[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR15.407-4]

[Page 278-279]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 15--CONTRACTING BY NEGOTIATION--Table of Contents
 
                     Subpart 15.4--Contract Pricing
 
Sec. 15.407-4  Should-cost review.

    (a) General. (1) Should-cost reviews are a specialized form of cost 
analysis. Should-cost reviews differ from traditional evaluation methods 
because they do not assume that a contractor's historical costs reflect 
efficient and economical operation. Instead, these reviews evaluate the 
economy and efficiency of the contractor's existing work force, methods, 
materials, facilities, operating systems, and management. These reviews 
are accomplished by a multi-functional team of Government contracting, 
contract administration, pricing, audit, and engineering 
representatives. The objective of should-cost reviews is to promote both 
short and long-range improvements in the contractor's economy and 
efficiency in order to reduce the cost of performance of Government 
contracts. In addition, by providing rationale for any recommendations 
and quantifying their impact on cost, the Government will be better able 
to develop realistic objectives for negotiation.
    (2) There are two types of should-cost reviews--program should-cost 
review (see paragraph (b) of this subsection) and overhead should-cost 
review (see paragraph (c) of this subsection). These should-cost reviews 
may be performed together or independently. The scope of a should-cost 
review can range from a large-scale review examining the contractor's 
entire operation (including plant-wide overhead and selected major 
subcontractors) to a small-scale tailored review examining specific 
portions of a contractor's operation.
    (b) Program should-cost review. (1) A program should-cost review is 
used to evaluate significant elements of direct costs, such as material 
and labor, and associated indirect costs, usually associated with the 
production of major systems. When a program should-cost review is 
conducted relative to a contractor proposal, a separate audit report on 
the proposal is required.
    (2) A program should-cost review should be considered, particularly 
in the case of a major system acquisition (see part 34), when--
    (i) Some initial production has already taken place;
    (ii) The contract will be awarded on a sole source basis;
    (iii) There are future year production requirements for substantial 
quantities of like items;
    (iv) The items being acquired have a history of increasing costs;
    (v) The work is sufficiently defined to permit an effective analysis 
and major changes are unlikely;
    (vi) Sufficient time is available to plan and adequately conduct the 
should-cost review; and
    (vii) Personnel with the required skills are available or can be 
assigned for the duration of the should-cost review.
    (3) The contracting officer should decide which elements of the 
contractor's operation have the greatest potential for cost savings and 
assign the available personnel resources accordingly. The expertise of 
on-site Government personnel should be used, when appropriate. While the 
particular elements to be analyzed are a function of the contract work 
task, elements such as

[[Page 279]]

manufacturing, pricing and accounting, management and organization, and 
subcontract and vendor management are normally reviewed in a should-cost 
review.
    (4) In acquisitions for which a program should-cost review is 
conducted, a separate program should-cost review team report, prepared 
in accordance with agency procedures, is required. The contracting 
officer shall consider the findings and recommendations contained in the 
program should-cost review team report when negotiating the contract 
price. After completing the negotiation, the contracting officer shall 
provide the ACO a report of any identified uneconomical or inefficient 
practices, together with a report of correction or disposition 
agreements reached with the contractor. The contracting officer shall 
establish a follow-up plan to monitor the correction of the uneconomical 
or inefficient practices.
    (5) When a program should-cost review is planned, the contracting 
officer should state this fact in the acquisition plan or acquisition 
plan updates (see subpart 7.1) and in the solicitation.
    (c) Overhead should-cost review. (1) An overhead should-cost review 
is used to evaluate indirect costs, such as fringe benefits, shipping 
and receiving, facilities and equipment, depreciation, plant maintenance 
and security, taxes, and general and administrative activities.
    It is normally used to evaluate and negotiate an FPRA with the 
contractor. When an overhead should-cost review is conducted, a separate 
audit report is required.
    (2) The following factors should be considered when selecting 
contractor sites for overhead should-cost reviews:
    (i) Dollar amount of Government business.
    (ii) Level of Government participation.
    (iii) Level of noncompetitive Government contracts.
    (iv) Volume of proposal activity.
    (v) Major system or program.
    (vi) Corporate reorganizations, mergers, acquisitions, or takeovers.
    (vii) Other conditions (e.g., changes in accounting systems, 
management, or business activity).
    (3) The objective of the overhead should-cost review is to evaluate 
significant indirect cost elements in-depth, and identify and recommend 
corrective actions regarding inefficient and uneconomical practices. If 
it is conducted in conjunction with a program should-cost review, a 
separate overhead should-cost review report is not required. However, 
the findings and recommendations of the overhead should-cost team, or 
any separate overhead should-cost review report, shall be provided to 
the ACO. The ACO should use this information to form the basis for the 
Government position in negotiating an FPRA with the contractor. The ACO 
shall establish a follow-up plan to monitor the correction of the 
uneconomical or inefficient practices.