[Federal Register: November 30, 2006 (Volume 71, Number 230)]
[Notices]               
[Page 69205-69206]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr30no06-26]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP05-357-004]

 
Cheniere Creole Trail Pipeline, L.P.; Notice of Amendment

November 22, 2006.
    Take notice that on November 16, 2006, Cheniere Creole Trail 
Pipeline, L.P. (Creole Trail Pipeline), 717 Texas Avenue, Suite 3100, 
Houston, Texas 77002, filed in Docket No. CP05-357-004, an application 
to amend its pending amendment application filed on August 4, 2006, in 
Docket No. CP05-357-003. Creole Trail Pipeline explains that it was 
granted certificate authorization on June 15, 2006, in

[[Page 69206]]

Docket Nos. CP05-357-000, et al., to, in part, construct 116.8-mile, 
dual 42-inch pipelines, referred to as Line 1 and Line 2--Segments 2 
and 3. In the pending August 4, 2006 amendment application, Creole 
Trail Pipeline requests authorization to construct 18.1 miles of 42-
inch pipeline, referred to as Segment 1, to interconnect the 
certificated 116.8-mile dual pipelines to Cheniere Sabine Pass 
Pipeline, L.P. On November 16, 2006, concurrently with the instant 
filing, Creole Trail Pipeline submitted, in Docket No. CP05-357-005, a 
motion to vacate the certificate authorization granted on June 15, 
2006, to construct Line 2. Herein, Creole Trail Pipeline withdraws its 
pending request for deferred rate and accounting treatment and requests 
approval of revised initial system-wide transportation rates to reflect 
the effects of vacating its authorization to construct Line 2.
    The application is on file with the Commission and open for public 
inspection. This application is available for review at the Commission 
in the Public Reference Room or may be viewed on the Commission's Web 
site at http://www.ferc.gov using the ``eLibrary'' link. Enter the 

docket number excluding the last three digits in the docket number 
field to access the document. For assistance, please contact FERC 
Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208-
3676, or for TTY, contact (202) 502-8659.
    Any questions regarding the application should be directed to 
Patricia Outtrim, Cheniere Creole Trail Pipeline, L.P., 717 Texas 
Avenue, Suite 3100, Houston, Texas 77002, (713) 659-1361 or Lisa 
Tonery, King & Spalding LLP, 1185 Avenue of the Americas, New York, NY 
10036, (212) 556-2307.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date listed below, file with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 14 copies of this filing and all subsequent filings made with 
the Commission and must mail a copy of all filing to the applicant and 
to every other party in the proceeding. Only parties to the proceeding 
can ask for court review of Commission orders in the proceeding.
    However, other persons do not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to this 
project provide copies of their protests only to the party or parties 
directly involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project, or in support of or in opposition to this project, should 
submit an original and two copies of their comments to the Secretary of 
the Commission. Environmental commenters will be placed on the 
Commission's environmental mailing list, will receive copies of the 
environmental documents, and will be notified of meetings associated 
with the Commission's environmental review process. Environmental 
commenters will not be required to serve copies of filed documents on 
all other parties. The Commission's rules require that persons filing 
comments in opposition to the project provide copies of their protests 
only to the applicant. However, the non-party commenters will not 
receive copies of all documents filed by other parties or issued by the 
Commission (except for the mailing of environmental documents issued by 
the Commission) and will not have the right to seek court review of the 
Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the Internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site (http://www.ferc.gov) under the ``e-Filing'' link.

    Comment Date: December 13, 2006.

Magalie R. Salas,
Secretary.
[FR Doc. E6-20262 Filed 11-29-06; 8:45 am]

BILLING CODE 6717-01-P