Areas of Concern
(AoCs)
Sediment
Remediation Projects in Great Lakes Areas of Concern*
AREA OF CONCERN |
CONTAMINATED SEDIMENT REMEDIATION PROJECT(S) |
Manistique River |
- In 1995-1996, approximately 14,000 m3 of Polychlorinated
Biphenyl (PCB)-contaminated sediment near the North Bay/U.S. 2 Highway was removed and
disposed of in a nearby landfill. The remainder of the PCB-contaminated sediment will be
addressed by the end of 1998. When the final removal is completed, approximately 92,000 m3
of contaminated sediment will have been dredged from the river and shipped off-site for
disposal. The total project cost is estimated at $16 million.
|
Lower Menominee River |
- In 1993-1994, approximately 11,500 m3 of bulk paint sludge was
removed by mechanical dredging and transported to a nearby Treatment, Storage, and
Disposal facility. This was an emergency removal through administrative orders by the
Michigan Department of Environmental Quality (MDEQ).
|
Milwaukee Estuary |
- In 1994, approximately 5,900 m3 of PCB-contaminated sediment
was removed from behind Ruck Pond Dam. Over 95% of the mass of PCBs was removed from the
system as a result of this project. The total project cost was $7.5 million.
- In
1991, approximately 570,000 m3 of contaminated sediment with varying levels was isolated
from the Milwaukee River by the removal of the North Avenue Dam. The cost involved with
the isolation of the contaminated sediment was approximately $1,348,000.
|
Waukegan Harbor |
- As a result of a 1989 Consent Decree, Outboard Marine
Corporation (OMC) provided $20 million for remediation of PCB-contaminated sediment. No
soils or sediment above 50 mg/kg PCBs remain onsite, except those within containment
cells. Approximately 30,000 m3 of contaminated sediment was dredged and placed in two
separate containment cells.
|
Grand Calumet
River |
- From 1994 to 1996, LTV Steel dredged approximately 89,000 m3
of contaminated sediment from a slip adjacent to Indiana Harbor. The total project cost
was an estimated $14 million.
|
Collingwood Harbour |
- From 1992 to 1993, approximately 8,000 m3 of contaminated
sediment was removed from the shipyard slips and adjacent areas in the harbour using the
Pneuma airlift system. The total project cost, which included partners from the Ministry
of Environment and Energy, Canada Steamship Lines, Transport Canada, and the Town of
Collingwood, was an estimated $650,000.
|
Rouge River |
- The PCB-source area to Newburgh Lake (Evans Products Ditch
Site) was recently addressed by the MDEQ with support from U.S. EPA. Completed in April
1997, approximately 7,300 m3 of PCB-contaminated stream sediment was removed and
transported for disposal at a landfill in Michigan and hazardous waste disposal facility
in New York. The total project cost was approximately $500,000.
- In 1997,
PCB-contaminated sediment is being removed from an impoundment (Newburgh Lake) in the
Upper Rouge River and placed in a secure landfill. By the end of the project,
approximately 306,000 m3 of PCB-contaminated sediment will be removed. The project is
expected to be completed by July 1998. The total project cost is estimated at $11.8
million.
- In 1986, 30,000 m3 of zinc-contaminated sediment was removed from the Lower
Branch of the Rouge River by mechanical dredging and placed in cell #5 of the Corps of
Engineers' Pointe Mouille Confined Disposal Facility on southwestern Lake Erie. All
dredging and disposal activities were completed at an approximate cost of $1 million.
|
River Raisin |
- Starting in mid-July and running through the end of Setember
1997, Ford Motor Company in Monroe, Michigan removed approximately 20,000 m3 of
PCB-contaminated sediment in a hot-spot adjacent to the shipping channel. The
PCB-contaminated sediment has been disposed of in a TSCA cell that was built on the
property of the Ford Monroe Plant.
|
Black River |
- In 1990, the USX/KOBE Steel Company removed over 38,000 m3 of PAH-contaminated sediment from the Black River mainstem in the areas of the former coke
plant outfall. The total project cost, which was funded entirely by USX/KOBE, was $1.5
million.
|
Hamilton Harbour |
- In 1995, in situ capping used a layer of uncontaminated
material to uniformly cover PCB-and PAH-contaminated sediment. The project was funded
through the Great Lakes 2000 Cleanup Fund at a cost of $300,000. An additional $350,000
was provided by the National Water Research Institute to further monitor and evaluate the
project.
