                       Subpart 43.2--Change Orders
 
Sec. 43.205  Contract clauses.

    (a)(1) The contracting officer shall insert the clause at 52.243-1, 
Changes--Fixed-Price, in solicitations and contracts when a fixed-price 
contract for supplies is contemplated.
    (2) If the requirement is for services, other than architect-
engineer or other professional services, and no supplies are to be 
furnished, the contracting officer shall use the clause with its 
Alternate I.
    (3) If the requirement is for services (other than architect-
engineer services, transportation, or research and development) and 
supplies are to be furnished, the contracting officer shall use the 
clause with its Alternate II.
    (4) If the requirement is for architect-engineer or other 
professional services, the contracting officer shall use the clause with 
its Alternate III.
    (5) If the requirement is for transportation services, the 
contracting officer shall use the clause with its Alternate IV.
    (6) If it is desired to include the clause in solicitations and 
contracts when a research and development contract is contemplated, the 
contracting officer shall use the clause with its Alternate V.
    (b)(1) The contracting officer shall insert the clause at 52.243-2, 
Changes--Cost-Reimbursement, in solicitations and contracts when a cost-
reimbursement contract for supplies is contemplated.
    (2) If the requirement is for services and no supplies are to be 
furnished, the contracting officer shall use the clause with its 
Alternate I.
    (3) If the requirement is for services and supplies are to be 
furnished, the contracting officer shall use the clause with its 
Alternate II.
    (4) If the requirement is for construction, the contracting officer 
shall use the clause with its Alternate III.
    (5) If a facilities contract is contemplated, the contracting 
officer shall use the clause with its Alternate IV.
    (6) If it is desired to include the clause in solicitations and 
contracts when a research and development contract is contemplated, the 
contracting officer shall use the clause with its Alternate V.
    (c) Insert the clause at 52.243-3, Changes--Time-and-Materials or 
Labor-Hours, in solicitations and contracts when a time-and-materials or 
labor-hour contract is contemplated. The contracting officer may vary 
the 30-day period in paragraph (c) of the clause according to agency 
procedures.
    (d) The contracting officer shall insert the clause at 52.243-4, 
Changes, in solicitations and contracts for (1) dismantling, demolition, 
or removal of improvements; and (2) construction, when a fixed-price 
contract is contemplated and the contract amount is expected to exceed 
the simplified acquisition threshold.
    (e) The contracting officer shall insert the clause at 52.243-5, 
Changes and Changed Conditions, in solicitations and contracts for 
construction, when the contract amount is not expected to exceed the 
simplified acquisition threshold.
    (f) The contracting officer may insert a clause, substantially the 
same as the clause at 52.243-6, Change Order Accounting, in 
solicitations and contracts for supply and research and development 
contracts of significant technical complexity, if numerous changes are 
anticipated. The clause may be included in solicitations and contracts 
for construction if deemed appropriate by the contracting officer.