[Federal Register: August 19, 2008 (Volume 73, Number 161)]
[Notices]               
[Page 48376-48377]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr19au08-42]                         


[[Page 48376]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army; Corps of Engineers

 
Intent To Prepare a Draft Environmental Impact Statement for the 
Reopening of an Idle Open Pit Taconite Mine and Construction and 
Operation of a Taconite Ore Concentration Plant Proposed by Mesabi 
Mining, LLC and Steel Dynamics, Inc. (Collectively, the Applicant) Near 
Aurora and Hoyt Lakes in St. Louis County, MN

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DOD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: Mesabi Mining, LLC and Steel Dynamics, Inc. have applied to 
the St. Paul District, Corps of Engineers (Corps) for a Clean Water Act 
Section 404 permit to discharge fill material into jurisdictional 
wetlands to facilitate the reopening of an open pit taconite mine and 
construction and operation of a taconite ore concentration plant near 
Aurora and Hoyt Lakes in St. Louis County, MN. Tailings would be 
discharged into an existing, idle open pit mine. The proposed project 
is known as the Mesabi Nugget Phase II Project. The project would be 
located entirely on portions of the site of the former LTV Steel Mining 
Company Facility (also known as Erie Mining Company prior to 1986). 
Taconite mining was conducted at the site from the late 1950s until 
operations ceased in early 2001. Prior to taconite mining, the area was 
also mined for natural iron ore in nearby pits as early as 1903. Mesabi 
Mining now proposes to reopen and mine taconite ore from two open pits, 
haul the ore in trucks to a proposed new processing plant where the ore 
would be crushed, ground, magnetically separated, and then passed 
through a flotation circuit to produce a concentrate. About one-third 
of the concentrate (approximately 1.04 million metric tonnes per year) 
would be used as feed for Mesabi Nugget Delaware's on-site Large Scale 
Demonstration Project (LSDP) iron nugget facility that was permitted in 
2005 and will be ready for operation in the second quarter of 2009. The 
remainder of the concentrate (approximately 2.09 million metric tonnes 
per year) would be shipped by rail for use in other facilities. The 
mining process would require the construction of overburden and waste 
rock, and lean ore stockpiles adjacent to the open pits. The project 
would operate 24 hours per day; 365 days per year during its proposed 
20-year life. The project area would be approximately 4,760 acres, of 
which approximately 3,820 acres (80 percent) has previously been 
disturbed by mining activities.
    The project would require the discharge of fill material into 
approximately 235 acres of wetlands. While some of the wetlands may be 
isolated, the majority of the wetlands are abutting Second Creek (a 
tributary to the Partridge River) or an unnamed tributary (Unnamed 
Creek) to the Partridge River. The Partridge River is a tributary to 
the St. Louis River, which is navigable water of the United States up 
to the mouth of the Embarrass River. The Applicant proposes to develop 
a detailed compensatory wetland mitigation plan for inclusion in the 
Draft Environmental Impact Statement (DEIS) to provide compensation for 
the unavoidable wetland impacts planned during at least the first five 
years of the project. Conceptual wetland mitigation plans will be 
developed for inclusion in the DEIS to provide compensation for the 
unavoidable wetland impacts planned during the remainder of the project 
(years six through twenty). The discharge of dredged or fill material 
into waters of the United States requires a permit issued by the Corps 
under Section 404 of the Clean Water Act. The Final Environmental 
Impact Statement (FEIS) will be used as a basis for the permit decision 
and to ensure compliance with the National Environmental Policy Act 
(NEPA).

ADDRESSES: Questions concerning the DEIS can be addressed to Mr. Jon K. 
Ahlness, Regulatory Branch by letter at U.S. Army Corps of Engineers, 
190 Fifth Street East, Suite 401, St. Paul, MN 55101-1638, by telephone 
or by e-mail at jon.k.ahlness@usace.army.mil.

FOR FURTHER INFORMATION CONTACT: Mr. Jon K. Ahlness, (651) 290-5381.

SUPPLEMENTARY INFORMATION: The Corps and the State of Minnesota will 
jointly prepare the DEIS. The Corps is the lead federal agency and the 
Minnesota Department of Natural Resources (MnDNR) is the lead state 
agency. To determine issues to be addressed in the DEIS, a scoping 
process will be conducted. The MnDNR, with assistance from the Corps, 
will prepare and release to the public a Draft Scoping Decision 
Document (Draft SDD) and a Scoping Environmental Assessment Worksheet 
(SEAW). Federal, state, and local agencies; the general public; 
interested private organizations and parties; and affected Native 
American tribes will have 30 days to provide comments on those two 
documents. During the 30-day public comment period, the Corps and the 
MnDNR will jointly conduct a public scoping meeting. The meeting will 
be held on Wednesday, September 3, 2008, from 6 p.m. to 9 p.m. at the 
Aurora Community Center at 15 West 1st Avenue North, Aurora, MN. The 
MnDNR, with assistance from the Corps will prepare and release to the 
public a Final SDD based upon the comments received during the scoping 
process. Significant issues and resources identified in the Final SDD 
will be addressed in the DEIS.
    The DEIS will assess impacts of the proposed action and reasonable 
alternatives, identify and evaluate mitigation alternatives, and 
discuss potential environmental monitoring. Anyone who has an interest 
in participating in the development of the DEIS is invited to contact 
the St. Paul District, Corps of Engineers. Major issues identified to 
date for discussion in the DEIS are the impacts of the proposed project 
on:
    1. Fish, wildlife, and ecologically sensitive resources.
    2. Water resources, including: surface and groundwater resources; 
waters of the U.S., including wetlands; and receiving stream 
geomorphology.
    3. Water quality, including: surface water runoff; and storm water 
management.
    4. Air quality.
    5. Cumulative impacts, including: wildlife habitat loss/
fragmentation and habitat corridor obstruction/landscape barriers; 
wetlands in the Partridge River watershed; loss of threatened and 
endangered plant species; air quality in federally-administered Class I 
areas; air quality in Class II areas; water quality; streamflow and 
lake level changes; and socioeconomic impacts.

Additional issues of interest may be identified through the public 
scoping process. We anticipate that the DEIS will be available to the 
public in March of 2009.
    Issuing a permit for the reopening of an open pit taconite mine and 
the construction and operation of a taconite ore concentration facility 
is considered to be a major Federal action that may have a significant 
impact on the quality of the human environment. The project: (1) would 
have a significant adverse effect on wetlands (which are special 
aquatic sites), and (2) has the potential to significantly affect water 
quality, groundwater, air quality, fish, and wildlife. Our 
environmental review will be conducted to meet the requirements of the 
National Environmental Policy Act of 1969, National Historic 
Preservation Act of 1966, Council of Environmental Quality Regulations,

[[Page 48377]]

Endangered Species Act of 1973, Section 404 of the Clean Water Act, and 
other applicable laws and regulations.

    Dated: August 7, 2008.
Jon L. Christensen,
Colonel, Corps of Engineers, District Engineer.
 [FR Doc. E8-19164 Filed 8-18-08; 8:45 am]

BILLING CODE 3710-CY-P