- From 1992 to 1994, there was in situ treatment of contaminated sediment
in one industrial boat slip near the headwall area. Oxygen, iron oxide, and calcium
carbonate were injected. This was a demonstration treatment to find the depth of
contamination. The total project cost was estimated at $323,000.
|
St. Clair River |
- In 1996, Dow Chemical removed several thousand cubic meters of pentochlorophenol-contaminated sediment. The removal took place about 1 km south of the
Cole Drain, about 30 m offshore. The total project cost was estimated at $350,000.
|
Detroit River |
- Removal of contaminated sediment in Monguagon Creek, a
tributary to the Detroit River, was initiated in 1997. The project is funded largely by
Elf Atochem North America Inc., with an estimated cost of $3 million. When the final
removal is completed, approximately 12,250 m3 of contaminated sediment will have been
dredged from the creek.
- In 1993, approximately 3,075 m3 of contaminated sediment
was removed by Wayne County near a marina by Elizabeth Park. The total project cost was
estimated at $1.33 million.
|
Niagara River |
- In 1995, approximately 10,000 m3 of contaminated sediment was
removed from the Welland River (Ontario) using an Amphibex dredge. The total project cost
was estimated at $2.6 million.
- In 1996, approximately 21,800 m3 of contaminated
sediment was removed from the 102nd Street Embayment (New York).
- In 1995, approximately 11,500 m3 of contaminated sediment was removed from Pettit
Flume (New York).
- In 1992, approximately 6,100 m3 of contaminated sediment was removed from Gill
Creek (New York). The total project cost, which was funded entirely by DuPont, was
approximately $10 million.
- In 1990, approximately 13,000 m3 of dioxin-contaminated sediment from Black and Bergholtz Creeks (New York) was removed. The total project cost was approximately $14
million.
|
St. Lawrence
River |
- The New York portion of the AOC involves three major large
industrial sites. Ongoing remediation projects, as required by New York State and U.S.
EPA, address land-based and contaminated river sediment. Some land-based projects involve
shoreline and on-site wetland remediation. The contaminated river sediment projects at
each industry include:
- General Motors - During the summer of 1995, GM completed
the major portion of its St. Lawrence dredging with the removal of approximately 11,500 m3
of PCB contaminated river sediment. The river work to date has cost $10 million. The
extent of required treatment and disposal for the dredged materials is under review.
Further river sediment remediation in a cove adjacent to the St. Regis Mohawk Tribe
remains to be completed. Total project costs, including land-based actions with
groundwater recovery and treatment, are estimated to cost as much as $70 million.
- Reynolds Metals - The required contaminated river sediment removal project for
the St. Lawrence River has not yet begun. This will include shoreline remediation. The
land-based plant site remediation, which includes wetlands remediation, is nearing
completion at a cost of $53.7 million. The contaminated river sediment work is estimated
to cost an additional $57 million.
- ALCOA - The major "hot-spot" at the plant outfall in the Grasse River
was remediated in 1995 as part of a 'non-time critical removal action." This involved
the removal of approximately 3,000 m3 of PCB contaminated river sediment. The results of
this project are under review as is the feasibility of other remedial alternatives
downstream from the outfall in the Grasse River up to the St. Lawrence River confluence.
Major land-based inactive hazardous waste site remediation at the ALCOA plant site
continues with 10 of the 14 Record of Decision sites now completed. Overall remediation
costs are estimated to be in excess of $250 million.
|
|