • Beyond the footprint is the contractor's responsibility to negotiate.
Disadvantages to D-B
  • State gives up control.
  • States must have the money up front.
  • Local contractors may feel a disadvantage in getting the work.
  • Public involvement is more challenging.
  • There is concern that D-B is a violation of the Brooks Act (qualification versus low bid).
State DOTs and D-B
  • Need to look at the RFQ/RFP process.
    • The qualifications set forth various standards.
    • must set forth ahead of time how you're going to award the contract based on the proposals.
    • standard procedures must be used.
  • Plug what you value into the RFP.
Proposed ideas: D-B
  • Bidders would receive a stipend, and we would own their ideas to give to the successful bidder.
Staging/Packaging
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Staging
  • Must be a corridor-level effort.
  • The media and the public are interested in the river crossing.
  • Public involvement is focused on the river bridge to the detriment of the rest of the corridor.
  • Davenport is focused on the 53rd Street exit.
  • Must build a good coalition with parties on both sides of the river.
Independent utility projects
  • Need to get money earmarked for these pieces.
  • Be sure to include public involvement so that the public understands this is a funding issue; slowly integrate it into the bridge.
Bridge condition
  • Bridge condition is not driver for replacement.
  • Both bridges are similar; structural condition is not driving cost; a functional aspect is driving the project.
  • This is an operational issue: maintenance on the bridges (extended maintenance) is costly.
Secondary impacts
  • They flow across bridge.

Financing
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Earmarked money
  • This money is for preliminary engineering and final design.
  • The bulk of the money has some ties to the structure itself.
  • There is a mix of funding (TSP, corridor funds, structures dollars), but it is still a fraction of what is needed.
  • Public officials are earmarking specifically for the Mississippi River crossing.
50/50 cost structure and approach
  • Coordinate between the States.
  • States are in the process of establishing boundaries due to approaches.
Regulated bonding
  • The size of the contract is an issue.
  • Typically there are not multi-million-dollar contracts in Iowa.
  • This is comparable to other States.
  • Iowa/Illinois contracts are smaller.
  • Keeping it smaller will attract more bidders.
  • The paradigm for Iowa is smaller contracts: breaking up contract would be better for Iowa but may not be the best for the Quad cities.
  • If the funding is not there, you can't offer one large contract anyway.
  • Larger contracts are more common in Illinois.
Bonds
  • Consider Garvee bonds, bonds issued on revenue, gas taxes, etc.
  • Legislative approval and voting of the people are issues.
  • Could bond against your own gas tax.
  • It's more difficult to sell bonding than tolling because it is not a State-wide issue.
  • Bonding for I-80 border to border would be easier to sell.
  • You would have to bond for a statewide improvement.
Financing
  • Need to determine if we can get the money and how much we can spend.
  • Time, quality and dollars are issues, as is the priority of projects.
Bonding with insurance
  • Provides for faster design and completion. Would need to establish a toll authority to make decisions.
Tax increase and tolling on local community
  • Consider for the I-74 corridor/east bridge.
  • Is there a strategy to issue the bond and shadow toll?
  • Depending on government structure, the two governments would need to work together and package the two bridges together.
  • From a capital market point of view, this would be more profitable.
  • The turnpike authority would need to be a sub-organization of the DOTs; a local taxing authority was tried in the past.
Local funding
  • Locals have been made aware that money is needed to fund this project; they've been going after earmarked funds.
  • Could leave it up to the locals to decide if revenues can be generated for I-74; tolling would be a no-revenue option.
  • Could take a vote to the locals as to when they want the bridge up.
Tax increment financing
  • Use additional revenue coming from specific areas.
Dedicated increment of fuel tax each year
  • Use specific taxes for specific projects.
Tolling
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Keeping contracts local
  • Larger contractors would likely sub out to local contractors, keeping the work local.
Duration
  • Note that the river bridge is less tied to traffic; the approach is more tied to traffic.
  • Makes for more complex duration and staging.
Corridor
  • Maintain similarities.

Optional combination
  • Offer all the separate contracts and then one large single contract.
  • Consider combining the contracts into one contract - this hasn't been discussed.
  • Staging and constructability are issues; traffic control would need to be coordinated.
  • Past experience shows that putting contracts together increases the price but improves the schedule.
  • Iowa contractors are more craft-orientated.
  • There have been problems getting bidders in the Quad Cities area for small contracts.
  • Allow contractors to bid the whole project or bid small components of the project; makes the competition better and the bidding lower.
Getting bidders
  • Consider a larger contract/one complete contract.
  • Would attract national bidders; more expeditious.
SEP 14/15
  • Consider 14-contract methods, 15 financing.
Size of contracts
  • $300 million might be $700 million.
  • Start with a 40 percent contingency, which drops through more engineering information.
Illinois/Iowa edge of river
  • This is not intended to be buildable as a separate contract.
  • Take the approach out from the bridge structure and bid it separately.
  • Innovative contracting should be part of the initial plan and not be left to the end.
Interchanges north and south of bridge
  • Combine to one contract to facilitate coordination and scheduling.
  • There would be one contractor to answer to the public rather than two contractors deflecting heat back and forth.
Financing Options
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Cash reimbursement option
  • This is traditional law from the two State legislatures.
  • The funds would be released in increments.
  • This is a viable option for Iowa and Illinois (in Illinois, would have to work way up the priority list).
Tolling the bridge portion
  • Start now on the current bridge or later on the new bridge.
  • The Iowa DOT has the authority to toll structures:
    • need to define the structure span, abutment to abutment, approach to approach
    • negotiations can be made and limits revised.
    • IDOT also has this ability.
    • The remainder of the corridor could be funded with appropriations.
  • Implement a small toll on the current bridge, committing to upgrade with a future bridge.
  • If you put a toll on the bridge now, you give up the authority to have a toll authority in the future.
  • Also, if you choose the toll option, it kills local funding options for sales and gas taxes.
  • If the legislature establishes the toll, a multi-State authority can be achieved.
  • There could be a backlash from reinstating toll bridges after doing away with them.
Toll bridge privatization
  • Bridge would be owned and tolled privately.
    • A privately-owned, operated and financed facility (either a 99-year lease or an outright purchase) tends to operate more efficiently, and there's a guaranteed revenue stream.
Sales taxes, tax increment financing
  • Utilize a tax increment plus annual appropriations.
  • This would require a State/local jurisdiction partnership and a system approach.
  • Consider a partnership with two bridges (exclude the 67 bridge).
Bonding against gas taxes, Federal grants statewide
  • Bond would be based on State revenue based on gas taxes, Garvee, TIF, Federal monies, etc.
Earmarks
  • How much more can we get from earmarks?
  • Use the average of past earmarks for future planning.
Miscellaneous Topics
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Iowa DOT 15 years from now
  • This is not a "top five" project for the Illinois DOT.
  • The Iowa DOT also has other Interstate projects that rank higher than this project.
  • Would need a billion dollars to fund this project.
  • Other projects of this magnitude have been done without tolls, bonds, etc.
Riverfront development impacts

