[Federal Register: June 21, 2002 (Volume 67, Number 120)]
[Notices]               
[Page 42250]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr21jn02-56]                         

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP02-385-000]

 
Williams Gas Pipelines Central, Inc.; Notice of Request Under 
Blanket Authorization

June 17, 2002.
    Take notice that on June 10, 2002, Williams Gas Pipelines Central, 
Inc. (Williams), P.O. Box 20008, Owensboro, Kentucky 42304, filed in 
Docket No. CP02-385-000 a request pursuant to Sections 157.205 and 
157.211(b) of the Commission's Regulations under the Natural Gas Act 
(18 CFR 157.205, 157.211(b)) for authorization to construct and operate 
13 miles of 30-inch and 24-inch pipeline and a 12-inch delivery meter 
station with appurtenant facilities located in Oklahoma County, 
Oklahoma, under Williams's blanket certificate issued in Docket No. 
CP82-479-000 pursuant to Section 7(c) of the Natural Gas Act, all as 
more fully set forth in the request.
    Copies of this filing are on file with the Commission and are 
available for public inspection. This filing may also be viewed on the 
web at http://www.ferc.gov using the ``Rims'' link, select 
``Docket'' and follow the instructions (call 202-208-2222 for 
assistance).
    Williams requests authorization to construct and operate the 
facilities to serve Redbud Energy, LP (Redbud). Williams states that it 
would use the facilities to transport up to 51,980 MMBtu equivalent of 
natural gas per day. Williams estimates the cost of the facilities to 
be $13,008,000. Williams states further that the proposal would have no 
significant effect on Williams' peak day and annual deliveries, and 
service to Redbud through the new delivery point would be accomplished 
without detriment to Williams' other existing customers.
    Any questions regarding the application should be directed to David 
N. Roberts, Manager of Certificates and Tarriffs, at: (713) 853-6549, 
Williams Gas Pipelines Central, Inc., P.O. Box 20009, Owensboro, 
Kentucky 42304.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and, pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205), a protest 
to the request. If no protest is filed within the time allowed 
therefor, the proposed activity shall be deemed to be authorized 
effective the day after the time allowed for filing a protest. If a 
protest is filed and not withdrawn within 30 days after the allowed for 
filing a protest, the instant request shall be treated as an 
application for authorization pursuant to section 7 of the Natural Gas 
Act.
    Comments, protests and interventions may be filed electronically 
via the Internet in lieu of paper. See, 18 CFR385.2001(a)(1)(iii) and 
the instructions on the Commission's web site under the ``e-filing'' 
link.

Linwood A. Watson, Jr.,
Deputy Secretary.
[FR Doc. 02-15687 Filed 6-20-02; 8:45 am]
BILLING CODE 6717-01-P