Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BROWNS FERRY 1 |
0 |
03/03/1985 |
DEFUELED |
|
|
BROWNS FERRY 2 |
100 |
|
|
|
|
BROWNS FERRY 3 |
100 |
|
|
|
|
BRUNSWICK 1 |
100 |
|
|
|
|
BRUNSWICK 2 |
100 |
|
|
|
|
CATAWBA 1 |
88 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
CATAWBA 2 |
100 |
|
|
|
|
CRYSTAL RIVER 3 |
100 |
|
|
|
|
FARLEY 1 |
89 |
|
HOLDING POWER AT THIS LEVEL TO PERFORM COOLING TOWER REPAIRS |
* |
|
FARLEY 2 |
100 |
|
|
|
|
HARRIS 1 |
100 |
|
|
|
|
HATCH 1 |
0 |
09/29/2000 |
REFUELING OUTAGE - INITIAL (PARTIAL) CORE OFFLOAD COMPLETE |
|
|
HATCH 2 |
100 |
|
|
|
|
MCGUIRE 1 |
100 |
|
|
|
|
MCGUIRE 2 |
16 |
|
EXITING REFUELING OUTAGE - HOLDING POWER AT THIS LEVEL WITH THE UNIT ON LINE TO PERFORM A 2-HOUR SOAK FOLLOWED BY A TURBINE OVERSPEED TRIP TEST |
* |
|
NORTH ANNA 1 |
100 |
|
|
|
|
NORTH ANNA 2 |
100 |
|
|
|
|
OCONEE 1 |
100 |
|
|
|
|
OCONEE 2 |
100 |
|
|
|
|
OCONEE 3 |
100 |
|
|
|
|
ROBINSON 2 |
100 |
|
|
|
|
SAINT LUCIE 1 |
100 |
|
|
|
|
SAINT LUCIE 2 |
100 |
|
. |
|
|
SEQUOYAH 1 |
0 |
10/06/2000 |
FORCED MAINTENANCE OUTAGE |
|
|
SEQUOYAH 2 |
81 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
SUMMER 1 |
0 |
10/07/2000 |
REFUELING OUTAGE - HEAD LIFT COMPLETE - PREPARING FOR FUEL OFFLOAD |
* |
|
SURRY 1 |
100 |
|
|
|
|
SURRY 2 |
0 |
09/30/2000 |
REFUELING OUTAGE - DEFUELED |
|
|
TURKEY POINT 3 |
100 |
|
|
|
|
TURKEY POINT 4 |
0 |
09/24/2000 |
REFUELING OUTAGE - FUEL RELOAD IN PROGRESS |
|
|
VOGTLE 1 |
0 |
09/17/2000 |
REFUELING OUTAGE - REACTOR COOLANT SYSTEM FILL AND VENT IN PROGRESS |
|
|
VOGTLE 2 |
100 |
|
|
|
|
WATTS BAR 1 |
100 |
|
|
|
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BRAIDWOOD 1 |
100 |
|
|
|
|
BRAIDWOOD 2 |
100 |
|
|
|
|
BYRON 1 |
22 |
|
EXITING REFUELING OUTAGE - HOLDING POWER AT THIS LEVEL WITH THE UNIT OFF LINE DUE TO TURBINE PROBLEMS |
* |
|
BYRON 2 |
100 |
|
|
|
|
CLINTON 1 |
98 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
COOK 1 |
0 |
09/08/1997 |
REFUELING OUTAGE - DEFUELED |
|
|
COOK 2 |
100 |
|
|
|
|
DAVIS BESSE 1 |
100 |
|
|
|
|
DRESDEN 2 |
100 |
|
|
|
|
DRESDEN 3 |
100 |
|
|
|
|
DUANE ARNOLD 1 |
100 |
|
|
|
|
FERMI 2 |
100 |
|
|
|
|
KEWAUNEE 1 |
96 |
|
MAXIMUM POWER DUE TO PLUGGED STEAM GENERATOR TUBES |
|
|
LASALLE 1 |
93 |
|
HOLDING POWER AT THIS LEVEL TO WORK ON A HEATER DRAIN VALVE |
|
|
LASALLE 2 |
97 |
|
HOLDING POWER AT THIS LEVEL DUE TO THERMAL LIMITS |
|
|
MONTICELLO 1 |
100 |
|
|
|
|
PALISADES 1 |
100 |
|
|
|
|
PERRY 1 |
95 |
|
HOLDING POWER AT THIS LEVEL DUE TO MSR #2A AND #2B BEING ISOLATED |
|
|
POINT BEACH 1 |
90 |
|
HOLDING POWER AT THIS LEVEL FOR PLANNED 345-kV LINE MAINTENANCE |
|
|
POINT BEACH 2 |
98 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
PRAIRIE ISLAND 1 |
100 |
|
|
|
|
PRAIRIE ISLAND 2 |
100 |
|
|
|
|
QUAD CITIES 1 |
80 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
QUAD CITIES 2 |
95 |
|
HOLDING POWER AT THIS LEVEL DUE TO A TURBINE CONTROL VALVE PROBLEM |
* |
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
ARKANSAS NUCLEAR 1 |
100 |
|
|
|
|
ARKANSAS NUCLEAR 2 |
0 |
09/15/2000 |
REFUELING OUTAGE - REPLACING STEAM GENERATORS - DEFUELED |
|
|
CALLAWAY 1 |
100 |
|
|
|
|
COMANCHE PEAK 1 |
100 |
|
|
|
|
COMANCHE PEAK 2 |
0 |
09/30/2000 |
REFUELING OUTAGE - DEFUELED |
|
|
COOPER 1 |
100 |
|
|
|
|
DIABLO CANYON 1 |
0 |
10/08/2000 |
ENTERING REFUELING OUTAGE |
|
|
DIABLO CANYON 2 |
100 |
|
|
|
|
FT CALHOUN 1 |
75 |
|
DECREASING POWER DUE TO INDICATION OF REACTOR COOLANT PUMP SEAL DEGRADATION (NOT LEAKAGE) - PLAN TO GO TO COLD SHUTDOWN TO REPLACE SEAL PRIOR TO SEAL FAILURE |
* |
|
GRAND GULF 1 |
100 |
|
|
|
|
PALO VERDE 1 |
100 |
|
|
|
|
PALO VERDE 2 |
0 |
10/03/2000 |
REFUELING OUTAGE - DEFUELED |
* |
|
PALO VERDE 3 |
99 |
|
HOLDING POWER AT THIS LEVEL DUE TO THERMAL LIMITS |
* |
|
RIVER BEND 1 |
95 |
|
POWER UP RATE IN PROGRESS |
|
|
SAN ONOFRE 2 |
0 |
10/07/2000 |
ENTERING REFUELING OUTAGE - HEAD LIFT IN PROGRESS |
* |
|
SAN ONOFRE 3 |
100 |
|
|
|
|
SOUTH TEXAS 1 |
100 |
|
|
|
|
SOUTH TEXAS 2 |
100 |
|
|
|
|
WATERFORD 3 |
100 |
|
|
|
|
WNP-2 |
100 |
|
|
|
|
WOLF CREEK 1 |
0 |
09/29/2000 |
REFUELING OUTAGE - DEFUELED |
|
|