PART 48--VALUE ENGINEERING--Table of Contents
 
                  Subpart 48.1--Policies and Procedures
 
48.105  Relationship to other incentives.

    Contractors should be offered the fullest possible range of 
motivation, yet the benefits of an accepted VECP should not be rewarded 
both as value engineering shares and under performance, design-to-cost, 
or similar incentives of the contract. To that end, when performance, 
design-to-cost, or similar targets are set and incentivized, the targets 
of such incentives affected by the VECP are not to be adjusted because 
of the acceptance of the VECP. Only those benefits of an accepted VECP 
not rewardable under

[[Page 905]]

other incentives are rewarded under a value engineering clause.

[48 FR 42443, Sept. 19, 1983, as amended at 54 FR 5057, Jan. 31, 1989]