[Federal Register: July 6, 1998 (Volume 63, Number 128)] [Notices] [Page 36452-36453] From the Federal Register Online via GPO Access [wais.access.gpo.gov] [DOCID:fr06jy98-86] ======================================================================= ----------------------------------------------------------------------- NUCLEAR REGULATORY COMMISSION [Docket No. 50-461] In the Matter of Illinois Power and Clinton Power Station; Confirmatory Order Modifying License Effective Immediately I Illinois Power (IP or the Licensee) is the holder of Facility Operating License No. NPF-62, which authorizes operation of Clinton Power Station located in DeWitt County, Illinois. II The staff of the U.S. Nuclear Regulatory Commission (NRC) has been concerned that Thermo-Lag 330-1 fire barrier systems installed by licensees may not provide the level of fire endurance intended and that licensees that use Thermo-Lag 330-1 fire barriers may not be meeting regulatory requirements. During the 1992 to 1994 timeframe, the NRC staff issued Generic Letter (GL) 92-08, ``Thermo-Lag 330-1 Fire Barriers,'' and subsequent requests for additional information that requested licensees to submit plans and schedules for resolving the Thermo-Lag issue. The NRC staff has obtained and reviewed all licensees' corrective plans and schedules. The staff is concerned that some licensees may not be making adequate progress toward resolving the plant-specific issues, and that some implementation schedules may be either too tenuous or too protracted. For example, several licensees informed the NRC staff that their completion dates had slipped by 6 months to as much as 3 years. For plants that have completion action scheduled beyond 1997, the NRC staff has met with these licensees to discuss the progress of the licensees' corrective actions and the extent of licensee management attention regarding completion of Thermo- Lag corrective actions. In addition, the NRC staff discussed with licensees the possibility of accelerating their completion schedules. IP was one of the licensees with which the NRC staff held meetings. At these meetings, the NRC staff reviewed with IP the schedule of Thermo-Lag corrective actions described in the IP submittals to the NRC. Based on the information submitted by IP, and provided during the meetings, the NRC staff has concluded that the schedules presented by IP are reasonable. This conclusion is based on the (1) amount of installed Thermo-Lag, (2) the complexity of the plant-specific fire barrier configurations and issues, (3) the need to perform certain plant modifications during outages as opposed to those that can be performed while the plant is at power, and (4) integration with other significant, but unrelated issues that IP is addressing at its plant. In order to remove compensatory measures such as fire watches, it has been determined that resolution of the Thermo-Lag corrective actions by IP must be completed in accordance with current IP schedules. By letter dated May 3, 1998, the NRC staff notified IP of its plan to incorporate IP's schedule commitment into a requirement by issuance of an order and requested consent from the Licensee. By letter dated May 22, 1998, the Licensee provided its consent to issuance of a Confirmatory Order. III The Licensee's commitment as set forth in its letter of May 22, 1998, is acceptable and is necessary for the NRC to conclude that public health and safety are reasonably assured. To preclude any schedule slippage and to assure public health and safety, the NRC staff has determined that the Licensee's commitment in its May 22, 1998, letter be confirmed by this Order. The Licensee has agreed to this action. Based on the above, and the Licensee's consent, this Order is immediately effective upon issuance. IV Accordingly, pursuant to sections 103, 161b, 161i, 161o, 182, and 186 of the Atomic Energy Act of 1954, as amended, and the Commission's regulations in 10 CFR 2.202 and 10 CFR Part 50, It is hereby ordered, effective immediately, that: Illinois Power (IP) complete final implementation of Thermo-Lag 330-1 fire barrier corrective actions at Clinton Power Station as described in the June 19, 1997, and March 30, 1998, submittals to the NRC, in addition to the repair of the butt joint described in the March 28, 1995, submittal to the NRC, by December 31, 1998. The Director, Office of Nuclear Reactor Regulation, may relax or rescind, in writing, any provisions of this Confirmatory Order upon a showing by the Licensee of good cause. V Any person adversely affected by this Confirmatory Order, other than the Licensee, may request a hearing within 20 days of its issuance. Where good cause is shown, consideration will be given to extending the time to request a hearing. A request for extension of time must be made in writing to the Director, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and include a statement of good cause for the extension. Any request for a hearing shall be submitted to the Secretary, U.S. Nuclear Regulatory Commission, Attention: Docketing and Services Section, Washington, DC 20555. Copies of the hearing request shall also be sent to the Director, Office of Nuclear Reactor Regulation, U. S. Nuclear Regulatory Commission, Washington, DC 20555, to the Deputy Assistant General Counsel for Enforcement at the same address, to the Regional Administrator, NRC Region III, 801 Warrenville Road, Lisle, IL 60532- 4351, and to the Licensee. If such a person requests a hearing, that person shall set forth with particularity the manner in which his/her interest is adversely affected by this Order and shall address criteria set forth in 10 CFR 2.714(d). If a hearing is requested by a person whose interest is adversely affected, the Commission will issue an Order designating the time and place of any such hearing. If a hearing is held, the issue to be considered at such hearing shall be whether this Confirmatory Order should be sustained. In the absence of any request for hearing, or written approval of an extension of time in which to request a hearing, the provisions specified in Section IV above shall be final 20 days from the date of this Order without further order or proceedings. If an extension of time for requesting a hearing has been approved, the provisions specified in Section IV shall [[Page 36453]] be final when the extension expires if a hearing request has not been received. An answer or a request for hearing shall not stay the immediate effectiveness of this Order. For the Nuclear Regulatory Commission. Dated at Rockville, Maryland this 26th day of June 1998. Samuel J. Collins, Director, Office of Nuclear Reactor Regulation. [FR Doc. 98-17773 Filed 7-2-98; 8:45 am] BILLING CODE 7590-01-P