[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR32.1004]

[Page 680-682]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 32--CONTRACT FINANCING--Table of Contents
 
                Subpart 32.10--Performance-Based Payments
 
Sec. 32.1004  Procedures.

    Performance-based payments may be made either on a whole contract or 
on a deliverable item basis, unless otherwise prescribed by agency 
regulations. Financing payments to be made on a whole contract basis are 
applicable to the entire contract, and not to specific deliverable 
items. Financing payments to be made on a deliverable item basis are 
applicable to a specific individual deliverable item. (A deliverable 
item for these purposes is a separate item with a distinct unit price. 
Thus, a contract line item for 10 airplanes, with a unit price of 
$1,000,000 each, has 10 deliverable items--the separate planes. A 
contract line item for 1 lot of 10 airplanes, with a lot price of 
$10,000,000, has only one deliverable item--the lot.)
    (a) Establishing performance bases. (1) The basis for performance-
based payments may be either specifically described events (e.g., 
milestones) or some measurable criterion of performance. Each event or 
performance criterion that will trigger a finance payment must be an 
integral and necessary part of contract performance and must be 
identified in the contract, along with a description of what constitutes 
successful performance of the event or attainment of the performance 
criterion. The signing of contracts or modifications, the exercise of 
options, or other such actions must not be events or criteria for 
performance-based payments. An event need not be a critical event in 
order to trigger a payment, but the Government must be able to readily 
verify successful performance of each such event or performance 
criterion.
    (2) Events or criteria may be either severable or cumulative. The 
successful completion of a severable event or criterion is independent 
of the accomplishment of any other event or criterion. Conversely, the 
successful accomplishment of a cumulative event or criterion is 
dependent upon the previous accomplishment of another event. A contract 
may provide for more than one series of severable and/or cumulative 
performance events or criteria performed in parallel. The contracting 
officer must include the following in the contract:

[[Page 681]]

    (i) The contract must not permit payment for a cumulative event or 
criterion until the dependent event or criterion has been successfully 
completed.
    (ii) The contract must specifically identify severable events or 
criteria.
    (iii) The contract must identify which events or criteria are 
preconditions for the successful achievement of each cumulative event or 
criterion.
    (iv) Because performance-based payments are contract financing, 
events or criteria must not serve as a vehicle to reward the contractor 
for completion of performance levels over and above what is required for 
successful completion of the contract.
    (v) If payment of performance-based finance amounts is on a 
deliverable item basis, each event or performance criterion must be part 
of the performance necessary for that deliverable item and must be 
identified to a specific contract line item or subline item.
    (b) Establishing performance-based finance payment amounts. (1) The 
contracting officer must establish a complete, fully defined schedule of 
events or performance criteria and payment amounts when negotiating 
contract terms. If a contract action significantly affects the price, or 
event or performance criterion, the contracting officer responsible for 
pricing the contract modification must adjust the performance-based 
payment schedule appropriately.
    (2) Total performance-based payments must--
    (i) Reflect prudent contract financing provided only to the extent 
needed for contract performance (see 32.104(a)); and
    (ii) Not exceed 90 percent of the contract price if on a whole 
contract basis, or 90 percent of the delivery item price if on a 
delivery item basis.
    (3) The contract must specifically state the amount of each 
performance-based payment either as a dollar amount or as a percentage 
of a specifically identified price (e.g., contract price, or unit price 
of the deliverable item). The payment of contract financing has a cost 
to the Government in terms of interest paid by the Treasury to borrow 
funds to make the payment. Because the contracting officer has wide 
discretion as to the timing and amount of the performance-based 
payments, the contracting officer must ensure that--
    (i) The total contract price is fair and reasonable, all factors 
considered; and
    (ii) Performance-based payment amounts are commensurate with the 
value of the performance event or performance criterion, and are not 
expected to result in an unreasonably low or negative level of 
contractor investment in the contract. To confirm sufficient investment, 
the contracting officer may request expenditure profile information from 
offerors, but only if other information in the proposal, or information 
otherwise available to the contracting officer, is expected to be 
insufficient.
    (4) Unless agency procedures prescribe the bases for establishing 
performance-based payment amounts, contracting officers may establish 
them on any rational basis, including (but not limited to)--
    (i) Engineering estimates of stages of completion;
    (ii) Engineering estimates of hours or other measures of effort to 
be expended in performance of an event or achievement of a performance 
criterion; or
    (iii) The estimated projected cost of performance of particular 
events.
    (5) When subsequent contract modifications are issued, the 
contracting officer must adjust the performance-based payment schedule 
as necessary to reflect the actions required by those contract 
modifications.
    (c) Instructions for multiple appropriations. If there is more than 
one appropriation account (or subaccount) funding payments on the 
contract, the contracting officer must provide instructions to the 
Government payment office for distribution of financing payments to the 
respective funds accounts. Distribution instructions must be consistent 
with the contract's liquidation provisions.
    (d) Liquidating performance-based finance payments. Performance-
based amounts must be liquidated by deducting a percentage or a 
designated dollar amount from the delivery payments. The contracting 
officer must specify

[[Page 682]]

the liquidation rate or designated dollar amount in the contract. The 
method of liquidation must ensure complete liquidation no later than 
final payment.
    (1) If the contracting officer establishes the performance-based 
payments on a delivery item basis, the liquidation amount for each line 
item is the percent of that delivery item price that was previously paid 
under performance-based finance payments or the designated dollar 
amount.
    (2) If the performance-based finance payments are on a whole 
contract basis, liquidation is by predesignated liquidation amounts or 
liquidation percentages.
    (e) Competitive negotiated solicitations. (1) If a solicitation 
requests offerors to propose performance-based payments, the 
solicitation must specify--
    (i) What, if any, terms must be included in all offers; and
    (ii) The extent to which and how offeror-proposed performance-based 
payment terms will be evaluated. Unless agencies prescribe other 
evaluation procedures, if the contracting officer anticipates that the 
cost of providing performance-based payments would have a significant 
impact on determining the best value offer, the solicitation should 
include an adjustment of proposed prices to reflect the estimated cost 
to the Government of providing each offeror's proposed performance-based 
payments (see Alternate I to the provision at 52.232-28).
    (2) The contracting officer must--
    (i) Review the proposed terms to ensure they comply with this 
section; and
    (ii) Use the adjustment method in 32.205(c) if the price is to be 
adjusted for evaluation purposes in accordance with paragraph (e)(1)(ii) 
of this section.

[65 FR 16282, Mar. 27, 2000]