            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 32--CONTRACT FINANCING--Table of Contents
 
                      Subpart 32.9--Prompt Payment
 
Sec. 32.904  Determining payment due dates.

    (a) General. Agency procedures must ensure that, when specifying due 
dates, contracting officers give full consideration to the time 
reasonably required by Government officials to fulfill their 
administrative responsibilities under the contract.
    (b) Payment due dates. Except as prescribed in paragraphs (c) 
through (f) of this section, or as authorized in 32.908(a)(2) or (c)(2), 
the due date for making an invoice payment is as follows:
    (1) The later of the following two events:
    (i) The 30th day after the designated billing office receives a 
proper invoice from the contractor (except as provided in paragraph 
(b)(3) of this section).
    (ii) The 30th day after Government acceptance of supplies delivered 
or services performed.
    (A) For a final invoice, when the payment amount is subject to 
contract settlement actions, acceptance is deemed to occur on the 
effective date of the contract settlement.
    (B) For the sole purpose of computing an interest penalty that might 
be due the contractor--
    (1) Government acceptance is deemed to occur constructively on the 
7th day after the contractor delivers supplies or performs services in 
accordance with the terms and conditions of the contract, unless there 
is a disagreement over quantity, quality, or contractor compliance with 
a contract requirement;
    (2) If actual acceptance occurs within the constructive acceptance 
period, the Government must base the determination of an interest 
penalty on the actual date of acceptance;
    (3) The constructive acceptance requirement does not compel 
Government officials to accept supplies or services, perform contract 
administration functions, or make payment prior to fulfilling their 
responsibilities; and
    (4) Except for a contract for the purchase of a commercial item, 
including a brand-name commercial item for authorized resale (e.g., 
commissary items), the contracting officer may specify a longer period 
for constructive acceptance in the solicitation and resulting contract, 
if required to afford the Government a reasonable opportunity to inspect 
and test the supplies furnished or to evaluate the services performed. 
The contracting officer must document in the contract file the 
justification for extending the constructive acceptance period beyond 7 
days. Extended acceptance periods

[[Page 673]]

must not be a routine agency practice and must be used only when 
necessary to permit proper Government inspection and testing of the 
supplies delivered or services performed.
    (2) If the contract does not require submission of an invoice for 
payment (e.g., periodic lease payments), the contracting officer must 
specify the due date in the contract.
    (3) If the designated billing office fails to annotate the invoice 
with the actual date of receipt at the time of receipt, the invoice 
payment due date is the 30th day after the date of the contractor's 
invoice, provided the designated billing office receives a proper 
invoice and there is no disagreement over quantity, quality, or 
contractor compliance with contract requirements.
    (c) Architect-engineer contracts. (1) The due date for making 
payments on contracts that contain the clause at 52.232-10, Payments 
Under Fixed-Price Architect-Engineer Contracts, is as follows:
    (i) The due date for work or services completed by the contractor is 
the later of the following two events:
    (A) The 30th day after the designated billing office receives a 
proper invoice from the contractor.
    (B) The 30th day after Government acceptance of the work or services 
completed by the contractor.
    (1) For a final invoice, when the payment amount is subject to 
contract settlement actions (e.g., release of claims), acceptance is 
deemed to occur on the effective date of the settlement.
    (2) For the sole purpose of computing an interest penalty that might 
be due the contractor, Government acceptance is deemed to occur 
constructively on the 7th day after the contractor completes the work or 
services in accordance with the terms and conditions of the contract 
(see also paragraph (c)(2) of this section). If actual acceptance occurs 
within the constructive acceptance period, the Government must base the 
determination of an interest penalty on the actual date of acceptance.
    (ii) The due date for progress payments is the 30th day after 
Government approval of contractor estimates of work or services 
accomplished. For the sole purpose of computing an interest penalty that 
might be due the contractor--
    (A) Government approval is deemed to occur constructively on the 7th 
day after the designated billing office receives the contractor 
estimates (see also paragraph (c)(2) of this section).
    (B) If actual approval occurs within the constructive approval 
period, the Government must base the determination of an interest 
penalty on the actual date of approval.
    (iii) If the designated billing office fails to annotate the invoice 
or payment request with the actual date of receipt at the time of 
receipt, the payment due date is the 30th day after the date of the 
contractor's invoice or payment request, provided the designated billing 
office receives a proper invoice or payment request and there is no 
disagreement over quantity, quality, or contractor compliance with 
contract requirements.
    (2) The constructive acceptance and constructive approval 
requirements described in paragraphs (c)(1)(i) and (ii) of this section 
are conditioned upon receipt of a proper payment request and no 
disagreement over quantity, quality, contractor compliance with contract 
requirements, or the requested progress payment amount. These 
requirements do not compel Government officials to accept work or 
services, approve contractor estimates, perform contract administration 
functions, or make payment prior to fulfilling their responsibilities. 
The contracting officer may specify a longer period for constructive 
acceptance or constructive approval, if required to afford the 
Government a reasonable opportunity to inspect and test the supplies 
furnished or to evaluate the services performed. The contracting officer 
must document in the contract file the justification for extending the 
constructive acceptance or approval period beyond 7 days.
    (d) Construction contracts. (1) The due date for making payments on 
construction contracts is as follows:
    (i) The due date for making progress payments based on contracting 
officer approval of the estimated amount and value of work or services 
performed, including payments for reaching milestones in any project, is 
14 days after