Materials for bridge
  • There would be significant savings from not constructing a steel bridge; there's still room for innovation.
ROW
  • Final design is not needed to get ROW plats; ROW would be working concurrently with final design.
  • Historically Federal aid has not been used for ROW, but this has changed recently with earmarked monies.
Options for pre-bid meetings

Economic influences/safety drivers

Construction manager
  • Do the design and hire the contractors; the manager has incentives to maintain a certain fee.
International financing
  • International bridges are mostly privately owned and maintained.
Purpose and need
  • Discuss the need to improve alternative routes, the current level of service, future development and detour options.
Roadway construction first
  • It's harder to justify money for bridge; better off to construct the bridge first.
Schedule
  • Determine how funding affects the timeline.
Expediting contracts
  • Iowa does not have a lot of experience with A-plus-B contracts.
  • Weekend closure may work.
  • Consider a hyper-fix (60-90 days, an alignment tie-in between old and new).
  • Need modification to NEPA documents, options to bring to a public meeting.
  • Staging traffic off of the mainline would expedite construction; from legality of the NEPA document, staging is not an issue.
  • The requirement to keep the bridge open during the project has been set (set prior to the project).
Minimizing influence on traffic
  • Designate a corridor traffic manager to work between the two States.
  • It is critical to project success that this is viewed as one project being done by one team.
Project management office
  • Designate an I-74 project engineer with access to people at all levels, he/she would coordinate all corridor activities with the executive team.
  • Utilize a project web page and phone line.
  • Hire a PR firm to staff the office and communicate with residents and media.
  • One person needs to be accountable for the entire project; need for both States to be involved and report to the executive committee.
  • The committee should consist of members from both States.
Contracting
  • Let several small contracts with the option to tie them together into one contract.


  • Bid substructure and superstructure separately.
  • Build for the long-term with future expansion possibilities.

  • Include long-term maintenance in the contract.
  • This includes pavement maintenance, bridge maintenance and snow removal.
  • Use warranties.
  • Remember that construction funds cannot be used for maintenance contracts (not currently).
A-plus-B

Performance management specs

Safety incentives
  • Look at contractor's operations in disrupting traffic through performance specifications.
  • If the accident rate goes down, the public benefits.
  • Focus the contractor's thinking on safety.
  • Side road traffic should not be included, as it's more variable; focus on the mainline only or the entire project.
Environmental Incentives
  • Address erosion, water quality, etc.
No excuse bonus
  • Federal aid cannot be used.
  • The bonus is awarded if the contractor can complete the project within the specified timeframe.
  • Make it an incentive/disincentive, and use liquidated damages.
CPM scheduling
  • Update monthly and implement.
Quality-driven performance-based specifications

Design alternatives
  • Not using.
Prequalifications
  • All contractors are prequalified to bid on Iowa DOT projects.
  • Iowa uses an extended advertising period for larger jobs with no mandatory pre-bid meetings.
  • Select pre-bid meetings are not mandatory.
  • The Iowa DOT allows confidential bidding and holds constructability meetings.
  • Talk to AGC and advertise.
  • Anything discussed is distributed to all contractors.
Materials acceptance
  • Use QA/QC specs for asphalt, structural concrete, embankments.
Dispute resolution process/escalation procedures
  • A way to escalate conflict on projects (partnering) has been established but has not used lately.
  • Need to have a mechanism in place to keep issues from festering and get them resolved in a timely manner.
  • Put this in the contract using timing as an issue.
Multi-parameter bidding
  • Consider A-plus-B, providing pay award to enhancements for quality; A-plus-B-C (C being a warranty).
Bridge construction
  • Iowa DOT likes to be able to replace decking;
    • looking at different material options (steel, concrete, concrete filled steel).
    • considering expandable shoulders.
<< PreviousContentsNext >>

Events

Contact

Chris Schneider
Office of Asset Management
202-493-0551
E-mail Chris

Joe Huerta
Resource Center (Baltimore)
410-962-2298
E-mail Joe

 
 
This page last modified on 07/27/07
 

FHWA
United States Department of Transportation - Federal Highway Administration