No. IV-06-004   April 25, 2006
CONTACT: Victor Dricks
Phone: 817-860-8128
E-mail: opa4@nrc.gov

NRC TO DISCUSS 2005 PERFORMANCE AT COMANCHE PEAK NUCLEAR PLANT
Printable Version PDF Icon


Nuclear Regulatory Commission staff will meet with TXU Energy officials on May 1, to discuss the NRC’s annual assessment of safety performance at the Comanche Peak nuclear plant during 2005.

The 6 p.m. meeting at the Somervell County Expo Center, 202 Bo Gibbs Blvd., Glen Rose, Texas, is open to public observation. Before the session ends, NRC staff will be available to answer questions on the plant’s safety performance, as well as the agency’s role in ensuring safe plant operation.

"Each year, the NRC assesses the performance of all of the nation’s commercial nuclear power plants," said Region IV Administrator Bruce S. Mallett. "The meeting gives us an opportunity to discuss our findings with the company, local officials and members of the public. We look forward to meeting with members of the community and answering any questions they may have about our oversight."

A letter sent from the NRC Region IV Office to plant officials addresses the performance of the plant during 2005 and will serve as the basis for the meeting discussion. It is available on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/cp_2005q4.pdf PDF Icon.

Overall, Comanche Peak operated safely during the period. The NRC uses color-coded inspection findings and performance indicators to assess nuclear power plant performance. The colors start with "green" and then increase to "white," "yellow" or "red," commensurate with the safety significance of the issues involved. Because all of the inspection findings and performance indicators for the plant during the last quarter of 2005 were determined to be "green," Comanche Peak will receive a baseline (or routine) level of inspections during the upcoming assessment period. In addition, the NRC staff will perform steam generator and reactor vessel head replacement inspections.

Routine inspections are performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region IV Office in Arlington, Texas. Among the areas of plant operations to be inspected during the next year by NRC specialists are emergency preparedness and radiological safety.

Current performance information for Comanche Peak Unit 1 is available on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/CP1/cp1_chart.html.
Current performance information for Comanche Peak Unit 2 is available at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/CP2/cp2_chart.html.