[[Page 674]]

the designated billing office receives a proper payment request.
    (A) If the designated billing office fails to annotate the payment 
request with the actual date of receipt at the time of receipt, the 
payment due date is the 14th day after the date of the contractor's 
payment request, provided the designated billing office receives a 
proper payment request and there is no disagreement over quantity, 
quality, or contractor compliance with contract requirements.
    (B) The contracting officer may specify a longer period in the 
solicitation and resulting contract if required to afford the Government 
a reasonable opportunity to adequately inspect the work and to determine 
the adequacy of the contractor's performance under the contract. The 
contracting officer must document in the contract file the justification 
for extending the due date beyond 14 days.
    (C) The contracting officer must not approve progress payment 
requests unless the certification and substantiation of amounts 
requested are provided as required by the clause at 52.232-5, Payments 
Under Fixed-Price Construction Contracts.
    (ii) The due date for payment of any amounts retained by the 
contracting officer in accordance with the clause at 52.232-5, Payments 
Under Fixed-Price Construction Contracts, will be as specified in the 
contract or, if not specified, 30 days after approval by the contracting 
officer for release to the contractor. The contracting officer must base 
the release of retained amounts on the contracting officer's 
determination that satisfactory progress has been made.
    (iii) The due date for final payments based on completion and 
acceptance of all work (including any retained amounts), and payments 
for partial deliveries that have been accepted by the Government (e.g., 
each separate building, public work, or other division of the contract 
for which the price is stated separately in the contract) is as follows:
    (A) The later of the following two events:
    (1) The 30th day after the designated billing office receives a 
proper invoice from the contractor.
    (2) The 30th day after Government acceptance of the work or services 
completed by the contractor. For a final invoice, when the payment 
amount is subject to contract settlement actions (e.g., release of 
contractor claims), acceptance is deemed to occur on the effective date 
of the contract settlement.
    (B) If the designated billing office fails to annotate the invoice 
with the actual date of receipt at the time of receipt, the invoice 
payment due date is the 30th day after the date of the contractor's 
invoice, provided the designated billing office receives a proper 
invoice and there is no disagreement over quantity, quality, or 
contractor compliance with contract requirements.
    (2) For the sole purpose of computing an interest penalty that might 
be due the contractor for payments described in paragraph (d)(1)(iii) of 
this section--
    (i) Government acceptance or approval is deemed to occur 
constructively on the 7th day after the contractor completes the work or 
services in accordance with the terms and conditions of the contract, 
unless there is a disagreement over quantity, quality, contractor 
compliance with a contract requirement, or the requested amount;
    (ii) If actual acceptance occurs within the constructive acceptance 
period, the Government must base the determination of an interest 
penalty on the actual date of acceptance;
    (iii) The constructive acceptance requirement does not compel 
Government officials to accept work or services, approve contractor 
estimates, perform contract administration functions, or make payment 
prior to fulfilling their responsibilities; and
    (iv) The contracting officer may specify a longer period for 
constructive acceptance or constructive approval in the solicitation and 
resulting contract, if required to afford the Government a reasonable 
opportunity to adequately inspect the work and to determine the adequacy 
of the contractor's performance under the contract. The contracting 
officer must document in the contract file the justification for 
extending the constructive acceptance or approval beyond 7 days.

