Interstate Lead Company
Site ID: ALD041906173
Location: Leeds, Jefferson County, AL
Congressional District: 06
NPL Status: Proposed: 09/18/85; Final 06/10/86
Project Manager
Site Repository:
Leeds Public Library
802 Parkway Dr. SE
Leeds, AL 35094
Documents:
Site Background:
The ILCO facility, located in Leeds, Alabama, was operated as a secondary
lead smelter and lead battery recycling facility from 1970 to 1992.
From approximately 1970 to 1984, the company reportedly used lead-contaminated
materials such as blast furnace slag, battery casings, and wastewater
treatment sludge as fill material at seven satellite sites in and
around the City of Leeds which are known as the: ILCO Parking Lot,
Gulf/BP Service Station (currently operated as a BP Service Station),
J & L Fabricators, Flemmings Patio, the Connell Property, the
City of Leeds Landfill, and the Church of God of Prophecy in Acmar,
herein referred to as the Acmar Church of God. The ILCO main facility
is bordered by an abandoned foundry and a wooded area to the south,
an unnamed tributary to Dry Creek, to the west, Borden Avenue and
the ILCO Parking Lot to the north and another business to the east.
The area is primarily industrial with a few residences within a
half-mile radius. The Interstate Lead Company ceased operations
in March 1992 and declared bankruptcy shortly thereafter
Cleanup Progress: Threat Mitigated by Physical Clean-up Work
The operator of the ILCO facility refused to conduct an RI/FS;
therefore, EPA performed a fund-lead RI/FS. ILCO ceased operations
in 1992, and abandoned the ILCO facility. Shortly thereafter, EPA
initiated a fund-lead emergency removal action to mitigate the imminent
threat associated with the abandoned ILCO main facility. EPA issued
RODs for each of the 3 operable units comprising the Site. The estimated
cost of implementing the selected remedies is approximately $60,000,000.
As the State of Alabama did not have sufficient resources to fund
the state cost share, a fund-lead cleanup was not an option. Based
upon ILCO's operating records, EPA identified approximately 979 PRPs
who sent spent batteries or other lead bearing waste material to
the Site. EPA issued notice letters to these PRPs in the fall of
1993. Special Notice Letters were issued to large quantity generators
in the fall of 1995. On September 30, 1996, the Region requested
DOJ to concur in a settlement with 20 generator PRPs at the ILCO
site. Under the terms of the proposed settlement, the settling defendants
will conduct RD/RA for the entire Site including all seven satellite
sites, and will reimburse the United States for $1,823,644 of $16,683,773
in past response costs. Also, the ILCO PRPs will reimburse the United
States for future oversight costs related to the Consent Decree in
excess of $300,000. Under the guidance on orphan share compensation
dated June 3, 1996, the Region, with Headquarters concurrence, has
agreed to compensate the Settling Defendants by giving them a credit
of $14,860,125 against outstanding past costs which represents 25%
of the estimated future cleanup costs. This settlement is one of
the first to provide for compensation to settlors under the orphan
share reform in accordance with the recently issued guidance. In
addition, proceeds from deminimis settlements will be split between
EPA and the Settling Defendants 50-50 with EPA's share to be applied
against outstanding past costs. Based upon deminimis settlements
totaling over $1.8 million, the PRPs were wired over $900,000 in
May 1999.
The Remedial Design (RD) for the ILCO Superfund site was approved
on March 12, 1999. In coordination with the Alabama Department of
Environmental Management, EPA modified the RD document to include
groundwater monitoring. The Record of Decision (ROD) calls for a
pump and treat system, but the ROD does allow for groundwater monitoring
to see if a technical impracticability waiver is needed. However,
if groundwater monitoring continues during the Remedial Action (RA)
at the site, the levels may meet the action levels specified in the
ROD. The levels of lead in groundwater are vastly lower from the
levels found during the Remedial Investigation (RI) since a removal
action has contained the source and since the sampling protocols
have changed to a slow purge technique. Lead is not currently detected
above action levels in groundwater in any of the wells at the site.
There are several metals still above Maximum Contaminant Levels (MCLs),
but the concentrations of these contaminants are approaching the
MCL. The PRP group requested a ROD amendment to change the groundwater
cleanup levels in a document submitted separately from the RD, but
EPA previously directed the PRPs in the comments on the Pre-Final
Design to include groundwater monitoring in the final design. ADEM
has participated throughout this entire process.
The Remedial Action Workplan was approved in January 2000. RMT,
Inc. was contracted by the Settling Defendants to conduct the remedial
action for OU 1 and Ou 2. A preconstruction meeting was held on January
19, 2000. RMT, Inc. is bringing the soils from the satellite sites
to the main facility for treatment. Contaminated soil from the satellite
sites and the main facility are being stabilized and rendered non-hazardous.
Due to continuous disagreements between the PRPs and their contractor,
the PRPs informed EPA on June 6, 2001, that RMT, INC had been directed
to demobilize from the site(s). A steering group representing the
PRPs selected ENTACT of Irving, Texas as the new supervising contractor
to complete the remediation required at the site(s). ENTACT did a
good job getting up to speed quickly continuing to make progress
with the remedation activities at the site. The remedial action report
addressing the remediation of all contaminated soil at the site above
action levels was approved by EPA in September 2006.
EPA is currently reviewing groundwater data submitted by the PRPs
to determine if natural attenuation or a technical impracticability
waiver is more appropriate than the pump and treat system selected in
the ROD. Any deviation from the ROD will be documented by Fact Sheet,
ESD, or ROD Ammendment as appropriate. The next five-year review
is scheduled for 2011.
|