Incentive/Disincentives (ID) Program
Overview
Contacts
Reference Materials
Instructional Pages
Overview
 
Introduction
 
The use of Liquidated Damages (LD’s) as an enforcement tool for work completion is not a success.   For some projects, the reliance on LD’S is simply a path to failure for timely performance.  I/D’s are designed to enhance the project LD’s and encourage contractors to view the project with high importance to the completion schedule.
 
Objectives of this Site
  • Evaluate the project need for an I/D
  • Organize the process for developing I/D's
  • Calculate the dollar range of I/D values
  • Assist the selection of the best I/D amount
  • Document the project team decisions
 
Use this link to learn more about the "Background" of this program and the "Concept of Timely Completion of Work."
 

Contacts

John Riedl
Senior Cost Engineer
503-986-3886
Lucien Darensburg
Cost Engineer Estimator & Scheduler
503-986-3760
 

Reference Materials

Primary Resources Other Resources
FHWA 1989 Guideline to I/Ds ODOT RUC Memo 10 MPH Rule
ID Research Report 2007 - SPR 630 FHWA Memo 10 MPH Rule
Specifications for Liquidated Damages The Value of Travel-Time
Guidance for Selecting the Daily I/D Unexpected Delay Cost Estimates (pdf)
Traffic Tables & Oregon State ATR Map 2007 Incident Delay Statewide (xls)
RUC Gillespie The Value of Travel-Time
 

Instructional Pages

DAP Review
The DAP Review form is provided to help document prequalification requirements and estimates for projects.  The form is prepared as a MS Word document with check boxes to answers prerequisite questions and a text holder to copy and paste data from the ID Analysis Spreadsheet. 
Information needed:
 
Total biddable dollars
Estimated % of bid $ in I/D
Estimated bid date
Estimated completion date
Highway ADT
Posted preconstruction speed
Project length in miles
If a crossover detour is needed
 
Tools:
 
DAP I/D Analysis Spreadsheet
Final Review
The purpose is to provide the second level of review at the advanced design 75% level to refine the initial assumptions for the project I/D. 
Information needed:
 
Baseline CPM Schedule
Accelerated CPM Schedule
Total biddable dollars
Dollar biddable portion in I/D
ADT
Calculated Daily RUC
Preliminary traffic control plans
 
Tools:
 
CPM Schedule Tool
Estimator Program
I/D Cost Calculator (Password Required)
Sample Specifications
PD-17 Overview
The PD-17 provides guidance and clarification on the use of Incentive/Disincentive (I/D) contracting provisions.
Tools:    PD-17 Policy  |  PD-17 I/D Suitability Checklist  |  PD-17 Flowchart
 

 