[Federal Register: August 14, 2002 (Volume 67, Number 157)]
[Notices]
[Page 52965]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr14au02-86]
[[Page 52965]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL00-95-000, EL00-98-000 and ER02-1656-000]
San Diego Gas & Electric Company, Complainant, v. Sellers of
Energy and Ancillary Services Into Markets Operated by the California
Independent System Operator and the California Power Exchange,
Respondents, Investigation of Practices of the California Independent
System Operator and the California Power Exchange, and California
Independent System Operator (MD02); Amended Notice of Technical
Conference and Agenda
August 8, 2002.
The Federal Energy Regulatory Commission Staff is convening a
technical conference to facilitate continued discussions between the
California Independent System Operator Corporation (CAISO), market
participants, state agencies and other interested participants on the
development of a revised market design for the CAISO. Attached is the
proposed agenda for the conference. The conference will be held in San
Francisco, California, at the Renaissance Parc 55 Hotel, 55 Cyril
Magnin Street, San Francisco, CA, on August 13, 14 and 15, 2002,
beginning at 9 a.m.
For additional information concerning the conference, interested
persons may contact Susan G. Pollonais at (202) 502-6011 or by
electronic mail at ``susan.pollonais@ferc.gov.'' No telephone
communication bridge will be provided at this technical conference.
Linwood A. Watson, Jr.,
Deputy Secretary.
Discussion Issues for FERC Technical Conference on California Market
Design (MD02), August 13-15, 2002
1. Introduction and Statement of Goals for Technical Conference
2. Overview and Discussion on Forthcoming Process
a. Short-term Issues--Process for Resolving Issues Related to
Phase II
b. Long-term Issues--Process for Resolving Issues Related to
Phase III
3. Standard Market Design (SMD) Overview
a. Market Power Mitigation b. Day-Ahead and Real-Time Markets
c. Resource Adequacy
d. Congestion Revenue Rights (CRRs)
4. Implementation Issues and Milestones
a. Introduction--Overview of FERC Directives
b. Phase IA
i. Status Report on Development of Automatic Mitigation
Procedures(AMP)
ii. Status Report on RFP for Independent Entity to Develop AMP
Reference Prices
c. Phase IB
i. Status Report on Implementation of Real-Time
EconomicDispatch/Deviation Penalties (enhanced Scheduling Logging
for the ISO of California (SLIC))
d. Phase 2
i. Update on Implementation Requirements and Timeline
ii. Issues:
Integrated Forward Markets and Simultaneous
Optimization
Residual Unit Commitment
Financial v. Physical Forward Schedules
e. Phase III (including Locational Marginal Pricing (LMP) and
CRRs)
i. Update on Implementation Timeline
ii. Issues:
Network Model and State Estimator MP and Optimal Power
Flow (OPF)
CRRs
Financial v. Physical Foward Schedules
5. California ISO Market Surveillance Committee--Opinion and Comment
6. Next Steps/Future Conferences
[FR Doc. 02-20543 Filed 8-13-02; 8:45 am]
BILLING CODE 6717-01-P