Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
Braidwood 1 |
100 |
|
|
|
|
Braidwood 2 |
100 |
|
|
|
|
Byron 1 |
100 |
|
|
|
|
Byron 2 |
100 |
|
|
|
|
Clinton |
95 |
|
100% ELECTRICAL CAPABILITY |
|
|
D.C. Cook 1 |
100 |
|
|
|
|
D.C. Cook 2 |
100 |
|
|
|
|
Davis-Besse |
100 |
|
|
|
|
Dresden 2 |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
Dresden 3 |
98 |
|
100% ELECTRICAL CAPABILITY |
* |
|
Duane Arnold |
92 |
|
TROUBLESHOOTING HEATER LEVEL PROBLEM |
* |
|
Fermi 2 |
100 |
|
|
|
|
Kewaunee |
0 |
02/20/2005 |
RESOLVING AUXILIARY FEEDWATER ISSUES |
|
|
La Salle 1 |
83 |
|
RECOVERING FROM FEEDWATER HEATER TRANSIENT |
* |
|
La Salle 2 |
100 |
|
|
|
|
Monticello |
100 |
|
|
|
|
Palisades |
100 |
|
|
|
|
Perry 1 |
91 |
|
HOLDING PRIOR TO DOWN POWER FOR CONTROL ROD ADJUSTMENTS |
* |
|
Point Beach 1 |
100 |
|
|
|
|
Point Beach 2 |
0 |
04/01/2005 |
REFUELING OUTAGE |
|
|
Prairie Island 1 |
100 |
|
|
|
|
Prairie Island 2 |
0 |
04/15/2005 |
REFUELING OUTAGE - DEFUELED |
|
|
Quad Cities 1 |
85 |
|
LIMITED IN POWER (STEAM DRYER MONITORING) |
|
|
Quad Cities 2 |
0 |
05/09/2005 |
STEAM DRYER REPLACEMENT OUTAGE |
* |
|