[[Page 675]]

    (3) Construction contracts contain special provisions concerning 
contractor payments to subcontractors, along with special contractor 
certification requirements. The Office of Management and Budget has 
determined that these certifications must not be construed as final 
acceptance of the subcontractor's performance. The certification in 
52.232-5(c) implements this determination; however, certificates are 
still acceptable if the contractor deletes paragraph (c)(4) of 52.232-5 
from the certificate.
    (4)(i) Paragraph (d) of the clause at 52.232-5, Payments under 
Fixed-Price Construction Contracts, and paragraph (e)(6) of the clause 
at 52.232-27, Prompt Payment for Construction Contracts, provide for the 
contractor to pay interest on unearned amounts in certain circumstances. 
The Government must recover this interest from subsequent payments to 
the contractor. Therefore, contracting officers normally must make no 
demand for payment. Contracting officers must--
    (A) Compute the amount in accordance with the clause;
    (B) Provide the contractor with a final decision; and
    (C) Notify the payment office of the amount to be withheld.
    (ii) The payment office is responsible for making the deduction of 
interest. Amounts collected in accordance with these provisions revert 
to the United States Treasury.
    (e) Cost-reimbursement contracts for services. For purposes of 
computing late payment interest penalties that may apply, the due date 
for making interim payments on cost-reimbursement contracts for services 
is 30 days after the date of receipt of a proper invoice.
    (f) Food and specified items.

------------------------------------------------------------------------
                                               Payment must be made as
        If the items delivered are:           close as possible to, but
                                                   not later than:
------------------------------------------------------------------------
(1) Meat or meat food products. As defined   7th day after product
 in section 2(a)(3) of the Packers and        delivery.
 Stockyard Act of 1921 (7 U.S.C. 182(3)),
 and as further defined in Public Law 98-
 181, including any edible fresh or frozen
 poultry meat, any perishable poultry meat
 food product, fresh eggs, and any
 perishable egg product.
(2) Fresh or frozen fish. As defined in      7th day after product
 section 204(3) of the Fish and Seafood       delivery.
 Promotion Act of 1986 (16 U.S.C. 4003(3)).
(3) Perishable agricultural commodities. As  10th day after product
 defined in section 1(4) of the Perishable    delivery, unless another
 Agricultural Commodities Act of 1930 (7      date is specified in the
 U.S.C. 499a(4)).                             contract.
(4) Dairy products. As defined in section    10th day after a proper
 111(e) of the Dairy Production               invoice has been received.
 Stabilization Act of 1983 (7 U.S.C.
 4502(e)), edible fats or oils, and food
 products prepared from edible fats or
 oils. Liquid milk, cheese, certain
 processed cheese products, butter, yogurt,
 ice cream, mayonnaise, salad dressings,
 and other similar products fall within
 this classification. Nothing in the Act
 limits this classification to refrigerated
 products. If questions arise regarding the
 proper classification of a specific
 product, the contracting officer must
 follow prevailing industry practices in
 specifying a contract payment due date.
 The burden of proof that a classification
 of a specific product is, in fact,
 prevailing industry practice is upon the
 contractor making the representation.
------------------------------------------------------------------------

    (g) Multiple payment due dates. Contracting officers may encourage, 
but not require, contractors to submit separate invoices for products 
with different payment due dates under the same contract or order. When 
an invoice contains items with different payment due dates (i.e., a 
mixed invoice), the payment office will, subject to agency policy--
    (1) Pay the entire invoice on the earliest due date; or
    (2) Split invoice payments, making payments by the applicable due 
dates.