[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR32.503-6]

[Page 654-656]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 32--CONTRACT FINANCING--Table of Contents
 
             Subpart 32.5--Progress Payments Based on Costs
 
Sec. 32.503-6  Suspension or reduction of payments.

    (a) General. The Progress Payments clause provides a Government 
right to reduce or suspend progress payments, or to increase the 
liquidation rate, under specified conditions. These conditions and 
actions are discussed in paragraphs (b) through (g) below.
    (1) The contracting officer shall take these actions only in 
accordance with the contract terms and never precipitately or 
arbitrarily. These actions should be taken only after--
    (i) Notifying the contractor of the intended action and providing an 
opportunity for discussion;
    (ii) Evaluating the effect of the action on the contractor's 
operations, based on the contractor's financial condition, projected 
cash requirements, and the existing or available credit arrangements; 
and
    (iii) Considering the general equities of the particular situation.
    (2) The contracting officer shall take immediate unilateral action 
only if warranted by circumstances such as overpayments or 
unsatisfactory contract performance.
    (3) In all cases, the contracting officer shall (i) act fairly and 
reasonably, (ii) base decisions on substantial evidence, and (iii) 
document the contract file. Findings made under paragraph (c) of the 
Progress Payments clause shall be in writing.
    (b) Contractor noncompliance. (1) The contractor must comply with 
all material requirements of the contract. This includes the requirement 
to maintain an efficient and reliable accounting system and controls, 
adequate for the

[[Page 655]]

proper administration of progress payments. If the system or controls 
are deemed inadequate, progress payments shall be suspended (or the 
portion of progress payments associated with the unacceptable portion of 
the contractor's accounting system shall be suspended) until the 
necessary changes have been made.
    (2) If the contractor fails to comply with the contract without 
fault or negligence, the contracting officer will not take action 
permitted by paragraph (c)(1) of the Progress Payments clause, other 
than to correct overpayments and collect amounts due from the 
contractor.
    (c) Unsatisfactory financial condition. (1) If the contracting 
officer finds that contract performance (including full liquidation of 
progress payments) is endangered by the contractor's financial 
condition, or by a failure to make progress, the contracting officer 
shall require the contractor to make additional operating or financial 
arrangements adequate for completing the contract without loss to the 
Government.
    (2) If the contracting officer concludes that further progress 
payments would increase the probable loss to the Government, the 
contracting officer shall suspend progress payments and all other 
payments until the unliquidated balance of progress payments is 
eliminated.
    (d) Excessive inventory. If the inventory allocated to the contract 
exceeds reasonable requirements (including a reasonable accumulation of 
inventory for continuity of operations), the contracting officer should, 
in addition to requiring the transfer of excessive inventory from the 
contract, take one or more of the following actions, as necessary, to 
avoid or correct overpayment:
    (1) Eliminate the costs of the excessive inventory from the costs 
eligible for progress payments, with appropriate reduction in progress 
payments outstanding.
    (2) Apply additional deductions to billings for deliveries (increase 
liquidation).
    (e) Delinquency in payment of costs of performance. (1) If the 
contractor is delinquent in paying the costs of contract performance in 
the ordinary course of business, the contracting officer shall evaluate 
whether the delinquency is caused by an unsatisfactory financial 
condition and, if so, shall apply the guidance in paragraph (c) above. 
If the contractor's financial condition is satisfactory, the contracting 
officer shall not deny progress payments if the contractor agrees to--
    (i) Cure the payment delinquencies;
    (ii) Avoid further delinquencies; and
    (iii) Make additional arrangements adequate for completing the 
contract without loss to the Government.
    (2) If the contractor has, in good faith, disputed amounts claimed 
by subcontractors, suppliers, or others, the contracting officer shall 
not consider the payments delinquent until the amounts due are 
established by the parties through litigation or arbitration. However, 
the amounts shall be excluded from costs eligible for progress payments 
so long as they are disputed.
    (3) Determinations of delinquency in making contributions under 
employee pension, profit sharing, or stock ownership plans, and 
exclusion of costs for such contributions from progress payment 
requests, shall be in accordance with paragraph (a)(3) of the clause at 
52.232-16, Progress Payments, without regard to the provisions of 
32.503-6.
    (f) Fair value of undelivered work. Progress payments must be 
commensurate with the fair value of work accomplished in accordance with 
contract requirements. Governed by the principles of paragraphs (c) and 
(e) of this subsection, the contracting officer must adjust progress 
payments when necessary to ensure that the fair value of undelivered 
work equals or exceeds the amount of unliquidated progress payments. On 
loss contracts, the application of a loss ratio as described in 
paragraph (g) of this subsection constitutes this adjustment.
    (g) Loss contracts. (1) If the sum of the total costs incurred under 
a contract plus the estimated costs to complete the performance are 
likely to exceed the contract price, the contracting officer shall 
compute a loss ratio factor and adjust future progress payments to 
exclude the element of loss. The loss ratio factor is computed as 
follows:

[[Page 656]]

    (i) Revise the current contract price used in progress payment 
computations (the current ceiling price under fixed-price incentive 
contracts) to include any pending change orders and unpriced orders to 
the extent funds for the orders have been obligated.
    (ii) Divide the revised contract price by the sum of the total costs 
incurred to date plus the estimated additional costs of completing the 
contract performance.
    (2) If the contracting officer believes a loss is probable, future 
progress payment requests shall be modified as follows:
    (i) The contract price shall be the revised amount computed under 
subparagraph (1)(i) above.
    (ii) The total costs eligible for progress payments shall be the 
product of (A) the sum of paid costs eligible for progress payments 
times (B) the loss ratio factor computed under subparagraph (1)(ii) 
above.
    (iii) The costs applicable to items delivered, invoiced, and 
accepted shall not include costs in excess of the contract price of the 
items.
    (3) The contracting officer may use audit assistance, technical 
services, management reports, and other sources of pertinent data to 
evaluate progress payment requests. If the contracting officer concludes 
that the contractor's figures in the contractor's progress payment 
request are not correct, the contracting officer shall--
    (i) In the manner prescribed in paragraph (4) below, prepare a 
supplementary analysis to be attached to the contractor's request;
    (ii) Advise the contractor in writing of the differences; and
    (iii) Adjust all further progress payments in accordance with 
paragraph (1) above, using the contracting officer's figures, until the 
difference is resolved.
    (4) The following is an example of the supplementary analysis 
required in paragraph (g)(3) of this subsection:

                               Section I
Contract price..........................................      $2,850,000
Change orders and unpriced orders (to extent funds have          150,000
 been obligated)........................................
Revised contract price..................................       3,000,000

                               Section II

Total costs incurred to date............................       2,700,000
Estimated additional costs to complete..................         900,000
Total costs to complete.................................       3,600,000
                                                          ..............


                                                          [GRAPHIC] [TIFF OMITTED] TR27MR00.000
                                                          

Total costs eligible for progress payments..............       2,700,000
Loss ratio factor.......................................          x83.3%
Recognized costs for progress payments..................       2,249,100
Progress payment rate...................................          x80.0%
Alternate amount to be used.............................       1,799,280

                               Section III

Factored costs of items delivered*......................         750,000
Recognized costs applicable to undelivered items              1,499,100
 ($2,249,100-750,000)...................................

* This amount must be the same as the contract price of the items
  delivered.


[48 FR 42328, Sept. 19, 1983, as amended at 52 FR 30077, Aug. 12, 1987; 
54 FR 5056, Jan. 31, 1989; 54 FR 48989, Nov. 28, 1989; 64 FR 72451, Dec. 
27, 1999; 65 FR 16280, Mar. 27, 2000]