Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BRAIDWOOD 1 |
100 |
|
|
* |
|
BRAIDWOOD 2 |
100 |
|
|
|
|
BYRON 1 |
100 |
|
|
|
|
BYRON 2 |
100 |
|
|
|
|
CLINTON 1 |
93 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
COOK 1 |
0 |
04/23/2003 |
Hot Shutdown MAINTENANCE OUTAGE |
* |
|
COOK 2 |
0 |
04/23/2003 |
Refueling DEFUELED |
|
|
DAVIS BESSE 1 |
0 |
02/15/2002 |
Cold Shutdown REFUELING OUTAGE |
|
|
DRESDEN 2 |
18 |
|
Power Operation CONDENSER MAINTENANCE |
* |
|
DRESDEN 3 |
98 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
DUANE ARNOLD 1 |
94 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
FERMI 2 |
100 |
|
|
|
|
KEWAUNEE 1 |
100 |
|
|
|
|
LASALLE 1 |
91 |
|
Power Operation CONTROL ROD PATTERN CHANGE |
* |
|
LASALLE 2 |
78 |
|
Power Operation CONTROL ROD PATTERN CHANGE |
* |
|
MONTICELLO 1 |
15 |
|
Startup INCREASING POWER |
* |
|
PALISADES 1 |
100 |
|
|
|
|
PERRY 1 |
0 |
04/04/2003 |
Cold Shutdown PREPERATIONS FOR RESTART |
|
|
POINT BEACH 1 |
100 |
|
|
|
|
POINT BEACH 2 |
50 |
|
Power Operation FEED PUMP LEAK |
* |
|
PRAIRIE ISLAND 1 |
100 |
|
|
|
|
PRAIRIE ISLAND 2 |
100 |
|
|
|
|
QUAD CITIES 1 |
0 |
05/20/2003 |
Refueling SHUTDOWN FOR PLANNED MAINTENANCE OUTAGE |
|
|
QUAD CITIES 2 |
64 |
|
Power Operation POWER SUPPRESSION TESTING |
* |
|