Sec. 34.004  Acquisition strategy.

    The program manager, as specified in agency procedures, shall 
develop an acquisition strategy tailored to the particular major system 
acquisition program. This strategy is the program manager's overall plan 
for satisfying the mission need in the most effective,

[[Page 701]]

economical, and timely manner. The strategy shall be in writing and 
prepared in accordance with the requirements of subpart 7.1, except 
where inconsistent with this part, and shall qualify as the acquisition 
plan for the major system acquisition, as required by that subpart.